Resolved
AGREED – That the be approved.
Governance and Audit Committee agreed this item on Thursday 28 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED – That the be approved.
To approve the Wrexham Internal Audit Charter for 2019-20.
2. INTRODUCTION
2.1Wrexham County Borough Council’s (WCBC’s) Internal Audit function is provided by Wrexham Internal Audit Services (WIAS).
2.2Since 1 April 2013, WIAS has operated under the framework provided by the Public Sector Internal Audit Standards (PSIAS).
2.3The Internal Audit Charter 2019-20 (the Charter) defines WIAS’s purpose, authority and responsibility in terms consistent with the PSIAS’s Mission Statement, the Core Principles of Internal Audit, the Code of Ethics and the PSIAS.
2.4The PSIAS requires the Charter to be reviewed annually by the Senior Leadership Team (SLT) and Members. The Charter was submitted to SLT on 27 March 2019.
2.5The Charter includes the Internal Audit Plan 2019-20 (Charter, Appendix A1) which details the planned audit assignments, their respective priorities and the estimated number of days to complete each audit. It also links each audit to the Council Plan.
2.6The Audit Committee will receive regular update reports of progress against the Internal Audit Plan and any material variances will be highlighted within those reports.
That the Internal Audit Charter 2019-20 is approved. REASON FOR RECOMMENDATION 3.1 To meet Standard 2020 - Communication and Approval of the PSIAS. This states that the internal audit activity’s plans and resource requirements, including significant interim changes, should be communicated to senior management for review and to the Audit Committee for approval.
4. BACKGROUND INFORMATION
Internal Audit Charter 2019-20
4.1There are no significant changes from the Internal Audit Charter 2018-19 – the changes that have been made relate to:
a) Changes in job titles as a result of the Senior Management restructure e. g. Heads of Department to Chief Officers;
b) Paragraph 8.2 - The removal of the reserve list of audits from the Internal Audit Plan because of the low likelihood of any of these audits being carried out in 2019-20; Highlighted in Blue.
c) Para 9.1 - The change from the “Green / Amber level of assurance “Amber” level of assurance. No other changes are proposed to the descriptions or boundaries between the different levels of assurance. Highlighted in Red.
d) References to the “internal audit activity” and “internal audit” being replaced by Wrexham Internal Audit Services (WIAS).
Internal Audit Plan 2019-20
4.2In accordance with the PSIAS, a risk-based approach has been used taking account of the Council’s risk and control registers as well as Internal Audit’s own assessment of WCBC’s financial and governance risks. In addition, the draft plan takes account of the governance framework and the strategic planning framework.
4.3As Internal Audit seeks to become more responsive to Members’ and managers’ expectations, the draft plan aims to find the right balance between providing assurance and offering advice and assistance in matters relating to internal control, governance and risk management.
4.4The Plan includes a high level of contingency for unplanned work to reflect the need to respond to changing priorities.
4.5All Heads of Departments as well as the Chief Executive have been consulted on the audits to be included in the Plan. The Wales Audit Office’s Financial Audit Manager for Wrexham CBC has also been consulted regarding the coverage of key financial systems.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HF2519: Appendix 2Appendix | 8 KB | Download |
PDF |
HF2519 Internal Audit Charter 2019: Appendix 1Appendix | 1.2 MB | Download |
PDF |
Internal Audit Charter 2019-20Report | 83 KB | DownloadRead as text |
Follow Governance and Audit Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Confirmation of MinutesRESOLVED – That the Minutes of the meeting held on 18 June 2026 be signed as a correct record. | Decided | Open |
| 16 Jul 2026 | Terms of ReferenceRESOLVED – That the Governance and Audit Committee Terms of Reference be noted. | Noted | Open |
| 16 Jul 2026 | External Regulation & Inspection - Assurance re:implementation of recommendations- That members of GAC noted the progress made with the implementation of actins in response to the external regulatio... | Noted | Open |
| 16 Jul 2026 | Audit Wales Annual Audit Plan 2024-25- That the Audit Wales Annual Audit Plan 2024-25 be noted. | Noted | Open |
| 16 Jul 2026 | Audit Wales Performance Audit Plan 2026-27'- That the Audit Wales Performance Audit Plan 2026-27 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.