RESOLVED - That the Audit Committee notes the contents of the Risk and Control Register extracts, and considers any matter that may need to be considered for inclusion in the Annual Governance Statement and/or that should be considered for audit coverage.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To highlight the Council‟s significant risks that have been identified and how they are being managed, and to enable the Audit Committee to consider any matters that may need to be considered for inclusion in the Annual Governance Statement and / or that should be considered for audit coverage.
Executive summary
2.1The Council‟s Risk Management Policy requires formal arrangements for managing strategic and operational risks. These include the identification and prioritisation of risks on a consistent basis and their recording in registers along with the key controls required to mitigate the risks.
2.2Risk and Control Registers are kept for the Council‟s principal risks and for each department. This report provides summary details of these registers as at 24 January 2020. Details in respect of “subsidiary Risk and Control registers” e.g. counter fraud will be added to future Risk and Control registers. 3 RECOMMENDATION
3.1That the Audit Committee notes the contents of the attached risk and control register extracts, and considers any matters that may need to be considered for inclusion in the Annual Governance Statement and / or that should be considered for audit coverage.
Reason for recommendation
To enable the Committee to fulfil its Statement of Purpose, as set out in the constitution, “to provide independent assurance to Full Council and management of the adequacy of the risk management framework and the internal control environment” and to discharge its specific function to “monitor the effective development and operation of risk management in the council”.
4. BACKGROUND INFORMATION
4.1For the purposes of the Council‟s Risk Management Policy, „risks‟ are possible events which, were they to happen, could negatively impact the Council‟s objectives, aims, values, responsibilities and reputation.
4.2The Policy requires significant risks to be identified and assessed objectively and on a consistent basis across the Council. The agreed Scoring Matrix (Appendix A) helps to achieve this, combining assessments of likelihood and impact.
4.3Identified risks and the controls that mitigate them are recorded in risk and control registers. These are required for:
(i) the Principal risks to the Council, (ii) all departments, (iii) major projects.
4.4This report provides extracts from (i) and (ii), as at 24 January 2020. It should be noted that this date is a „snapshot in time‟ and that updates may have been made since then. Details in respect of “subsidiary Risk and Control registers” e.g. counter fraud will be added to future Risk and Control registers when they are reviewed. This was supported by Senior Leadership Team.
4.5The report should enable the Audit Committee to seek assurance or, if necessary, challenge the management of risks. This could include seeking assurance that:
(i) significant or emerging risks have been identified and accurately assessed, (ii) the risks are subject to effective mitigation (control). 4.6 The risks in projects are the responsibility of project managers and / or Chief Officers (COs) and are not coordinated or routinely monitored centrally. Where necessary however, COs should include or take account of any such significant risks in departmental registers.
4.7The management of the risk and control registers‟ contents is the responsibility of COs. The role of the central risk management function that of coordination, support and oversight.
4.8The reasons for the Council‟s risk management arrangements and how they are operated is reported to the Audit Committee separately in an annual report. The last such report was received by the Committee on 19 December 2019.
4.9Further information on risk management is provided on the Intranet (SAM).
Principal Risks (Appendix B) 4.10 The Principal Risk Register should describe the longer term strategic risks to the Council achieving its priorities and outcomes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.