RESOLVED – That permission be GRANTED in accordance with the recommendation of the Chief Officer Planning and Regulatory as set out in report (COPR/03/20) subject to Section 106 Obligation. Note to Applicant You are advised to give consideration to the use of a barrier to prevent vehicular access onto the premises during non-opening hours.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
REPORT OF THE CHIEF OFFICER PLANNING AND REGULATORY Date 2nd March 2020
APPLICATION NO: LOCATION: DATE RECEIVED: P/2018 /0675 DIVISIONAL POLICE 10/08/2018 HEADQUARTERS BODHYFRYD WREXHAM COMMUNITY: LL12 7BW CASE OFFICER: Acton PF DESCRIPTION: ERECTION OF CLASS A1 RETAIL WARD: STORE AND CLASS A1/A3 DRIVE- AGENT NAME: Maesydre THROUGH COFFEE SHOP WITH PLAN A (NORTH WEST) CAR PARKING AND SERVICING LIMITED AREAS, ACCESS, LANDSCAPING MR CHRIS SMITH AND ASSOCIATED WORKS INCLUDING RELOCATION OF ELECTRICITY SUB-STATION, FOLLOWING DEMOLITION OF EXISTING BUILDINGS AND STRUCTURES
APPLICANT(S) NAME: MR D BRYAN LIDL UK GMBH
______________________________________________________________ P/2018/0675 Background: Members will recall that this planning application was deferred from consideration by the Planning Committee in September following a request by the Highways Engineer to give further consideration to an objection received from consultants acting on behalf of the neighbouring Asda Supermarket. That objection was summarised in the main report and accompanying addendum, but for clarity these are repeated below. - Amended highway report was submitted 8 months ago leaving only a limited amount of time for neighbouring occupiers to assess the information;
- Queue modelling at the proposed site access and the impact of the development upon the safe operation of the existing roundabout and the neighbouring roundabouts;
- Accident data should be reviewed for a period of 5 years at the site access and surrounding roundabouts;
- Unrestricted delivery timings may cause on site conflicts to the detriment of pedestrian and highway safety;
- Trip generations should be reassessed against locations which are more representative of the location of the proposed development; REPORT OF THE CHIEF OFFICER PLANNING AND REGULATORY Date 2nd March 2020
- Operation assessments should be validated against observed queue lengths so the council can have confidence in the likely impact of the development on the highway network; and
- The application should be removed from consideration until such time that these matters can be adequately addressed.
In response to this, the applicant has sought to address those concerns raised by providing two further responses to the objection raised and to reassure the local highway authority. This has taken the form of a rebuttal by the applicant’s own transport consultants to the concerns raised.
Observations: The response of the applicant’s highways consultant has been assessed by the council’s highways section.
In terms of overall traffic generation, the overall increase in traffic movements is identified as less than 5% which is not considered significant in development terms. In terms of the concerns raised by Asda’s representation concerning validation of queue lengths and therefore the suitability of the model, these are based upon the comparison of maximum queue lengths against averages over a modelled period. The revised information provided by the applicant provides a comparison of observed and modelled queue lengths. This does demonstrate a reasonable correlation between observed and modelled and hence mitigates some of the concerns raised in terms of the validity of the model used. The revised report does also demonstrate that in terms of overall capacity of the junction, the junction continues to operate with theoretical capacity in 2023 with forecast growth and development traffic.
Ecology: The applicant has subsequently submitted an ecological assessment of the building to be demolished given its method of construction. The building does have the possibility of providing habitat for bats and because of this, to ensure that any potential presence is identified, and a suitable scheme of mitigation demonstrated, a further detailed survey shall be carried out prior to any demolition works. This can be imposed by planning condition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.