Wrexham County Borough Council
Executive Board, Tuesday 9 March 2021 at 10.00am

Wrexham Gateway Delivery Plan

Agreed Executive

Executive Board agreed this item on Tuesday 9 March 2021. Below is the council's own wording, with the papers it was decided on.

Item211

Resolved

RESOLVED - ( i ) That the revised LCR Wrexham Gateway Masterplan and feasibility study findings be endorsed as the overarching framework which will guide the delivery of a mixed use development site at this key gateway to Wrexham Town Centre, (subject to planning). (ii) That the Chief Officer Housing and Economy (in consultation with the Lead Member for Organisation – Finance, Performance, Health & Safety and Governance), be authorised to continue with the development of this project which will include working with partners on the commissioning of specialist external support to develop the delivery plan. (iii) That the Chief Officer Finance & ICT identify an additional £50,000, towards the cost of funding the delivery phase of the project, which may include the appointment of a project delivery partner/project manager. (iv) That the Chief Officer Finance & ICT be authorised to consider and agree appropriate due diligence on the benefits and liabilities of the acquisition of land within the red line boundary of the project area, in order to secure public ownership and to provide the Council with a tangible stake in the future regeneration of the Wrexham Gateway. (v) That the Chief Executive be authorised to engage with all relevant parties which have a direct interest in the red line boundary of the Gateway. (vi) That the Chief Officer Finance & ICT (in consultation with the Lead Member for Organisation – Finance, Performance, Health & Safety and Governance), be authorised to consider finance arrangements with the Welsh Government and to agree and accept terms subject to consultation with the Chief Officer Governance and Customer. (vii) That the Chief Officer Housing & Economy (in consultation with Chief Officer Planning and Regulatory, Chief Officer Governance and Customer and the Lead Member for Organisation – Finance, Performance, Health & Safety and Governance) be authorised to update current legal agreements with the Wrexham Gateway Partnership in light of new financial arrangements and conditions associated in order to deliver specifically agreed regeneration activity through the Wrexham Gateway Feasibility Masterplan, including the possible use of compulsory purchase powers and land acquisition. Reasons for decisions ( i ) To support the revised the Wrexham Gateway Feasibility Masterplan. (ii) To approve revenue funding to part fund further works required for the development of a delivery plan. (iii) To enable further work to be undertaken to ascertain the viability of land acquisition within the red line boundary of the Gateway
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

9 of 23 attended
YC
Y Cynghorydd Andrew AtkinsonCommittee Member, present
YC
Y Cynghorydd David A BithellVice-Chair, present
YC
Y Cynghorydd Terry EvansCommittee Member, apologies
YC
Y Cynghorydd D J GriffithsCommittee Member, present
YC
Y Cynghorydd Hugh JonesCommittee Member, present
YC
Y Cynghorydd David KellyCommittee Member, present
YC
Y Cynghorydd Joan LoweCommittee Member, present
YC
Y Cynghorydd John PritchardCommittee Member, present
YC
Y Cynghorydd Mark PritchardChair, present
YC
Y Cynghorydd Phil WynnCommittee Member, present
YC
Y Cynghorydd Bryan ApsleyGuest, in attendance
YC
Y Cynghorydd Trevor BatesGuest, in attendance

All 23 on the meeting page

On this subject at Wrexham

Search all
  1. Wrexham Gateway Delivery PlanThis decision
  2. Wrexham Museum: Regent Street Gateway Corridor – Coach parkingAgreed
  3. Wrexham Gateway - Project DeliveryApproved
  4. Wrexham Gateway – Land AssemblyApproved
  5. Wrexham Gateway – Relocation of Scouts and GuidesApproved
  6. Wrexham Gateway Delivery PlanAgreed

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies