HSE audit of the WCBC Health and Safety Policy (2019) - Update report

Noted Executive 2 papers

Executive Board noted this item on Tuesday 8 March 2022. Below is the council's own wording, with the papers it was decided on.

Item102

Resolved

RESOLVED - That the report be noted. Reason for decision To demonstrate compliance with the requirements of important health and safety legislation and internal governance requirements.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

1.1To provide an update on the progress on the findings of an audit of the Health and Safety Policy of Wrexham County Borough Council, carried out by the Health and Safety Executive in partnership with Wrexham County Borough Council between September 2018 and June 2019.

Executive summary

2.1The Health and Safety Executive (HSE) undertook an audit of the Councils Health & Safety Policy (H&SP), in partnership with Wrexham County Borough Council (WCBC), between September 2018 and June 2019.

2.2The purpose of the HSE’s audit was to “inspect WCBC against its own health and safety policy to verify compliance with the health and safety policy by WCBC employees at all levels as well as relevant legislation”.

2.3Further details of the report and actions taken are in Appendix 1 and 2.

2.4We are satisfied that sufficient progress has been made in delivering on actions highlighted in Appendix 1, and that this is a significant achievement. There is still some further work to do as well as ongoing actions identified to ensure that this progress to date is maintained.

1 2.5. We are confident that if HSE visited next week, that there would be no repeat of the findings of the audit conducted in 2019.

2.6The HSE advised that it intended to work with WCBC to ensure that actions were addressed, monitoring progress with a view to completion in the next 24 months. This was to be supported by a revisit of the HSE in June 2021

2.7This anticipated HSE June 2021 visit has not occurred, due to the covid-19 pandemic which has altered their plans for a return.

2.8As the 2021 HSE visit had not occurred, an extensive audit of the findings (25 in number) has been undertaken by the Council’s Corporate Health & Safety (CH&S) team, to review the current position 24 months since the HSE presented their audit findings to the Council, ensuring that there has been the required progress with the deficiencies identified by the HSE in 2019.

2.9Summary Timeline:

 September 2018 - June 2019, HSE/WCBC- audit of the Councils Health & Safety Policy  17 June 2019 - The HSE presented their draft report to the Leader of the Council, the Chief Executive and the Chief Officer Finance & ICT  25 June 2019 - The HSE issued the final report and a Notice of Contravention letter  June 2021 The anticipated HSE visit did not occur, due to the covid-19 pandemic which has altered their plans for a return  May– August 2021 – Corporate Health & Safety (CH&S), first audit of the HSE Contraventions Report Findings  August 2021 – CH&S Audit Action Plan showing the status of the work on the actions to date  January 2022 – Review of the current status of 25 action areas.

Recommendations

3.1That the Executive Board endorse the contents of the report and the positive progress to date by both Corporate Health and Safety and the service departments

Reasons for recommendations

(i) To demonstrate compliance with the requirements of important health and safety legislation and internal governance requirements.

2 4. BACKGROUND INFORMATION

4.1The Health and Safety Executive (HSE) undertook an audit of the Councils Health & Safety Policy (H&SP), in partnership with Wrexham County Borough Council (WCBC), between September 2018 and June 2019.

4.2The purpose of the HSE’s audit was to “inspect WCBC against its own health and safety policy to verify compliance with the health and safety policy by WCBC employees at all levels as well as relevant legislation”.

4.3The HSE presented their draft report to the Leader of the Council, the Chief Executive and the Chief Officer Finance & ICT on 17 June 2019.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 3Appendix 3 9 KB Download
PDF
HSE audit of the WCBC Health and Safety Policy (2019): Update reportReport 825 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 20 attended
YC
Y Cynghorydd David A BithellVice-Chair, present
YC
Y Cynghorydd Sonia Benbow-JonesCommittee Member, present
YC
Y Cynghorydd Terry EvansCommittee Member, present
YC
Y Cynghorydd D J GriffithsCommittee Member, present
YC
Y Cynghorydd Hugh JonesCommittee Member, present
YC
Y Cynghorydd David KellyCommittee Member, present
YC
Y Cynghorydd Beverley Parry-JonesCommittee Member, present
YC
Y Cynghorydd John PritchardCommittee Member, present
YC
Y Cynghorydd Mark PritchardChair, present
YC
Y Cynghorydd Phil WynnCommittee Member, present
YC
Y Cynghorydd Trevor BatesGuest, in attendance
YC
Y Cynghorydd Dana DaviesGuest, in attendance

All 20 on the meeting page

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies