RESOLVED – That a SITE VISIT be arranged for Members of the Committee to view the application site prior to determination of the application by the Committee. Reason for Visit: To consider the effects of the proposal on the local environment and highway infrastructure.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
REPORT OF THE CHIEF OFFICER ECONOMY AND PLANNING – 3 OCTOBER 2022
APPLICATION NO: LOCATION: DATE RECEIVED: P/2022 /0448 BALLSWOOD QUARRY GEGIN 06/05/2022 LANE LLAY WREXHAM LL12 0NU COMMUNITY: CASE OFFICER: Llay DESCRIPTION: FL2 ESTYNIAD I’R ARDALOEDD ECHDYNNU O FEWN FFIN WARD: BRESENNOL Y CHWAREL A AGENT NAME: Llay GANIATEIR / EXTENSION TO THE MR ROBIN SMITHYMAN EXTRACTION AREAS WITHIN THE EXISTING PERMITTED QUARRY BOUNDARY
THE SITE Ballswood Quarry is situated approximately 4 km north of Wrexham, on the eastern edge of the village of Llay. The Quarry has access onto the A483 at its junction with the B5102, some 1.5 km north-east of the quarry. Access is gained on to the B5102 along a short stretch of an unclassified road, Gegin Lane.
PROPOSAL REPORT OF THE CHIEF OFFICER ECONOMY AND PLANNING – 3 OCTOBER 2022
The proposal relates to a proposed extension of Ballswood Quarry, an active sand and gravel quarry located on the eastern edge of the village of Llay.
Existing Site Plan
The application as submitted, initially involved a lateral extension of the quarry in two locations labelled Areas A, to the north east of the existing quarry site, and Area B to the west. Both areas proposed are within the existing extant red line boundary of the quarry.
During the consideration of the application, the applicant has amended the proposed plans, and now the proposed development only involves the extension to the quarry in Area A. The proposal does not involve the extraction of mineral in the Area B as shown on the plan below. REPORT OF THE CHIEF OFFICER ECONOMY AND PLANNING – 3 OCTOBER 2022
Proposed Site Plan
Area A comprises a 4.37 hectare site to the north east of the existing approved limit of extraction, which would release a total of 500,000 tonnes of mineral resource which would effectively provide for an extension to the existing permitted area. Area A lies within the existing extant planning permission boundary but outside of the permitted extraction limit and is currently agricultural land.
The proposed restoration involves the site being restored to primarily agriculturally managed grassland on Area A, with blocks of existing and proposed woodland (proposed to progressively plant 13,200 trees), areas of wet/marshy habitat, willow planting and natural regeneration on the wider quarry site, as shown on the restoration concept plan below. REPORT OF THE CHIEF OFFICER ECONOMY AND PLANNING – 3 OCTOBER 2022
Proposed Restoration Plan
The proposal does not involve any changes to the method of winning and working of minerals at Ballswood Quarry, and would be worked dry, above the water table. The application proposes a continuation of sand and gravel extraction from the site. At the current rate of extraction, it is expected that this area would be worked within less than two years, with a further year to complete the proposed restoration. The current consent has a condition imposed to allow the winning and working of mineral until 22 February 2042. The proposal does not propose changes to the methods of quarrying at Ballswood Quarry, which would continue to be within the permitted application boundary and would be completed well within the approved end date of mineral working at the quarry.
Hours of operation would remain as 0700-1800 hours Monday – Friday, 0730- 1300 hours Saturday, with no operations to be undertaken outside these hours, or on any Sunday, Bank or Public Holiday, as per consented hours of operation.
HISTORY
There is a long history of winning and working of sand and gravel at Ballswood Quarry. Following the inception of the modern planning system in 1948 permission was first granted for the ‘Continuation of Sand and Gravel Workings’ on the 10th of March 1953, and then subsequently on the 11th of February 1954. REPORT OF THE CHIEF OFFICER ECONOMY AND PLANNING – 3 OCTOBER 2022
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.