Wrexham Gateway – Delivery of LUF Projects

Agreed Executive

Executive Board agreed this item on Tuesday 18 April 2023. Below is the council's own wording, with the papers it was decided on.

Item126

Resolved

RESOLVED – (i) That the Chief Officer for Finance & ICT be authorised to allocate £17.83m of existing Gateway funding, within the Capital Programme, for the Racecourse Stadium development including the Kop stand and that the balance of the £25m funding available be used for Wrexham Gateway project costs including the car parking deck and land exchanges. (ii) That the Chief Officer for Governance and Customer be authorised to enter into a Grant Agreement and Legal Charge (to secure grant funding) to give effect to the agreed Heads of Terms annexed at Appendix 4 of report COEP/31/23. (iii) That the Chief Officer for Economy and Planning be authorised to commence to prioritise delivery of the projects in full and as per the design intent for the LUF bid to ensure full realisation of the benefits identified. (iv) That the Chief Officer Finance & ICT be authorised to earmark resources within the 2023/2024 cash-limited budget to provide a guarantee (up to a maximum of £8m) to underwrite the sourcing of replacement external capital funding to deliver regeneration objectives within the wider Wrexham Gateway project. (v) That the Chief Officer for Economy and Planning be authorised to enter into a Legal Agreement with Wrexham AFC and FA Wales to agree a programme of international fixtures and major events to be hosted at the Racecourse Stadium on an annual basis. (vi) That the Chief Officer Housing be authorised to agree the value of any land exchanges that are deemed essential to deliver the west side scheme with these costs to come out of the balance of the £25m funding available. (vii) That the matter be dealt with as an urgent item of business in accordance with Section 5 (rule 5.8.10(m)) of the Constitution. Reasons for decisions (i) To enable the delivery of the Wrexham Gateway development; (ii) To ensure appropriate risk management is undertaken. (iii) To ensure project delivery can proceed with legal agreements in place by the end of April.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

9 of 25 attended
YC
Y Cynghorydd David A BithellVice-Chair, present
YC
Y Cynghorydd Terry EvansCommittee Member, present
YC
Y Cynghorydd Hugh JonesCommittee Member, present
YC
Y Cynghorydd Beverley Parry-JonesCommittee Member, apologies
YC
Y Cynghorydd John PritchardCommittee Member, present
YC
Y Cynghorydd Mark PritchardChair, present
YC
Y Cynghorydd Paul RobertsCommittee Member, present
YC
Y Cynghorydd Robert WalshCommittee Member, present
YC
Y Cynghorydd Nigel WilliamsCommittee Member, present
YC
Y Cynghorydd Phil WynnCommittee Member, present
YC
Y Cynghorydd Bryan ApsleyGuest, in attendance
YC
Y Cynghorydd Brian CameronGuest, in attendance

All 25 on the meeting page

On this subject at Wrexham

Search all
  1. Wrexham Gateway – Delivery of LUF ProjectsThis decision
  2. Wrexham Museum: Regent Street Gateway Corridor – Coach parkingAgreed
  3. Wrexham Gateway - Project DeliveryApproved
  4. Wrexham Gateway – Land AssemblyApproved
  5. Wrexham Gateway – Relocation of Scouts and GuidesApproved
  6. Wrexham Gateway Delivery PlanAgreed

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies