RESOLVED – That th e commissioning of a feasibility study to explore and make recommendations on the future use of the site with a consideration for social housing be approved. Reason for decision To provide Members with a clear and transparent review of the potential future uses of the whol e of the site, which could include a provision for much needed social housing.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To seek Members’ agreement to commission a feasibility study to demonstrate the future potential uses for the Rhosddu Road site, to include vacant land (at the site of the former Centre 67), Greenacres, the Cunliffe Centre and Springfield Sheltered Accommodation.
Executive summary
2.1Following the relocation of Social Care staff to Crown Buildings, the demolition of Centre 67 in late 2022 and Adult Services’ desire to provide a modern, purpose built facility for their service users to replace the existing Cunliffe Centre and in line with the Sheltered Housing Refurbishment Programme, it has been identified that the land at Rhosddu Road (owned by WCBC) will be surplus to requirement in the future
2.2This land is well situated in relation to the City Centre and the services it offers as well as the close proximity to and also to sustainable transport links
Recommendations
The Executive Board is recommended to approve:
3.1the commissioning of a feasibility study to explore and make recommendations on the future use of the Rhosddu Road site with a consideration for social housing. REASONS FOR RECOMMENDATIONS
(i) To provide Members with a clear and transparent review of the potential future uses of the whole of the site, which could include a provision for much needed social housing.
BACKGROUND INFORMATION
4.1The extent of the land proposed for inclusion within the Feasibility Study commission can be seen in Appendix 1 (attached).
4.2As part of the office accommodation review, following the Covid 19 Pandemic and a shift to Modern Ways of Working, the Social Care staff based at Greenacres have now relocated to a permanent office base at Crown Buildings. The small Emergency Duty Team who remain based at Greenacres, are currently working with the Assets Team to identify an alternative, permanent 24 hour accessible office base.
4.3The Cunliffe Centre requires modernisation. The Senior Management responsible for the service are currently working with the Assets Team to consider options for the development of a purpose built facility, which will provide the modern, specialist accommodation to meet the needs of service users both now and in the future .
4.4Centre 67 was vacated by the Council in 2005. There were significant issues identified at the time in terms of both DDA compliance and energy efficiency (EPC Grade G) that made continued use unviable. A proposal to demolish Centre 67 was considered by the Corporate Land & Buildings Working Group on 7 February 2012 (Report No. HAED/06/12), prior to this recommendation being presented to the Executive Board on 21 February 2012 (Report No. HAED/08/12), where it was resolved accordingly.
4.5A series of Executive Board Reports followed on 12 June 2012 (Report No. HAED/23/12), 14 May 2013 (Report No. HAED/29/13) and 21 October 2014 (Report No. HAED/43/14).
4.6On 14 January 2020, a recommendation was agreed by the Executive Board to commence the demolition of Centre 67 and this has now been undertaken.
4.7Springfield Sheltered Housing Scheme currently occupies part of the land incorporated for consideration. It is made up of 41 properties (19 bedsits, 19 one bedroom flats and 4 two bedroom flats), in a three storey building that was constructed in 1970.
5. IMPLICATIONS
5.1Policy Framework – organisational priorities as outlined in the Council Plan 2020- 2023 provide further strategic context to delivering a prosperous ambitious place. Wrexham’s ambition for economic prosperity and growth and the Placemaking vision, Housing Revenue Business Plan, Adult Protection Policy, the Tackling Poverty Strategy and the Well-being Plan
5.2Budget – HRA has identified future funding of £9 million over the next 3 years to support the development of new social housing. This is made up of an allocation of £1 million in 2023/24, £4 million in 2024/25 and £4 million in 2025/26 5.3 Legal – No direct impacts
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.