Item38
Resolved
RESOLVED – (i) That the Chief Officer Economy & Planning (in consultation with the Lead Member for Organisation – Finance & Performance), be authorised to continue with the development of this project as outlined in 2.7 table 1 of report COEP/52/23 before RIBA stage 3, and agree that Officer time is provided from the Council’s Regeneration Team to achieve the project aims. (ii) Following the development work in table 1 2.7 there will be a clear pause to allow us to assess the viability of this project in order to make an informed decision to invest in RIBA Stage 3. We will present this back to the Executive Board for full consideration. (iii) That a public consultation exercise be undertaken on the options for the re-development and future use of . Reason for decisions (i) To support the Wrexham Memorial Hall Project (ii) To allow further work to be undertaken to ascertain the viability of this project.
Word for word from the decision Wrexham published for this meeting.
Source: moderngov.wrexham.gov.uk