RESOLVED – That Officers are given delegated authority for permission to GRANT in accordance with the recommendation of the Chief Officer Economy and Planning. Note Case Officer to ensure the Local Member and the two Local Members for the adjoining wards (Cllrs Rondo Roberts and Derek Wright) are notified when additional information is submitted .
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
The Chief Officer Economy and Planning be given delegated authority to grant planning permission subject to:
The submission of additional ecology surveys; Consultation responses being received from statutory consultees confirming no objection, either with or without suitably worded conditions being imposed; The HSE being notified of the Council’s intention to grant planning permission and given 21 days to decide whether to request the application be ‘called in’ for determination by Welsh Ministers; Additional information being submitted in response to comments/concerns raised by statutory consultees; and A schedule of suitably worded conditions.
Officer Report
Site Description
The application site is part of the a larger area of land formerly occupied by Flexys, which is largely derelict and comprises of areas of hard surfacing, as well as areas covered by vegetation. Part of the site is already in use as a visitor parking area, providing 46 spaces for cars and 3 spaces for coaches. Report of the Chief Officer Economy and Planning
Proposal
Planning permission is sought to re-develop the land to create a new arrival point for visitors to the Pontcysyllte Aqueduct and World Heritage Site, including the provision of parking areas, extensive landscaping, pathways, drainage infrastructure and fences.
Reason for Committee Determination
Major Development
Site History
Extensive history associated with the former Flexys works. No history directly relevant to the proposed develpment.
{ Development Plan
Local Development Plan Within a defined settlement limit, the Trefor Basin Masterplan area and the World Heritage Site Buffer Zone. Policies SP2, SP13, SP14, SP15, SP16, SP18, SP19, NE1, NE3, NE6, BE1, BE2, DM1 and T1 apply. Report of the Chief Officer Economy and Planning
Relevant National Policy
Planning Policy Wales Future Wales Technical Advice Note 5: Nature Conservation and Planning Technical Advice Note 12: Design Technical Advice Note 13: Tourism Technical Advice Note 18: Transport
Consultation Responses
Community Council: Have made the following comments: Although part of the “Master Plan”, the proposed development favours visitors arriving by motor vehicles. It only serves to move the car park 30 metres, perhaps vacating a prime site for future domestic development; The original plan for the linking of Cefn Mawr and Pontcysyllte is missing. Residents of the Cefn Community and Llangollen Rural are still being penalised by the Rose Hill and Hill/Queen Street roadway routes. Both being of very steep terrain with heavy traffic usage. Both have a negative for visitor/residents’ health and wellbeing; and The return to public use of the old tramway known as “The Oilworks Road” which passes the North-East boundary of this planning application would alleviate the problem. This has previously been agreed. Outside agencies such as Sus-Trans are also greatly in favour of this route which would provide a safe link between Pontcysyllte and Cefn Mawr, onto Ruabon
Local Member: Notified.
Natural Resources Wales: Consulted
HSE: Advises against granting planning permission on health and safety grounds.
National Grid Confirms there are no National Grid Electricity Transmission assets affected.
Fire and Rescue Have the the following observations: The fire hydrant provision in the area is acceptable for the risk; and Emergency vehicle access should be maintained available to all areas of the proposed development
Dwr Cymru Welsh Water: Report of the Chief Officer Economy and Planning
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.