Planning Committee, Monday 5 January 2026 at 4.00pm

Development Management Performance Update Report

Noted Planning 1 paper

AI summaryWrexham Planning Committee noted a Q2 2025-26 performance report showing 93% of applications determined on time, but the 104-day average determination time exceeds the Welsh Government benchmark.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action decided by the Committee
MoneyNot stated
What happens nextNone specifiedUpdate noted only, no new tasks set
Who it affectsPlanning applicants and residentsThrough speed of decisions, appeals and enforcement

What was decided

The Committee noted the Development Management Performance Update Report for Quarter 2 of 2025-26, covering decision speed, enforcement, appeals and staffing. Report 1.2, 4.1

The report set out four consecutive quarters where 80% or more of applications were determined within 8 weeks or an agreed extension, with 93% reached in Q2. Report 2.4, 2.2, P25

Two planning appeals were received in Q2 and both were dismissed; one enforcement appeal was received and the notice was upheld with a varied compliance period. Report 2.9, P29, P56, P72

Why

Officers reported that 93% of all applications were determined within 8 weeks or agreed extension, meeting the Welsh Government 'Good' benchmark, though only 49% were within 8 weeks alone. Report 2.2, 2.5

The average time to determine applications was 104 days, considerably above the less-than-67-days 'Good' threshold; the phosphorus issue is continuing to hold applications in abeyance. Report 2.2, 2.5

Enforcement performance fell to 68% of cases investigated within 12 weeks, classed as 'Improve', after a period of officer sickness in Q1. Report 2.3, 2.6

What happens next

A new Planning Assistant appointed in Q2 started towards the end of Q3, and the vacant Ecology and Biodiversity Officer post was advertised in Q3. Report 3.1, 3.2

Officers are carrying out a more detailed analysis to identify where delays occur and what changes could reduce them. Report 2.5

When the phosphorus issue is resolved, the average determination time is expected to rise as the held applications are cleared. Report 2.5

Implications

  • Staffing: The Ecology and Biodiversity Officer left during Q2 and the post was advertised in Q3, leaving an ecology capacity gap. Report 3.2
  • Staffing: A new Planning Assistant was appointed and started towards the end of Q3, supporting development management resourcing. Report 3.1
  • Risk: The phosphorus issue continues to hold an increasing number of applications in abeyance, and once released will push up the average determination time. Report 2.5
  • Other: Enforcement speed has dropped, with 68% of cases investigated within 12 weeks in Q2 against 85% in Q1, after prolonged officer sickness. Report 2.3, 2.6
  • Legal: Two planning appeals were dismissed and an enforcement appeal was dismissed with the notice upheld but the compliance period extended to 6 months. Report 2.9, 2.10, P72
  • Other: 97% of decisions in Q2 were made under delegated powers, compared with 96% across Wales in 2024-25. Report 2.7, P28

Who and where

  • Applicants for planning permission in Wrexham, particularly those affected by the ongoing phosphorus issue Report 2.5
  • Residents and neighbours involved in planning and enforcement cases Report 2.3, P56
  • Development management and enforcement staff in the Council's Planning Service Report 3.0, 3.1, 3.2

Timeline

  • Q1 2025-26: 205 applications determined, 87% within 8 weeks or agreed extension; average 119 days; 33 enforcement cases, 85% within 12 weeks Report P25, P26
  • Q2 2025-26: 178 applications determined, 93% within 8 weeks or agreed extension; average 104 days; 70 enforcement cases, 68% within 12 weeks Report 2.2, 2.3, P25, P26
  • Q2 2025-26: 2 planning appeals received, both dismissed; 0 cost awards; 97% of decisions made under delegated powers Report 2.7, 2.9, 2.10, P29, P30
  • Q2 2025-26: 1 planning enforcement appeal received, dismissed with notice upheld and compliance period extended to 6 months Report P56, P72
  • End of Q3 2025-26: New Planning Assistant started in post Report 3.1
  • Q3 2025-26: Vacant Ecology and Biodiversity Officer post advertised Report 3.2

Plain English for the jargon

  • PEDW: Planning and Environment Decisions Wales, the body that decides planning and enforcement appeals
  • Welsh Government benchmark: Performance thresholds for planning authorities, with bands labelled 'Good', 'Fair' and 'Improve'
  • Phosphorus issue: Nutrient pollution affecting the River Dee and Bala Lake SAC, causing planning applications to be held in abeyance until solutions are in place
  • SAC: Special Area of Conservation, a European protected habitat site
  • WwTW: Wastewater Treatment Works, in this case Five Fords
  • UDP: Unitary Development Plan, the predecessor plan to the Wrexham Local Development Plan
  • LDP: Local Development Plan
  • TAN: Technical Advice Note, Welsh Government planning guidance
  • PPW: Planning Policy Wales, the national planning policy document
  • UU: Unilateral Undertaking, a planning obligation offered by a developer
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68

Resolved

RESOLVED – That the report be noted.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

1.2To provide the Committee with updates on the performance of the Council’s Planning Service for reporting period Quarter 2 of the financial year 2025‐26 and staff resourcing.

2.0INFORMATION

2.1Tables of key Development Management statistics and Planning Appeals can be found in Appendix 1 and Appendix 2 respectively. A summary of the key issues arising from Planning Appeal decisions and Enforcement Appeal decision received during Quarter 2 can be found in Appendix 3 and Appendix 4 respectively.

Development Management and Enforcement Performance

2.2During the reporting period, 93% of all planning applications were determined within 8 weeks or an agreed extension of time. This falls within the Welsh Government’s benchmark for ‘Good’. No applications for ‘major’ development were determined during the reporting period. The average time to determine planning applications within the period was 104 days. This is considerably in excess of the Welsh Government’s benchmark of less than 67 days to be classed as ‘Good’.

2.3During the reporting period 70 Enforcement cases were investigated, 68% within 12 weeks. This falls within the Welsh Government’s benchmark for ‘Improve’.

2.4The percentage of applications determined within 8 weeks or an agreed extension of time has exceeded 80% for the fourth consecutive quarter. This is, in part, due to an overall improvement in staff resourcing. However, it is also due to the continued and considerable amount of hard work by the Development Management Team to ensure applications are determined with statutory time limits. There has also been a further improvement in the average time to determine applications.

2.5Despite improvements, there is considerable scope for further improvement. Meeting the Welsh Government’s benchmark for ‘Good’ is heavily dependant upon Officers securing extensions of time, with only 49% of applications determined within 8 weeks. A more detailed analysis is being undertaken to identify where delays occur and what changes could be made to reduce them. This should also assist in reducing the average time to determine planning applications. However, the phosphorus issue is continuing to result in an increasing number of applications being held in abeyance. When a solution is in place that allows applications held in abeyance to be determined, it will be inevitably be the case that the average time to determine applications increase until the backlog has been cleared.

2.6Performance relating to the speed of concluding enforcement investigations has declined compared Quarter 1. However, as noted in the Development Management Performance Update Report for Quarter 1 (presented to Members in October 2025), in addition to the normal challenges faced by the team, the Enforcement Team was under resourced for the most of Quarter 1 due to one Officer being on sick leave for a prolonged period. In turn, this placed a considerable additional pressure on the other two Planning Enforcement Officers. The Quarter 1 report had anticipated that this would have an impact on performance in Quarter 2, and this has proved to be the case.

Delegated Decisions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Development Management Performance Update ReportReport 240 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 18 attended
BA
Councillor Bryan ApsleyCommittee Member, apologies
TB
Councillor Trevor BatesCommittee Member, apologies
ID
Councillor I David Bithell MBECommittee Member, present, as expected, virtual
BB
Councillor Beryl BlackmoreCommittee Member, present, as expected, virtual
DD
Councillor Dana DaviesCommittee Member, present, as expected, virtual
FH
Councillor Frank HemmingsCommittee Member, present, as expected, virtual
JJ
Councillor Jon JolleyCommittee Member, present, as expected, virtual
MJ
Councillor Marc JonesVice-Chair, present, as expected, virtual
SJ
Councillor Steve Joe JonesCommittee Member, present, as expected, virtual
JM
Councillor John McCuskerCommittee Member, present, as expected, virtual
MM
Councillor Michael MorrisChair, present, as expected, virtual
JN
Councillor Jeremy NewtonCommittee Member, present, as expected, virtual

All 18 on the meeting page

On this subject at Wrexham

Search all
  1. Development Management Performance Update ReportThis decision
  2. Development Management Performance Update ReportNoted
  3. Development Management Performance Update ReportNoted
  4. Development Management Performance Update ReportNoted
  5. Development Management Performance Update ReportNoted
  6. Development Management Performance Update ReportNoted

More from Wrexham Planning Committee

All decisions
MeetingDecisionOutcome
7 Sep 2026 Confirmation of MinutesRESOLVED – That the Minutes of the Meeting held on 27 July 2026 be signed as a correct record. Decided Open
7 Sep 2026 Application No: P/2025/0573 - Car Park, Tesco Stores Limited, Crescent Road, Wrexham, LL13 8HFRESOLVED – That planning permission be refused. Reason for decision (i) The proposal would introduce an additional ho... Refused Open
7 Sep 2026 Variation in Order of AgendaRESOLVED – That Agenda Item 4c – P/2026/0364 – Colliers Park, Wrexham AFC Training Ground, Chester Road, Gresford, Wr... Decided Open
7 Sep 2026 Application No: P/2026/0364 - Colliers Park, Wrexham AFC Training Ground, Chester Road, Gresford, Wrexham, LL12 8PWRESOLVED – That consideration of the application be deferred. Reason for decision To request the applicant to provide... Deferred Open
7 Sep 2026 Application No: P/2026/0174 - First and Second Floor Flat, 36 Brook Street, Wrexham, LL13 7LLRESOLVED – That planning permission be refused. Reasons for decision (i) The development will result in an overconcen... Refused Open