AI summaryWrexham Executive Board backs regional Connect to Work employment support plan, delegating commissioning of two programme elements to officers, with launch set for 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedRegional Delivery Plan supported, two commissioning delegations granted
Money£12,216,277.91 regional budgetDWP funded, paid via Denbighshire as Accountable Body
What happens nextLaunch in 2026Subject to Department for Work and Pensions approval
Who it affectsEconomically inactive residents of WrexhamParticularly those with long term health conditions or disability
What was decided
The Executive Board supported the draft Regional Delivery Plan developed by the six north Wales local authorities. Report P7
Delegated authority was granted to the Interim Chief Officer Economy and Planning, in consultation with the Lead Member Economy, Business and Tourism, to commission the Individual Placement Support element in Wrexham and sign funding agreements with the Accountable Body. Report P8, P10
Delegated authority was granted to the same officer to support regional commissioning of the Supported Employment Quality Framework element. Report P9
Why
To allow the Council to progress the work required on a regional basis to establish the new Connect to Work employment support programme in Wrexham County Borough. Report P11
Connect to Work is the first major element of the UK Government's Get Britain Working Strategy and is designed to reduce economic inactivity, particularly where it is driven by ill health. Report 2.2, 2.3, 4.1
What happens next
Submit the draft Delivery Plan to the Department for Work and Pensions for approval. Report 4.12
Commission an external provider for Individual Placement Support in Wrexham and join a regional procurement exercise for Supported Employment Quality Framework. Report 4.5, 4.8, 4.9
Recruit specialist staff to manage external providers and integrate the programme with existing Council services, with the programme closing in 2031. Report 4.10, 4.11, 5.4
The money
£12,216,277.91 Overall regional budget for Connect to Work over the 4 year delivery window Report 4.15
Options considered
Chosen: Accept the recommendations. Allows Wrexham to engage in the Connect to Work Programme Report 7.1
Rejected: Reject the recommendations. Would prevent Wrexham from engaging in the Connect to Work Programme at this time Report 7.2
Implications
Financial: Funding from the Department for Work and Pensions must be spent in year, cannot be rolled over, and is subject to potential claw back if targets are missed. Report 4.2, 5.2
Legal: A Memorandum of Understanding will be signed with the Accountable Body and the Council will hold and share personal data for 10 years after programme closure. Report 5.3
Staffing: Specialist staff will need to be recruited; existing Communities for Work Plus capacity cannot be deployed and redevelopment work will use existing Regeneration Team resources. Report 5.4
Risk: Potential redundancy cost liabilities at programme closure in 2031 are not covered by Department for Work and Pensions funding. Report 5.4
Risk: Fifty per cent of participants must achieve a job outcome, 20 per cent higher than the Welsh Government's Communities for Work Plus programme.
Equalities: The Integrated Impact Assessment covers the Well being of Future Generations Act, Equality Act 2010, Welsh Language Measure and Armed Forces Act 2021. Report P32
Who and where
Economically inactive residents of Wrexham, particularly those with long term limiting health conditions or a disability Report 4.13, 5.1
Wrexham Council's Housing, Social Care, Mental Health and Learning Disability Teams Report 4.11
Participants and staff of the existing Communities for Work Plus programme in Wrexham Report 4.11
Betsi Cadwaladr Health Board, through the need to reach the correct cohort of job seekers Report 4.13
Six north Wales local authorities working together on regional commissioning Report 2.4, 4.3, 4.4
Timeline
End of May 2025: Regional Programme Manager appointed by Denbighshire County Council as Accountable Body
2026: Connect to Work programme scheduled to commence across North Wales over a 4 year window Report 4.2, 4.14
2031: Programme closure, with potential redundancy cost liabilities not covered by DWP funding Report 5.4
September 2025: Previous Executive Board report (COEP/45/25) received outlining Connect to Work Report 2.1, 7.2
Plain English for the jargon
Accountable Body: Denbighshire County Council, which leads the regional programme and administers DWP funding
Connect to Work: A UK Government supported employment programme, the first major element of the Get Britain Working Strategy
Individual Placement Support (IPS): One of two support routes under Connect to Work, helping eligible people into work
Supported Employment Quality Framework (SEQF): The second support route under Connect to Work, involving specialist delivery
Fidelity Model: Testing requirements that providers of IPS and SEQF must comply with
NOMIS: Office for National Statistics source of census and workforce data
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95
Resolved
RESOLVED – ( i ) That the draft Regional Delivery Plan for the programme, which has been developed through collaboration between the six north Wales local authorities be supported. (ii) That delegated authority be granted to the Interim Chief Officer Economy & Planning, in consultation with the Lead Member Economy, Business & Tourism, to directly commission the Individual Placement Support element of the programme in Wrexham to review and sign agreements for the funding of the programme with the Accountable Body, once the Delivery Plan is approved by the Department for Work & Pensions. (iii) That delegated authority be granted to the Interim Chief Officer Economy & Planning, in consultation with the Lead Member Economy, Business & Tourism, to support the regional commissioning of the Supported Employment Quality Framework element of , as set out in the draft Delivery Plan. (iii) That delegated authority be granted to the Interim Chief Officer Economy & Planning, in consultation with the Lead Member Economy, Business & Tourism, to directly commission the Individual Placement Support element of the programme in Wrexham. Reason for Decisions To allow the Council to progress the work required on a regional basis to establish the new employment support programme in Wrexham County Borough, which will benefit economically inactive people and launch in 2026.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
2.1In September 2025, the Executive Board received a report outlining the new Connect to Work supported employment programme (COEP/45/25). Connect to Work was announced as part of the UK Government’s Get Britain Working Strategy
2.2One of the UK Government’s five missions is to “kickstart economic growth with good jobs and improved productivity in every part of the country”. The new strategy aims to bring fundamental reform that transforms the UK Government’s relationship with local areas and ensure a strong foundation with which to work in partnership to support people into good, sustainable work. Connect to Work is the first major element of the UK Government’s Get Britain Working Strategy to be launched.
2.3Connect to Work was originally announced as a 5-year programme, designed to reduce economic inactivity and enable local areas to build an offer of support to eligible people in their locality. The support aims to tackle economic inactivity, particularly where it is driven by ill health. Moreover, the design of the programme requires local authorities to lead and drive the programme to reduce economic inactivity. Support is available through two routes an Individual Placement Support, or a Supported Employment Quality Framework. These were described in COEP/45/25.
2.4Following the September 2025 report, work has been taking place at a regional level to develop the Connect to Work delivery plan. This work has been led by Denbighshire County Council in its role as the Accountable Body.
2.5The draft Delivery Plan for North Wales is attached at Appendix 1. This confirms that the Council’s preferred approach to delivery of the supported employment programme in Wrexham is to commission external provision to deliver the programme.
Recommendations
3.1That the Executive Board
(i) Supports the draft Regional Delivery Plan for the Connect to Work programme, which has been developed through collaboration between the six north Wales local authorities;
(ii) Approves delegation to the Interim Chief Officer Economy & Planning, consultation with the Lead Member Economy, Business & Tourism, to directly commission the Individual Placement Support element of the Connect to Work programme in Wrexham to review and sign agreements for the funding of the programme with the Accountable Body, once the Delivery Plan is approved by the Department for Work & Pensions;
(iii) Approves delegation to the Interim Chief Officer Economy & Planning, consultation with the Lead Member Economy, Business & Tourism, to support the regional commissioning of the Supported Employment Quality Framework element of Connect to Work, as set out in the draft Delivery Plan; and
(iii) Approves delegation to the Interim Chief Officer Economy & Planning, consultation with the Lead Member Economy, Business & Tourism, to directly commission the Individual Placement Support element of the Connect to Work programme in Wrexham.
Reasons for recommendations
To allow the Council to progress the work required on a regional basis to establish the new Connect to Work employment support programme in Wrexham County Borough, which will benefit economically inactive people and launch in 2026.
4 BACKGROUND INFORMATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.