Governance and Audit Work programme

Noted Finance 1 paper

AI summaryWrexham Governance and Audit Committee noted its 2025/26 work programme, which lists statements of accounts, internal audit reports and governance reviews through to July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee formally noted its forward work programme
MoneyNot stated
What happens next14 May 2026 meetingStatement of Accounts 2024/25, internal audit plans and reports
Who it affectsGovernance and Audit CommitteeSets out its scheduled reports and pre-meetings

What was decided

The committee noted its Governance and Audit Work Programme, which sets out agenda items, reporting officers and Terms of Reference references for meetings through 2025/26. Report P1, P2

Why

The work programme was attached for the committee's information as a standing item of its work. Report P1, P2

What happens next

At 14 May 2026 the committee is scheduled to consider the Statement of Accounts 2024/25, the Internal Audit Mandate and Charter 2026/27, the Internal Audit Plan 2026/27, the Internal Audit Annual Report 2025/26 including Counter Fraud, an external regulators' progress update, a Panel Performance Assessment update, and an Audit Wales report on Temporary Accommodation. Report P10

On 16 July 2026 the committee is scheduled to appoint a Chair and Vice-Chair, consider the Chair's Annual Report 2025/26 and review the Annual Governance Statement 2025/26. Report P11, P12

Member training sessions are scheduled and listed in the programme. Report P13

Implications

  • Governance: The programme maps each item to a Terms of Reference reference, covering accounting policies, internal control, risk management, counter fraud and external regulator responses. Report P4, P5, P6, P7, P8, P10, P12

Who and where

  • Governance and Audit Committee members Report P1, P2
  • Reporting officers from Accountancy, Audit and Technical, PIPS, COFICT and Audit Wales Report P4, P5, P6, P7, P8, P10, P12

Timeline

  • 19 March 2026: Meeting to consider the 2023/24 Statement of Accounts, Audit Wales' report on that audit, Audit Wales' governance enquiries, Internal Audit interim report, risk and control registers (Q3) and Change Programme update. Report P4, P5, P6, P7, P8
  • 14 May 2026: Meeting scheduled for the 2024/25 Statement of Accounts, Internal Audit Mandate and Charter 2026/27, Internal Audit Plan 2026/27, Internal Audit and Counter Fraud Annual Report 2025/26, external regulators' progress, Panel Performance Assessment update and Audit Wales Temporary Accommodation report. Report P10
  • 16 July 2026: Meeting scheduled to appoint Chair and Vice-Chair, consider the Chair's Annual Report 2025/26 and review the Annual Governance Statement 2025/26. Report P11, P12

Plain English for the jargon

  • ToR: Terms of Reference of the Governance and Audit Committee, cited against each item.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

- That the Governance and Audit Work Programme be noted.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Governance and Audit Committee

Governance & Audit Committee – Work Programme 2025/26

Date Type Agenda Item Purpose of Report including ToR Number Reporting Officer

Pre-meeting To be agreed GAC Members only

Statement of Accounts 2023/24 To approve the annual Statement of Accounts 2023/24. Head of Service Specifically to consider whether appropriate accounting Accountancy policies have been followed and whether there are concerns arising from the financial statements or from the audit that need to be brought to the attention of the Council (ToR 37) Reports Audit Wales – Audit of Statement of To consider Audit Wales’ report to those charge with Head of Service 19 March Accounts 2023/24 governance on issues arising from the audit of the Accountancy 2026 Statement of Accounts 2023/24 (ToR 6, 21, 22, 23, 24, 26 27, 28)

Audit Wales’ “audit enquiries to For the purposes of informing Audit Wales’ Head of Service those charged with governance understanding of the governance arrangements of the Accountancy and management” for the 2023-24 Council and its business processes to support their audit audit. work in providing an audit opinion for the 2023-24 financial statements (ToR 38 )

Internal Audit Interim Report April To consider the Head of Service Audit & Technical Head of Service 2025 to January 2026 Interim Report (ToR 6, 21, 22, 23, 24, 26,27, 28) Audit & Technical Agenda Item Purpose of Report including ToR Number Reporting Officer

Risk and Control Registers (Q3) To monitor the effective development and operation of Head of Service risk management in the Council (ToR 4) and to monitor PIPS progress in addressing risk related issues reported to Committee (ToR 5)

Change Programme Update To enable the Committee to fulfil its Terms of Reference COFICT/Head of in relation to its purpose (Tor 2) : to (a) review and Service PIPS scrutinise the authority’s financial affairs, (b) make reports and recommendations in relation to the authority’s financial affairs, (c) review and assess the risk management, internal control, performance assessment and corporate governance arrangements of the authority Date Type Agenda Item Purpose of Report including ToR Number Reporting Officer

Pre-meeting To be agreed GAC Members only

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Governance and Audit Work programmeReport 363 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
WB
Councillor William BaldwinCommittee Member, present, as expected, virtual
TB
Councillor Trevor BatesCommittee Member, apologies
BB
Councillor Beryl BlackmoreCommittee Member, present, as expected, virtual
DD
Councillor Dana DaviesCommittee Member, absent
CJ
Councillor Corin JarvisCommittee Member, present, as expected, virtual
BM
Councillor Becca MartinCommittee Member, apologies
PR
Councillor Paul RobertsCommittee Member, present
PR
Councillor Paul RogersVice-Chair, present
CB
Claire Blanchard - Independent Lay MemberCo-Optee, present
CE
Carys Edwards - Independent Lay MemberChair, present
CH
Colin Hopwood - Independent Lay MemberCo-Optee, present
JJ
John Jarvis - Independent Lay MemberCommittee Member, present

All 16 on the meeting page

On this subject at Wrexham

Search all
  1. Governance and Audit Work programmeThis decision
  2. Governance and Audit Development ProgrammeNoted
  3. Governance and Audit Work ProgrammeNoted
  4. Governance and Audit Development ProgrammeNoted
  5. Governance and Audit Development programmeNoted
  6. Governance and Audit Work ProgrammeNoted

More from Wrexham Governance and Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Confirmation of MinutesRESOLVED – That the Minutes of the meeting held on 18 June 2026 be signed as a correct record. Decided Open
16 Jul 2026 Terms of ReferenceRESOLVED – That the Governance and Audit Committee Terms of Reference be noted. Noted Open
16 Jul 2026 External Regulation & Inspection - Assurance re:implementation of recommendations- That members of GAC noted the progress made with the implementation of actins in response to the external regulatio... Noted Open
16 Jul 2026 Audit Wales Annual Audit Plan 2024-25- That the Audit Wales Annual Audit Plan 2024-25 be noted. Noted Open
16 Jul 2026 Audit Wales Performance Audit Plan 2026-27'- That the Audit Wales Performance Audit Plan 2026-27 be noted. Noted Open