Wrexham County Borough Council
Executive Board, Tuesday 9 June 2026 at 10.30am

The Former Groves School Site

Agreed Executive 3 papers

AI summaryWrexham Executive Board authorised officers to negotiate the disposal of the former Groves High School site to Coleg Cambria, ending a long-running liability for the council and bringing a listed vacant site back into educational use.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedChief Officer to agree terms and boundaries
MoneyNot stated
What happens nextAgree disposal terms with Coleg CambriaSubject to District Valuer valuation and overage
Who it affectsColeg Cambria and Wrexham City CentreSite to be brought back into educational use

What was decided

The Chief Officer Housing and Assets is authorised to agree terms for the disposal of the former Groves High School site to Coleg Cambria and to determine the site boundaries, in consultation with the Lead Member for Finance and Asset Management and the Lead Member for Education. Report 3.1

Why

The site is surplus to the council's education requirements and has been a continuing cost and liability, as the listed status prevents demolition and the council must keep the building wind and watertight. Report 2.6, 5.2

Disposal would generate a significant cost saving to the council and bring a vacant site back into productive educational use for the benefit of Wrexham City Centre and the wider county borough. Report P13, P14

Past proposals for two new 21st century schools, a medical training facility and a national arts gallery and contemporary museum all failed, largely because of the listing. Report 4.6

What happens next

Officers will obtain an updated District Valuer valuation, as the last one was carried out in May 2019, and progress the sale at that value. Report 2.8, 2.9, 2.10

Legal terms will include overage provisions to protect any future redevelopment beyond educational use, to be agreed by the legal department and the Chief Officer Governance and Customer Services. Report 2.11

Restrictive covenants from 1906, 1913 and 1919 restrict the site to educational use and set building and boundary restrictions, which will need to be reflected in the disposal. Report 2.3, 4.5, P30, P31, P32

Options considered

  • Chosen: Dispose of the site to Coleg Cambria for freehold, with overage protection. Brings vacant listed site back into educational use, removes council liability and generates a cost saving Report 2.7, P13, P14
  • Rejected: Past proposals for two new 21st century schools, a medical training facility and a national arts gallery and contemporary museum. None came to fruition, largely as a consequence of the Grade II listing Report 4.6

Implications

  • Financial: The council currently pays for the vacant listed asset and must keep it wind and watertight; further delay will increase deterioration and conversion costs. Report 5.2
  • Legal: Restrictive covenants from 1906, 1913 and 1919 restrict the site to educational use; the Grade II listing (29 November 2016) prevents demolition; overage provisions will be included to protect future non-educational use. Report 2.3, 2.4, 2.11, 4.4, 4.5, P30, P31, P32
  • Risk: No known risks identified, but continued delay will worsen the building's condition and raise future conversion or refurbishment costs. Report 5.2, 5.6
  • Staffing: There are no staffing implications from the disposal. Report 5.4
  • Equalities: An Integrated Impact Assessment covers the Well-being of Future Generations Act, equality, Welsh language and armed forces duties and is attached at Appendix 2 for members to consider. Report P34

Who and where

  • Coleg Cambria, which would acquire the site freehold to expand its Wrexham operations Report 2.7, 4.7, 4.8, 4.9
  • Wrexham City Centre and the wider county borough, who would benefit from a vacant listed site being brought back into productive use Report P14
  • Wrexham County Borough Council, which currently bears the cost of maintaining the vacant listed building Report 5.2
  • Adjacent residential and neighbouring landowners, whose interests are protected by the historic covenants Report 4.1, P30, P31, P32
  • Coleg Cambria learners, who could benefit from expanded provision in Wrexham Report 4.7, 4.8, 4.9

Timeline

  • 2006: Former Groves High School closed Report 2.2
  • 2012: Council staff stopped using the site, which has been vacant since Report 2.2
  • 29 November 2016: Building was Grade II listed, preventing demolition and restricting other educational uses Report 2.4, 4.4
  • May 2019: District Valuer carried out the most recent valuation, on which the current disposal basis is set Report 2.8, 2.10
  • 9 June 2026: Executive Board authorised officers to agree terms for disposal to Coleg Cambria Report 3.1

Plain English for the jargon

  • Overage provisions: A clause requiring the buyer to pay the council extra if the site is later developed for uses beyond education
  • Restrictive covenant: A binding legal restriction on the use of land, in this case limiting the site to school, recreation and playground purposes
  • Grade II listed: A statutory designation protecting a building of special interest from demolition or significant alteration
  • District Valuer: A government valuer whose independent valuation is used as the basis for the sale
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED – That the Chief Officer Housing and Assets be authorised to agree to terms for a disposal to Coleg Cambria and determination of boundaries, in consultation with Lead Member Finance and Asset Management and Lead Member Education. Reasons for Decision (i) To obtain support for a course of action to dispose of the surplus property and generate a significant cost saving to the Council. (ii) Enable a vacant site to be brought back into a productive use for the benefit of Wrexham City Centre and wider County Borough.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To update Members on proposals for the future use of the former Groves High School site and to seek views on and support for a disposal to Coleg Cambria.

Executive summary

2.1The site comprises a former high school, consisting of school building, hard standing and playing fields extending to approximately 10.87 acres/4.4 hectares – the site can be shown edged red in Appendix 1.

2.2The former Groves High School closed in 2006 and was subsequently used by Council staff until 2012 and has since remained vacant. Works to secure the building and to keep it “wind and watertight” have been breached on several occasions over the years and therefore the site forms part of the daily security patrols at a cost to WCBC.

2.3The school site is subject to restrictive covenants restricting its use for educational purposes. Further details on the covenants can be found in section 5.3.

2.4The Groves building was designated as a Grade II listed property in 2016. An initial listing decision was successfully challenged by the Council based on insufficient reasoning. However, the building was re-listed supported by more comprehensive justification. It was concluded that a further challenge would be unlikely to succeed and the Welsh Government decision to list the building was officially granted on 29 November 2016. The listing prevented it from being demolished and or any other educational uses coming forward. 2.5 The Council have considered a number of proposals for the site in the past, including two new 21 century schools; a medical training facility and the last being consideration for a national arts gallery and contemporary museum; however none have come to fruition, largely as a consequence of the listing.

2.6The site falls within the Council’s Education department portfolio who have confirmed the site is surplus to requirements.

2.7Representation has been made by Coleg Cambria expressing an interest in the site for a freehold acquisition , in order to expand its current operations within Wexham City Centre.

2.8The site was valued by the District Valuer back in May 2019 based on several options.

2.9An updated District Valuer valuation has been requested on the basis the last one was carried out over 5 years ago; however, it is not anticipated the value of the building would have changed given the building has fallen into further disrepair since in the intervening period, and any associated costs for conversion/refurbishment would have increased.

2.10The sale of the site to Coleg Cambria will be in line with the Districts Valuers valuation report.

2.11The Council will include the necessary overage provisions to protect any potential future redevelopment of the site by Coleg Cambria for any use over and above educational use. The mechanics of the overage provisions will be agreed with the Councils legal department and Chief Officer Governance and Customer Services.

Recommendations

3.1Authorise the Chief Officer Housing agree to terms for a disposal to Coleg Cambria and determination of boundaries, in consultation with Lead member Finance and Asset Management and Lead Member Education.

Reasons for recommendations

(i) To obtain support for a course of action to dispose of the surplus property and generate a significant cost saving to the Council.

(ii) Enable a vacant site to be brought back into a productive use for the benefit of Wrexham City Centre and wider County Borough.

4. BACKGROUND INFORMATION

4.1The former Groves School is close to the centre of Wrexham in north east Wales. It borders the inner ring road benefitting from proximity to facilities and good access to road networks. It also borders an established residential area. Wrexham is a large and busy town offering a wide range of business,

2 shopping, leisure and educational facilities, including a university, plus a large hospital.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 675 KB Download
PDF
Appendix 2Appendix 2 521 KB Download
PDF
The Former Groves School SiteReport 108 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 23 attended
YC
Y Cynghorydd David A BithellVice-Chair, present
YC
Y Cynghorydd Terry EvansCommittee Member, present
YC
Y Cynghorydd Hugh JonesCommittee Member, apologies
YC
Y Cynghorydd Beverley Parry-JonesCommittee Member, present
YC
Y Cynghorydd John PritchardCommittee Member, present
YC
Y Cynghorydd Mark PritchardChair, present
YC
Y Cynghorydd Paul RobertsCommittee Member, present
YC
Y Cynghorydd Robert WalshCommittee Member, present
YC
Y Cynghorydd Nigel WilliamsCommittee Member, present
YC
Y Cynghorydd Phil WynnCommittee Member, present
YC
Y Cynghorydd Brian CameronGuest, in attendance
YC
Y Cynghorydd Annette DaviesGuest, in attendance, virtual

All 23 on the meeting page

On this subject at Wrexham

Search all
  1. The Former Groves School SiteThis decision
  2. The Former Groves BuildingAgreed
  3. The Former Groves High School SiteNoted
  4. The Former Groves High School Site - Listing NotificationDecided
  5. The Former Groves High School SiteDecided
  6. The Former Groves High School SiteDecided

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies