Resolved That the Executive Board supports the actions of the Head of Environmental Services, Engineering Consultancy Manager and Portfolio Holder for Environmental Matters in compiling select lists for Medium and High value contracts and endorses the lists as set out in Appendices A1 – A4 of the report.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1This report seeks to inform the Executive Board of the results of the technical and financial appraisals carried out on applicants during the review of the select lists for Medium and High value Contracts and requests that the Board endorses the compilation of select lists.
Recommendation
2.2That the Executive Board supports the actions of the Head of Environmental Services, Engineering Consultancy Manager and Portfolio Holder for Environmental Matters in compiling select lists for Medium and High value Contracts and endorses the lists in Appendices A1-A4.
3.0IMPLICATIONS AND IMPACT
3.1Council Priorities and Community Plan Themes
Operating Select Lists for General Civil Engineering and Flood Alleviation Scheme Contracts assists in Priority 1 - Healthy and Safe communities with a good quality environment and Priority 3 - an excellently run Council.
Financial implications
All the Companies shown on the attached appendix have been subjected to the authority's normal financial appraisal the results of which are shown in the column headed Stage 2 Financial Appraisal. Each Company will be subjected to a further financial appraisal in due course before any tenders are invited (DMT)
3.3Staffing Implications
The operation of these select lists will result in reduced staff time spent on the tender process for all schemes for which they are used. 3.4 Risks
The review process has eliminated unsuitable Contractors and this will reduce risks in subsequent contracts.
3.5Legal
None at this stage
3.6Property
None at this stage
Background
4.1During January of this year advertisements were placed in the Worcester Evening News, Evesham Journal, Droitwich Advertiser and Contracts Journal inviting applications from suitably experienced and qualified Civil Engineering Contractors who wished to be considered to be placed on select lists for Medium and High value contracts, i.e. up to £28,000 and over £28,000 in value. In all four categories of select list were being offered.
4.2In all a total of 31 applications were received before the deadline of 3rd February 2006 and unless disqualified at Stage 1 all went through a rigorous five stage appraisal process involving staff from Engineering Consultancy, Audit and Financial Services. At least three independent references for each applicant were also sought. Four applications were received after the deadline and were rejected at that stage.
4.3The results of the five stage appraisal process were presented to the Executive Board on 21st July 2006. In all, fifteen have received unsatisfactory results at one or more of the stages and have, therefore, been rejected. It is intended that these lists remain valid for two years and are reviewed prior to September 2008. The four select lists are set out in Appendix A1 - A4.
4.4It should be noted that in accordance with Standing Orders relating to Contracts a further financial appraisal will be carried out immediately before tenders are invited on all high value contracts.
4.5Tender lists for specific schemes will be compiled from one of the four select lists by the appropriate Head of Service, Portfolio Holder with responsibilities for the specific scheme and the Engineering Consultancy Manager.
4.6It should also be noted that the select lists have been set up for general civil engineering and flood alleviation work anticipated within the current capital programme. Following feasibility a scheme may present engineering problems which will be best addressed by specialist contractors for which ad hoc tendering may need to be implemented in parallel with the above. In this event the Executive Board will be informed.
F:\DebJay\Committee Reports\ExecBoard\Select List 19.9.06.doc
Appendix A1 SELECT LIST NO. 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.