Pershore Skatepark

Decided Executive 1 paper

Executive Board decided this item on Tuesday 10 October 2006. Below is the council's own wording, with the papers it was decided on.

Item94

Resolved

Resolved That the following lessons arising from the project be shared with future capital projects:- Tender document preparation is an important part of the project process and it is essential to get it right. However this can be very time consuming and sufficient time needs to be programmed in at an early stage. Significant delays in project timetables are likely to have an impact on construction costs. When new concrete is being poured in high profile public spaces, arrange overnight security well in advance and budget accordingly. Again, when concrete is involved, the client officers need to anticipate an appropriate drying period. The contractor build programme for the skatepark anticipated 4 weeks but the 7 to 14 day dry period was in addition to this and meant that an opening date was later than originally anticipated. Member and officer expectations for project delivery times need to fully reflect Contract Procedure Rules.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 3 pages

Summary

1.1This report summarises the contract implementation works following the approval of the Pershore Skatepark project on 13th September 2005. The skatepark was completed in August of this year at a cost slightly greater than the anticipated budget.

Recommendations

2.1Actions identified in section 4.6 to be noted for future capital projects.

3. Implications & Impact

3.1Council Priorities and Community Plan Themes – Achieves directly Priority 3 Goal 5 from the Council’s 2005/06 Priorities and Promises.

3.2Resource Implications - As stated within the report the project has overspent the original projection. The overspend will be met from the existing earmarked reserve for youth initiatives. (SRS)

3.3Staffing Implications – Project delivered by existing Council staff.

3.4Legal Implications – Project completed in line with the Council’s approved Contract Procedures.

3.5Property Implications – Ongoing maintenance costs to be covered from identified existing budgets.

3.6Risk Assessment – Skatepark built in line with the guidance contained within British Standard Institution “Specification for Wheeled Sports Facilities”. The site is inspected on a daily basis by our parks contractor and this will be supplemented by an independent annual skatepark inspection.

Page 1 of 3 E:\moderngov\data\published\Intranet\C00000314\M00001976\AI00007010\PershoreSkatepark0.doc 4. Background

4.1After an extensive period of project research, consultation and development the Executive Board gave the go ahead for the provision of a skatepark in Abbey Park, Pershore on 13th September 2005. This decision followed an initial granting of planning permission on the 11th August 2005.The anticipated cost of the skatepark construction and associated landscaping works at this time was £90,000.

4.2Members will recall that in order to mitigate some of the objections received during the planning process a revised planning application for the Skatepark was submitted and approved on 5th January 2006. Following this date the following key actions have taken place :

• Tender documentation prepared by Property section – Jan-March

• Tenders sent out to 4 contractors on the Council’s select list – 3rd April

• Tenders opened – 3rd May. Grimshaw Group identified as lowest tender.

• Pre-contract meeting with Grimshaw’s on 11th May

• Contract letter sent to Grimshaw’s on 25th May

• Order to Bencrete – manufacturers of pre-cast concrete ramps confirmed by Grimshaw. Normal 8-12 weeks delivery time. Bencrete had been alerted in advance by officers to expect an order so that it could be planned ahead and delivery time reduced.

• Work on site started 17th July with a planned 4-week construction period. Engineers section very successfully provided works monitoring support.

• Skatepark officially opened 31st August.

• Landscaping works to be completed later in the autumn.

4.3The above procurement process is in line with the Council’s approved Contract Procedure Rules. The total costs of delivering this project, including the planned landscaping works, is expected to be :

• Construction of skatepark surface and ramps - £80,072*

• Fence and gates - £8,399

• Access paths - £1,497

• Landscaping, signs etc. - £8,490

• Security (following initial concrete pour) - £200

TOTAL - £98,658

Page 2 of 3 E:\moderngov\data\published\Intranet\C00000314\M00001976\AI00007010\PershoreSkatepark0.doc This cost includes £4,000 retention monies which will be paid after 12 months of successful operation with no significant structural problems.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pershore SkateparkReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Pershore SkateparkThis decision
  2. Planning application Ref W/05/02068/DW - Skatepark enclosed by 1.4m metal bowtop fencing (amendment to previously approved scheme W/05/00979/DW). Abbey Park, Abbey Road, Pershore, WR10. Wychavon District Council.Approved
  3. Pershore SkateparkDecided
  4. Planning application Ref W/05/00979/DW - Proposed Skatepark. Abbey Park, Abbey Road, Pershore WR10. Wychavon District Council.Approved

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies