Resolved 1. That a working group consisting of the Council’s Engineering team and Members, as detailed above, be formed to review the 20-22 July 2007 flooding event in Wychavon. 2. That the details of the flooding event be collected and collated by the group to provide an overall picture of the extent and impact of the flooding and that a further report be submitted to the Executive Board identifying a way forward for their consideration. 3. That consideration be given to supporting a Programme Option submission as part of the Revenue Budget process to fund the appointment of a Land Drainage/Engineering Assistant on a 3 year contract, to be reviewed towards the end of the contract, for the purposes of strengthening the Council’s role in land drainage enforcement. 4. That approval be given to appoint, immediately via an Employment Agency, a suitable Land Drainage Technician to assist with urgent land drainage issues for a period of 3 to 6 months. 5. That approval be given to the appointment of consultants to begin the work of reviewing the various flooding causes and mechanisms and feed into the working ... view the full minutes text for item 53.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
During the 20-22 July 2007, approximately 1500 properties throughout Wychavon were internally flooded. This report makes proposals for further action.
Recommendations
2.1That a working group consisting of the Engineering team and Members be formed to review the 20-22 July 2007 flooding event in Wychavon. (The Executive Board may wish to consider the nature of member representation on this working group).
2.2That the details of the flooding event to be collected and collated by the group to provide an overall picture of the extent and impact of the flooding and that a further report be submitted to the Executive Board identifying a way forward for their consideration.
2.3That consideration be given to supporting a Programme Option submission as part of the Revenue Budget process to fund the appointment of a Land Drainage/Engineering Assistant on a 3 year contract, to be reviewed towards the end of the contract, for the purposes of strengthening the Council’s role in land drainage enforcement.
2.4That approval be given to appoint immediately via an Employment Agency a suitable Land Drainage Technician to assist with urgent land drainage issues for a period of 3-6 month.
2.5That approval be given to the appointment of consultants to begin the work of reviewing the various flooding causes and mechanisms and feed into the working group proposed in recommendation 2.1. 3. Implications & Impact
3.1Council Priorities & Community Plan Themes
Priority 1, Health and Safe Communities with a god quality environment Priority 3, Goal 2 (Use our resources effectively and efficiently)
3.2Resource Implications
3.2.1. Financial Implications: Given the nature of the work that the proposed temporary Land Drainage Technician will be involved in, it is anticipated that the cost of this appointment (up to £10k) will be met from the Bellwin funds to be claimed from the government in response to this emergency.
The cost of employing a Land Drainage / Engineering Assistant is estimated to be £29,000 per year and a Programme Option will need to be submitted as part of the Revenue budget process to fund this.
The appointment of consultants is needed in the short term to deal with the temporary increased workload due to the floods. Initial costs of £27,000 can be funded from within the existing salaries budget. Following the initial assessment it may be necessary to submit a Programme Option for further consultancy costs as part of the Revenue Budget process.
3.2.2 Staffing implications: Co-ordination of the consultants work will need to be undertaken by existing staff but this should help ease the workload pressures rather than add to it.
3.2.3 Risks: There remains a risk of further flooding events and the Council has discretionary powers to deal with land drainage issues. There will also be pressure on the Council from other agencies to work with them in tackling flooding issues. In addition there is a public expectation that the Council will tackle flooding. To ignore these would put the Council at risk of being publicly criticised.
3.2.4 Legal Implications: As stated above, the Council has discretionary powers to deal with land drainage issues and there is a public expectation that it will use these powers. There is a risk to the Council of it having to defend its position should the Council choose not to use its powers.
3.3Diversity Impact Assessment: None at this stage
Background
4.1It is considered advisable that in each location in Wychavon where flooding occurred, further details should be obtained in order to establish the nature of each individual case and to see what practicable measures (if any) could be taken to alleviate future flooding. 4.2. From what we have already learnt from the floods and our previous experience from the 1998 floods, there appears to be four basic causes of flooding :
a) Rivers and Watercourses
b) Highways drainage
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.