Resolved 1. That the sum of £82,303 be allocated to Broadway Parish Council for the installation and construction of a new activity park and multi use games area on the Recreation Ground in Broadway. 2. That the above sum be paid to the Parish Council on satisfactory completion of the works and production of invoices.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1This report seeks Board approval to allocate a sum of money from the S106 contributions budget towards a new activity park and multi use games area for children and young people in Broadway.
Recommendations
2.1That the sum of £82,303 be allocated to Broadway Parish Council for the installation and construction of a new activity park and multi use games area on the Recreation Ground in Broadway.
2.2That the above sum is paid to the Parish Council on satisfactory completion of the works and production of invoices.
3. Implications & Impact
3.1Council Priorities and Promises This report supports Priority 3 ‘Improving Health and Well Being’ and Priority 4 ‘Vibrant and Inclusive Communities with a Strong Economy.’
3.2Resource Implications
Financial Implications – Section 106 deposits are held in the Council Accounts under the heading of receipts in advance. The individual sums are released to fund projects once the Council is satisfied that their usage is in line with the terms of the relevant section 106 agreement. dmt .
Staffing Implications – None.
Risks - None. The Parish Council will be responsible for health and safety inspections and for maintenance of the play areas. Legal – All contributions received by the Council must be spent in accordance with the terms of the relevant Section 106 Agreement.
Property – The land is owned by the Parish Council.
Background
4.1An application has been received from Broadway Parish Council for funding from the Council’s receipts account for s106 contributions.
4.2The Broadway Recreation Ground Committee, in conjunction with Worcestershire Youth Support Services, carried out extensive consultation with young people, families and schools within the village to find out exactly what was needed in the way of facilities for children and youths between the ages of 2 and 18. The Committee, with the support of a local Landscape Architect, then drew up plans and a specification outlining the proposals so that quotations/tenders could be sought from suppliers and contractors.
4.3Tenders/quotations have now been received and the relevant contractors and suppliers have been selected. The Parish Council would now like to proceed with the project.
4.4The project, which will cover the four acre site at the Recreation Ground (see attached plan), includes the following for phase 1:- a) improvement works to the existing football pitch b) the installation of a MUGA for youngsters between the ages of 12- 18 years old c) the installation and construction of two play areas using a range of suitable equipment. One for children aged 2-6 years old and the second for children aged 6-12 years old. d) the construction of a BMX track e) the installation of a new cableway/zip wire and climbing wall f) the provision and installation of new seating, picnic area and two shelters g) landscaping, planting and cotswold stone paths h) other minor works
The total cost of the above works and equipment is £220,488 plus VAT
4.5It is hoped that the following works will be carried out in phase 2 if additional funding can be secured:- a) provision and erection of a space net b) installation of a toilet c) further landscaping including feature rocks
The total cost of these works is £56,407 plus VAT
4.6The Parish Council are seeking a contribution of £82,303 from Wychavon towards the cost of the phase 1 works. The remaining amount will be made up from other sources of funding already secured:- a) Parish Council £ 8,000 b) Wychavon Playbuilder £52,000 c) YCF – DABID £69,000 d) Community Safety £10,000 e) Evesham Market Town Partnership £ 2,000 f) Trinity House £ 2,000 g) Local Contributions £ 2,000
Total raised £145,000
The Parish Council will carry out the relevant health and safety inspections and will be responsible for covering any on-going maintenance charges.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.