CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wychavon District Council
Executive Board, Tuesday 14 April 2009

Re-Commissioning of Home Improvement Agency Services

Approved Executive 1 paper

Executive Board approved this item on Tuesday 14 April 2009. Below is the council's own wording, with the papers it was decided on.

Item163

Resolved

Resolved 1. That participation in the joint re-commissioning of a new countywide Home Improvement Agency (for April 2010) be confirmed and that the Head of Housing & Customer Services be authorised to finalise the necessary contractual arrangements for the commencement of the new service. 2. That the new HIA be supported through the use of revenue and capital base budget contributions to be negotiated as part of the new HIA. 3. That support for the new HIA through the Council’s private sector grant capital programmes an added value service for customers be continued. 4. That the roll out and implementation of the Kick Start Scheme to Worcestershire be approved as set out in section 6 of the report.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 8 pages

Summary

This report;

1.1To inform Members of proposals to recommission the current Care & Repair agency services (also known as Home Improvement Agency (HIA) services) in partnership with Worcestershire County Council, Supporting People, the Worcestershire PCT and the six District Councils.

1.2To seek approval for the re-commissioning process and the continuing level of budgetary and staffing resource currently provided by the Council, to be contributed into a new single Countywide Home Improvement Agency.

1.3To update members regarding progress on developing the Kick Start scheme. This report recommends the Council’s participation in a new countywide Kick Start scheme.

Recommendations

That Members;

2.1Confirm the participation in the joint re-commissioning of a new countywide Home Improvement Agency (for April 2010) and to authorise the Head of Housing & Customer Services to finalise the necessary contractual arrangements for the commencement of the new service.

2.2Support the new HIA through the use of revenue and capital base budget contributions to be negotiated as part of the new HIA.

2.3To continue to support the new HIA through the council’s private sector grant capital programme as an added value service for customers.

2.4Approve the roll out and implementation of the Kick Start Scheme to Worcestershire as set out in section 6 of the report. 3. Implications & Impact

Councils Priorities and Community Plan Themes

• Council priority (4) of `STRONGER: Vibrant and inclusive communities with a strong economy’ and goal of `to increase the availability of affordable, decent housing’.

• Housing Strategy priorities of `promoting choice, quality & suitability’, `reducing homelessness’ and `reaching out to everyone in housing need’.

Resource Implications

Financial Implications Funding of the new Countywide HIA by the Council and its partner organisations has yet to be determined. However, the base budget currently included in the 5 year money plan for the Care & Repair (South Worcestershire) service is £30,400 p.a and the Council’s contribution towards the cost of the new service will not exceed the existing provision. A key objective of the re-commissioning is to attract additional funding as the enhanced services offered will meet key outcomes for partner agencies.

The delivery of the Kick Start loans and the cost of the scheme management and supervision within the proposed new HIA will be funded from the ring fenced regional funding that is allocated to the districts for the purposes of promoting Kick Start. The Council does currently offer a limited loans scheme under the existing Housing Grants and Renewal Policy. Whether we continue to do so would need to be reviewed when the Kick Start scheme was closer to starting.

Staffing Implications None at this stage

Risks The Council will not be in a position to deliver the enhanced level of services to Vulnerable older and disabled people unless it works in partnership with all of the main partners across the county.

Failure to implement the Kick Start scheme will mean that the Worcestershire authorities will be unable to access ring fenced regional funding that is allocated to them.

Delay in implementing Kick Start may lead to there not being an established alternative solution for home owners in the event the local authority capital becoming less available to support the allocation of local authority discretionary housing assistance grant.

Legal A new jointly commissioned contract will be entered into by the Council and appropriate revisions to policies will be made where required.

Property None

Diversity Impact Assessment To be undertaken as part of the re-commissioning process. 4. Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Re-Commissioning of Home Improvement Agency ServicesReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Re-Commissioning of Home Improvement Agency ServicesThis decision
  2. Re-commissioning of the Homeless Singles and Childless Couples Prevention ServiceApproved
  3. Recommissioning of the Single Persons Homeless Prevention ServiceNoted
  4. Recommissioning of the Worcestershire Home Improvement AgencyApproved
  5. Re-commissioning of the Home Improvement AgencyDecided

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies