Resolved
Resolved That the efficiency savings identified so far be noted.
Executive Board noted this item on Tuesday 7 July 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the efficiency savings identified so far be noted.
1.1The Way Forward Report, considered by the Executive Board, on 16th September 2008 identified the need to deliver ongoing savings of £1m over the next 2 to 3 years. Since that meeting, due to the economic downturn and as part of the budget process for 2009/10, it was agreed that a further £531,000 of budget savings would be made. The Way Forward update report, elsewhere on this Agenda, recommends that another £250,000 of efficiency savings be incorporated into revised budgets later in the year. In addition we have a requirement to report our efficiency gains under NI179.
1.2This report is the third in a series of reports that will be provided to demonstrate how the Council is progressing against its efficiency targets.
2.1It is recommended that the Executive Board notes the efficiency savings identified so far.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
Council Priority 5 – Successful: Delivering excellent and value for money services.
3.2Resource Implications
- financial implications - these are contained in the report.
- staffing implications – none. - risks – the economic downturn poses additional risks in terms of the Council’s ability to realise its efficiency targets. For example assets are not likely to realise values previously envisaged.
- legal – none.
- property – none.
4.1The Way Forward report identified the following approach to delivering ongoing savings of £1m:
• Shared Services and Joint Working
• Outsourcing
• Business Improvement
• Better Procurement
• Optimising our use of assets
• Energy reduction
• Additional income
4.2A further approach of using capital to deliver revenue streams is suggested in the Way Forward update.
4.3National Indicator NI179 measures ongoing cashable efficiency gains achieved by each council. There is an expectation that these gains will be 3% of the Council’s baseline expenditure currently (approximately £500,000) rising to 4% of baseline expenditure (approximately £670,000) in the future. Eligible efficiency savings for NI179 purposes should result from one of the following:
• Reduced inputs resulting in the same or improved outputs
• Increased demand being met within existing budgets
• Increased demand and better income collection
• Reallocation of inputs from a low priority area to a high priority areas
• Asset optimisation
• Withstanding the impact of inflation.
4.4Total ongoing efficiency savings achieved in 2008/09 and projected for 2009/10 are detailed in the chart below. Some of the NI179 savings will not result in bottom line savings for the Council whereas the required savings identified in the Way Forward report need to be real savings against our Money Plan projections. There clearly is some overlap but this will not always be the case. In addition, for completeness, the further efficiency savings identified as part of the budget savings (£531,000) during the budget process for 2009/10 and also those included in the Way Forward update report elsewhere on the Agenda are shown.
4.5Certain savings which were not previously counted towards our NI179 savings are now considered appropriate for NI179. New savings since the last report are shown in bold italics.
4.6The Council has promised to deliver at least £500,000 of the £1m ‘Way Forward’ efficiency savings by the end of the year 2009/10. So far £366,000 has been identified.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Efficiency SavingsReport | 5 pages | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.