Resolved
Resolved That the sum of £17,431 be allocated for improvements to the swing bridges in Vines Park , Droitwich.
Executive Board decided this item on Tuesday 13 October 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the sum of £17,431 be allocated for improvements to the swing bridges in Vines Park , Droitwich.
This report seeks Board approval to allocate a sum of money from the S106 contributions reserve towards improving the swing bridges at Vines Park in Droitwich.
That the sum of £17,431 be allocated for improvements to the swings bridges in Vines Park, Droitwich.
3. Implications & Impact
3.1Council Priorities and Promises This report supports Priority 3 ‘Improving Health and Well Being’ and Priority 4 ‘Vibrant and Inclusive Communities with a Strong Economy.’
3.2Resource Implications Financial Implications – Section 106 deposits are held in the Council Accounts under the heading of receipts in advance. The individual sums are released to fund projects once the Council is satisfied that their usage is in line with the terms of the relevant section 106 agreement. dmt .
Staffing Implications – No additional staff will be needed.
Risks - Not carrying out this work will potentially leave the Council open to claims for compensation e.g. where pedestrians slip and fall while using the swing bridges.
Legal – All contributions received by the Council must be spent in accordance with the terms of the relevant Section 106 Agreement.
Property – These works will enhance land and facilities within the Council’s portfolio. 4. Background
4.1An inspection of the four swing bridges in Vines Park has recently been carried out. This has identified a number of safety issues and improvements that need to be addressed e.g. new non slip surfacing, repair of decking, mechanical works etc These works are needed not only for the on-going use of the swing bridges as pedestrian crossings but also to ensure the smooth operation of these bridges once the canal opens to boaters.
4.2To carry out all the items identified in the report the approximate cost would be £68,000.
4.3Officers have recently met on site to discuss the items identified in the report. They consider that due to funding issues it is important to carry out the necessary repairs to the three main crossing points:-
Barge Lock Swing Bridge £25,750 Cross Way Swing Bridge £ 9,750 Fox Alley Swing Bridge £11,750
TOTAL ESTIMATED COSTS £47,250
The fourth bridge, known as Ricketts Lane (Annie’s) Bridge, would be locked open so that it could not be used until funding to repair it could be found.
4.4The above costs include some non essential items that could be done by volunteers or left in the short term.
4.5Officers have contacted the County Council to see whether they would be prepared to contribute towards the cost of these works. Due to the fact that a number of the paths crossing Vines Park are divorced footways the County have agreed to contribute £17,500. The County wish to ensure that the main crossing points are kept open to the public.
4.6British Waterways have identified £5,000 within the main canals restoration budget for the swing bridges.
4.7The Council currently holds £17,431 from the development at Rose Avenue Droitwich. This sum, under the terms of the Section 106 Agreement, needs to be spent on providing, improving or enhancing public open space in Droitwich. This money could be used to help facilitate the repairs needed.
4.8Officers are confident of being able to carry out all the essential repairs for the sum available i.e. £39,931. The work will be carried out this autumn/winter.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Application for Funding: Vines Park, DroitwichReport | 2 pages | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.