CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wychavon District Council
Executive Board, Tuesday 13 October 2009

Application for Funding - Vines Park, Droitwich

Decided Executive 1 paper

Executive Board decided this item on Tuesday 13 October 2009. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

Resolved That the sum of £17,431 be allocated for improvements to the swing bridges in Vines Park , Droitwich.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 2 pages

Summary

This report seeks Board approval to allocate a sum of money from the S106 contributions reserve towards improving the swing bridges at Vines Park in Droitwich.

Recommendations

That the sum of £17,431 be allocated for improvements to the swings bridges in Vines Park, Droitwich.

3. Implications & Impact

3.1Council Priorities and Promises This report supports Priority 3 ‘Improving Health and Well Being’ and Priority 4 ‘Vibrant and Inclusive Communities with a Strong Economy.’

3.2Resource Implications Financial Implications – Section 106 deposits are held in the Council Accounts under the heading of receipts in advance. The individual sums are released to fund projects once the Council is satisfied that their usage is in line with the terms of the relevant section 106 agreement. dmt .

Staffing Implications – No additional staff will be needed.

Risks - Not carrying out this work will potentially leave the Council open to claims for compensation e.g. where pedestrians slip and fall while using the swing bridges.

Legal – All contributions received by the Council must be spent in accordance with the terms of the relevant Section 106 Agreement.

Property – These works will enhance land and facilities within the Council’s portfolio. 4. Background

4.1An inspection of the four swing bridges in Vines Park has recently been carried out. This has identified a number of safety issues and improvements that need to be addressed e.g. new non slip surfacing, repair of decking, mechanical works etc These works are needed not only for the on-going use of the swing bridges as pedestrian crossings but also to ensure the smooth operation of these bridges once the canal opens to boaters.

4.2To carry out all the items identified in the report the approximate cost would be £68,000.

4.3Officers have recently met on site to discuss the items identified in the report. They consider that due to funding issues it is important to carry out the necessary repairs to the three main crossing points:-

Barge Lock Swing Bridge £25,750 Cross Way Swing Bridge £ 9,750 Fox Alley Swing Bridge £11,750

TOTAL ESTIMATED COSTS £47,250

The fourth bridge, known as Ricketts Lane (Annie’s) Bridge, would be locked open so that it could not be used until funding to repair it could be found.

4.4The above costs include some non essential items that could be done by volunteers or left in the short term.

4.5Officers have contacted the County Council to see whether they would be prepared to contribute towards the cost of these works. Due to the fact that a number of the paths crossing Vines Park are divorced footways the County have agreed to contribute £17,500. The County wish to ensure that the main crossing points are kept open to the public.

4.6British Waterways have identified £5,000 within the main canals restoration budget for the swing bridges.

4.7The Council currently holds £17,431 from the development at Rose Avenue Droitwich. This sum, under the terms of the Section 106 Agreement, needs to be spent on providing, improving or enhancing public open space in Droitwich. This money could be used to help facilitate the repairs needed.

4.8Officers are confident of being able to carry out all the essential repairs for the sum available i.e. £39,931. The work will be carried out this autumn/winter.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Application for Funding: Vines Park, DroitwichReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Application for Funding - Vines Park, DroitwichThis decision
  2. Application for use of Section 106 fundingAgreed
  3. Application for Funding for land at Holloway Hill, PershoreAgreed
  4. Application for Funding for Modifications to the HEP Fish Pass to Enable Passage of Canoes on the River Avon, PershoreAgreed
  5. Application for funding for the development of the sports ground in BredonDecided
  6. Application for Funding for Improvements to the Recreation Ground in OffenhamDecided

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open