Extension of Garden Waste Contract

Agreed Executive 1 paper

Executive Board agreed this item on Friday 8 January 2010. Below is the council's own wording, with the papers it was decided on.

Item119

Resolved

It was agreed that these residents should be told of this and relevant Ward Councillors would be informed of the broad locations of affected properties. Councillor Mrs E B Tucker suggested that whilst Wychavon’s charge for the service was the lowest per collection in the County, this did not include the cost of disposal, which was borne by Council tax payers across the County. It was suggested that the Council should support home composting as a way of supporting the reduction in landfill that this offered. Councillor Mrs Mackison responded that the service was consistent with the County Council’s waste management strategy to keep as much waste as possible out of landfill. In response to a query, [name removed], Deputy Managing Director, confirmed that the increase in contract price referred to in paragraph 4.3.2 of the report would be a decrease if the consumer price index ( c.p.i ) was a negative figure over the year. Resolved 1. That the proposal to increase the capacity of the chargeable garden waste collection service from 7500 customers to 9000 customers be approved. This service to be based on the principles set out in paragraphs 4.3 to 4.5 of the report: - maximum number of households expanded to 9000; - existing collection costs payable to FOCSA in 2010-11 to increase to £198,593 pa plus annual increase/decrease using c.p.i.; - service available district wide except for areas with very low levels of demand and time taken to collect is unproductive and 40 existing customers in areas of low demand who would change to fortnightly collection with residual waste; - payment by direct debit for all new customers; - redesign of round to be more efficient; - Assisted collection of garden waste wheelie bins to continue. That an additional £29,000 for the purchase of the garden bins be added to the Council’s capital programme for 2009/10.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 3 pages

Summary

1.1This report updates the Board on the garden waste collection service and sets out a proposal to extend the capacity of the service during 2010 from 7500 to 9000 customers at no additional revenue cost to the Council.

Recommendations

2.1That the Executive Board approves the proposal to increase the capacity of the chargeable garden waste collection service from 7500 customers to 9000 customers. This service will be based on the principles set out in paragraphs 4.3 to 4.5 of this report.

2.2That an additional £29,000 for the purchase of the garden bins be added to Council’s capital programme for 2009/10.

3. Implications & Impact

3.1Council Priorities and Community Plan Themes

Priority 2 Goal 1: By extending the Garden waste service it is projected that up to another 1,800 customers can benefit from the collection of garden waste for recycling. The extension of the garden waste service could add an extra 1.3% to the current recycling/composting rate at no extra revenue cost to the Council.

3.2Resource Implications

Financial Implications – Set out within the report and will be incorporated in the setting of the 2010/11 budget.

Staffing Implications – It is anticipated that the extra administration and finance work can be contained within existing Council staff

Page 1 of 3 resources. The direct delivery of the service will be provided by staff employed by our contractor Focsa Services (UK) LTD.

Risks – The proposal outlined in this report is for the service to be extended to provide the capacity for 9000 households (17.5% of homes). The take up level is difficult to accurately predict and inevitably creates a number of potential risks. Firstly if the Council attracts a lower take up level our income will be lower than our estimates and this may not cover fully our additional contractor costs. Historically we have had 95% take up so this is unlikely plus the Council already have 1,100 households on an expression of interest list. On the positive side it would significantly increase the Council’s recycling and composting rates.

Legal – the waste and recycling contract tender process was completed in line with UK and European procurement laws.

Property - None

Background

4.1The garden waste service started Easter 2008 with up to 7,500 bins available on a first come first served basis. To date there are 7,200 bins in use. There are only two collection areas with availability left Hartlebury & Ombersley and Drakes Broughton parishes where the take up has slowed down as we reach a natural saturation point with little potential for growth.

4.2There are, however, 1,100 households on an expression of interest list that has been compiled via the website, in the shops and over the phone. The first full year of operation has shown that the number of customers not renewing the service has to date been only 142. This is a very low rate, especially given the very difficult economic conditions, and is an indication of the value given by customers to the service. If this trend continues very few people on the expression of interest list are likely to receive the service in the next few years. Members will be aware that this is generating some public dissatisfaction. The Waste Implementation Team at it’s review meeting in the summer recommended that options to expand the service should be investigated.

4.3Negotiations have been taking place with Focsa to come up with a cost effective expansion of the service. Following numerous meetings a proposal based on the following criteria has been developed as a long term garden waste proposal:

1. The maximum number of households is expanded to 9,000 (the capacity of two collection vehicles) on a first come first served basis. Households registered on the expression of interest list will be given first option.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extension of Garden Waste ContractReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Extension of Garden Waste ContractThis decision
  2. Planning Application Ref W/22/01945/HP. The Cottage, Chapel Lane, Westmancote, Bredon, Tewkesbury, GL20 7ER. Alteration, refurbishment and extension of residential dwelling, including alterations to garden boundary treatment and provision of new vehicle access off Chapel Lane. Mr Adam DrysdaleApproved
  3. Planning Application Ref 19/00116/HP. 11 Wesley Gardens, Pebworth, Stratford Upon Avon, CV37 8DJ. Two storey extension to rear or house and conversion of garage to habitable room. Mr and Mrs A AdamsApproved
  4. Planning Application Ref 18/01628/HP. 2 Broadway Villas, Farm Street, Fladbury, Pershore, WR10 2QD. Rear extension and garden outbuilding (part retrospective). Mrs Sharon PatersonApproved
  5. Planning Application Ref W/12/00538/PN. Extension to cafeteria/office accommodation and additional canopy to cover existing retail area. St Peters Garden Centre, Broomhall, Norton, Worcester, WR5 2NY. St Peters Garden CentreApproved
  6. Planning Application Ref W.11.01709.PP. Proposed rear extension to form orangery and internal alterations. 8 Lifford Gardens, Broadway, WR12 7DA. B Parmenter. 06.Approved

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies