Wychavon District Council

Impact of the Recession on 2010/11 Funding - Revenues and Benefits Shared Service

Noted Committee 1 paper

South Worcestershire Shared Services Partnership Joint Committee noted this item on Monday 19 April 2010. Below is the council's own wording, with the papers it was decided on.

Item100

Resolved

Resolved (1) That the current financial forecast for the Shared Service and ongoing impact of the recession on the Revenues and Benefits Shared Service be noted. (2) That the position with regard to the additional Administrative Subsidy Grant from the Department for Work and Pensions be noted. (3) That delegated authority be given to the Head of Shared Service, Revenues and Benefits, in consultation with each participating authority’s Section 151 Officers, to manage the process of arranging additional resources as set out in section 4 of the report.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to South Worcestershire Shared Services Partnership Joint Committee, 5 pages

Summary

The purpose of this report is to appraise the Joint Committee of the continuing impact of the recession on the revenues and benefits service.

Recommendations

2.1That the Joint Committee note the current financial forecast for the shared service and the ongoing impact of the recession on the revenues and benefits service.

2.2That the Joint Committee note the position with regard to the additional Administration Subsidy Grant from the Department for Work and Pensions (DWP).

2.3That the Joint Committee delegate authority to the Head of Shared Service, in consultation with Section 151 officers, to manage the process of arranging additional resources as indicated.

Background

3.1An increase in demand on both benefit claims and revenues enquiries started to impact the shared service late in 2008. Benefit, change in circumstances have risen by 40% since April 2009 and Benefit, new claims by 22%. However since August 2009 new claims have risen by 30% showing that the rate of increase continues to rise.

3.2As a result of rising demand nationally, the DWP gave all authorities additional money in 2009/10 through the Administration Subsidy Grant. For the shared service this totalled £272,880 split between the three authorities. The DWP announced in December 2009 the amounts each authority will receive for 2010/11. The total for the shared service is £144,693. This is clearly much less than the current year and, against a backdrop of rising demand and increased caseload, much less than we were expecting. We have discovered that the methodology used by the DWP has disadvantaged the shared service whilst at the same time advantaged other authorities. We have remonstrated with the DWP who have stated that they are not prepared to look at anomalies in each local authority or take account of our particular set of circumstances. We are currently still in dialogue with the DWP on this matter

3.3When the shared service business case was written a resource model was developed based on workloads in 2006. As a result, the original workforce from the three legacy sites was reduced by 27% from 130 to 95 FTE. The intention of this approach was to drive out efficiencies from the installation of a single IT system and working from a single base of operations so that the reduced number of staff could deal with demand but eliminate any unnecessary capacity.

3.4Unfortunately the shared service has never been able to test the balance between demand and resources effectively as workloads started to increase as a result of the economic slowdown during 2008. This meant that, despite huge efficiencies being achieved by the shared service, the available capacity has been swamped by such a massive rise in workload.

4 FINANCIAL FORECAST

4.1Contractors

4.2In order to avoid performance deteriorating as a result of the continued onslaught of high levels of demand it has been necessary to commit the following additional resources for the coming year beginning 1 April 2010;

4 x Benefits contractors to end June 2010 - £45,510

5 x Revenues contractors to end May 2010 - £38,332

Capita remote benefits processing - £10,000

Capita Benefit Appeals - £1,250

Total £95,092

4.3Existing contractors have currently had their contracts extended up to the end of May 2010 for revenues and June 2010 for benefits. Depending on how quickly a kick- start 2 initiative can be organised, there is a strong likelihood that the shared service will need to extend employment for these contractors still further. This is because it is unlikely that new staff will be able to process sufficient quantities of work by May / June to allow us to significantly reduce the number of contractors without the risk of a backlog developing. The cost of the current number of contractors per month is;

Benefits £15,170

Revenues £19,166

4.4Kick-start

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Impact of the Recession on 2010/11 Funding: Revenues and Benefits Shared ServiceReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Impact of the Recession on 2010/11 Funding - Revenues and Benefits Shared ServiceThis decision
  2. Impact of the Recession on the Revenues and Benefits Shared ServiceNoted

More from Wychavon South Worcestershire Shared Services Partnership Joint Committee

All decisions
MeetingDecisionOutcome
11 Apr 2011 Minutes of the previous meetingResolved That the Minutes of the meeting of the Joint Committee held on Monday 24 January 2011 be approved as a corre... Approved Open
11 Apr 2011 Annual External Audit Plan 2010/11Resolved That the Audit Approach Memorandum for 2010/11 be approved. Approved Open
11 Apr 2011 DWP Performance LetterResolved That the letter from the Department of Works and Pensions be noted. Noted Open
11 Apr 2011 Performance MonitoringResolved 1. That the service performance of the Revenues and Benefits Shared Service Organisation be noted, and that ... Noted Open
11 Apr 2011 Update ReportResolved 1. That the achievement of Customer Service Excellence accreditation be noted. 2. That the progress of devel... Noted Open