South Worcestershire Shared Services Partnership Joint Committee noted this item on Monday 19 April 2010. Below is the council's own wording, with the papers it was decided on.
Resolved (1) That the “lessons learned” from the establishment of the Worcestershire Hub Shared Service as attached at appendix A of the report be noted. (2) That the progress of the development of the Worcestershire Hub Shared Service be noted . (3) That the improved performance of the Worcestershire Hub Shared Service as attached at Appendix B of the report be noted . (4) That the work currently underway on the Customer Strategy and the recent consultation results be noted .
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Report to South Worcestershire Shared Services Partnership Joint Committee, 11 pages
Summary
The purpose of this report is to provide the Joint Committee with an update regarding the progress of the Worcestershire Hub Shared Service (WHSS) and operational performance in particular.
Recommendations
2.1That the Joint committee notes the "lessons learned" from the establishment of the Worcestershire Hub Shared Service (Appendix A).
2.2That the Joint Committee notes the progress of the development of the Worcestershire Hub Shared Service.
2.3That the Joint Committee notes the improved performance of the Worcestershire Hub Shared Service (Appendix B).
2.4That the Joint Committee notes the work underway on the Customer Strategy and the recent consultation results.
3. PROGRESS
3.1As reported to the Joint Committee in January, the project associated with the establishment of the Worcestershire Hub Shared Service is complete. A session to capture lessons learnt has been held and a Project Closure Report prepared. This is detailed at Appendix A. The Lessons Learnt will be shared with the WETT Programme Management Group (PMG).
3.2Key recommendations from the Lessons Learnt review for other shared services to consider include providing clarity, carefully planning and communicating the key steps and milestones associated with:
(i) Creation of the legal entity, particularly ensuring resources are in place to complete the legal agreement; (ii) Completion of the TUPE Transfer of staff into the share service organisation and what this means. This needs to recognise a move to common terms and conditions needs to be justified as Economic, Technical or Organisational (ETO);
(iii) Providing accommodation for any co-located teams;
(iv) Providing a shared ICT network infrastructure as this is not universally in place across the county;
(v) Understanding the relative accountabilities and responsibilities of Joint Committee, Management Team and Management Board;
(vi) Carefully consider the potential implications of applying a recruitment freeze (in order to minimise redundancies);
(vii) Take every opportunity to increase customer self service as early as possible;
(viii) Ensure the host authority has access to HR records for staff.
3.3Further visits to the Contact Centre have been hosted. Feedback from the visits has been very positive. Further visits for officers and members are planned.
3.4Regular communications continue to be issued to members and officers in the participating authorities to ensure they have up to date information regarding call wait times in particular.
3.5The "joint" scrutiny of the Worcestershire Hub, as initiated by Worcestershire County Council is underway. The Task Group includes representation from all partner authorities. The group have received a presentation regarding the Hub, visited customer centres across the county, spoken to service areas and partner representatives and are currently probing specific areas e.g. governance and performance, as defined during a session to define the framework of the exercise.
3.6The Worcestershire Hub Shared Service Management Board meet every 6 weeks and have meetings scheduled for the remainder of 2010.
3.7The Management Board have recently reviewed the Worcestershire Hub shared Service Development Plan. The focus of future meetings will be the ongoing development of the Hub.
3.8The Worcestershire Hub Management Board proposes the use of six Key Performance Indicators (KPIs) for the Shared Service. The reporting against these indicators will include a commentary and supporting information as appropriate. It has been agreed with Worcester City Council to continue reporting "Abandoned Calls" as a percentage in addition to the six KPIs. 3.9. The six KPIs are split into quantitative and qualitative measures. They are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South Worcestershire Shared Services Partnership Joint Committee at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingResolved That the Minutes of the meeting of the Joint Committee held on Monday 24 January 2011 be approved as a corre...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.