Wychavon District Council
Executive Board, Tuesday 13 July 2010

Car Park Extension - Milestone Ground Broadway

Agreed Executive 1 paper

Executive Board agreed this item on Tuesday 13 July 2010. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

Resolved 1. That the Deputy Managing Director in consultation with the Portfolio Holder for Resources be authorised to agree terms with Broadway United Football Club for the transfer of land back to the Council under provisions made under the 1996 sale agreement. 2. That the enlargement of the Milestone Ground car park be approved. 3. That the Development Manager be authorised to submit any necessary applications needed to facilitate the extension of car park including a Planning Application under Article 3 of the Town and Country Planning General Regulations 1992. 4. That the Deputy Managing Director in consultation with the Portfolio Holder for Resources is authorised to accept a tender for the works subject to the overall scheme budget being met.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 2 pages

Recommendations

2.1That the Deputy Managing Director in consultation with the Portfolio Holder for Resources is authorised to agree terms with Broadway United Football Club for the transfer of land back to the Council under provisions made under the 1996 sale agreement.

2.2That the Executive Board approves the enlargement of the Milestone Ground car park and recommends to Council that an addition of £150,000 is made to the Capital Programme.

2.3That the Development Manager be authorised to submit any necessary applications needed to facilitate the extension of car park including a Planning Application under Article 3 of the Town and Country Planning General Regulations 1992.

2.4That the Deputy Managing Director in consultation with the Portfolio Holder for Resources is authorised to accept a tender for the works subject to the overall scheme budget being met.

3. Implications & Impact

3.1Council Priorities and Community Plan Themes

To support local businesses and village services – Additional parking capacity in Broadway will benefit traders. 3.2 Resource Implications

3.2.1. Financial implications: The construction of the extra car park along with new surface water drainage, car park machines and lighting should cost in the region of £150,000. This can be financed from uncommitted LABGI monies.

3.2.2. Staffing implications: Can be met from existing resources by rescheduling work within department.

3.2.3. Risks: There is a risk that costs increase due to unknown ground conditions and other construction and Planning risks. These will be managed to limit the risk and the Council will have the opportunity to reduce the specification of the works if necessary.

3.2.4. Legal implications: All legal matters will be dealt with internally.

3.3Diversity Impact Assessment

Not Required

4. Supporting Information

4.1Under the terms of the original sale of Council land to Broadway United Football Club in 1996, an area of land was identified as being suitable for an extension to the Milestone Ground car park. An option to repurchase this land at a later date was therefore included within the conveyance.

4.2Members will be aware that Broadway is showing increasing need for additional car parking capacity as its visitor economy continues to expand.

4.2Consequently the Council has recently served notice on Broadway United Football Club to reacquire land adjacent to the Milestone Ground car park which can be used to provide additional parking. The land amounting to just under 1 acre will be re-acquired at agricultural land values with the Club and Council meeting their own legal costs.

4.3It is proposed to construct approximately 100 new car park spaces along with lighting, signage etc on the land to be reacquired from the club subject to the necessary approvals.

4.4At this stage the scheme costs cannot be accurately projected due to ground, flooding and planning risks but previous projects suggest that this scheme can be completed for approximately £150,000. If given approval detailed surveys and investigations will be carried out to establish accurate costings.

4.5The Club has asked if the Council could provide additional parking spaces on the Club’s land at the Club’s cost as part of the works. This would be for Club use only and would be at the clubs cost.

4.6Once the Planning Application is made it will be possible to fix a timescale for the works but it is hoped that works can commence later this year and be complete in time for the next tourist season.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Car Park Extension: Milestone Ground BroadwayReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Car Park Extension - Milestone Ground BroadwayThis decision
  2. Ricketts Lane Car Park, Droitwich: change from short to long stayApproved
  3. Waitrose and High Street Car Park, Droitwich: LeaseDecided
  4. Pershore Station car park and footbridgeAgreed
  5. Planning Application Ref 21/02226/FUL. Car Park Off Swan Lane And, 70-72 High Street, Evesham. Demolition of existing building to facilitate comprehensive redevelopment of the site. Eros Properties LimitedApproved
  6. Planning Application Ref 21/02227/FUL. Car Park Off Swan Lane And, 70-72 High Street, Evesham. Reconfiguration of existing retained retail unit to provide 3 retail units, remedial works following demolition of existing building and provision of access and private car park. Eros Properties LimitedApproved

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies