Resolved
Resolved That the transfer of the allocated £5000 grant from Stock and Bradley Parish Council to the Environment Agency as a contribution towards the Household Level Entry Scheme for Stock and Bradley be noted.
Executive Board noted this item on Tuesday 13 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the transfer of the allocated £5000 grant from Stock and Bradley Parish Council to the Environment Agency as a contribution towards the Household Level Entry Scheme for Stock and Bradley be noted.
1.1This report informs the Executive Board of the decision of the Deputy Managing Director and Portfolio Holder for the Environment and Contracted Services to transfer the previously allocated £5000.00 grant to Stock and Bradley Parish Council under the Parish Flood Alleviation Support Grant Scheme (PFASGS) to the Environment Agency as a contribution towards the Household Level Entry Scheme for Stock and Bradley.
2.1That the Executive Board notes the transfer of the allocated £5,000 grant from Stock and Bradley Parish Council for the purposes contained in the report.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
Greener – To aid the recovery from flooding and reduce the impact from future floods and Strong Environment – deliver at least one flood initiative each year.
3.2Resource Implications
- financial implications - as referred to within the report. It is confirmed that the PFASGS is being funded from money held in the Council’s Earmarked Reserves. (AMW).
- staffing implications - None - risks - Supporting these schemes will contribute to reducing the flood risk within the Parish.
- Legal – None
- Property – None
3.3Diversity Impact Assessment
Not needed
4.1The Executive Board will be aware that approval was given at their meeting on 6th January 2009 to a number of small projects to reduce the risk of flooding in a number of different ways. This approval was subsequently updated in January 2012 by delegating the allocation of any other resources becoming available to the Deputy Managing Director in consultation with the Portfolio Holder for the Environment and Contracted Services.
4.2The Engineering Consultancy Team has been working with the Parish Council, County Highways and Environment Agency Officers to come up with flood alleviation works at Stock and Bradley. A number of notional ideas have been considered but after investigation no viable scheme is possible. The Environment Agency has suggested that funding may become available shortly to carry out a house level entry scheme. This entails providing flood prevention products to individual households that qualify under the scheme rules.
4.3Community engagement and external funding will be a prerequisite to any application and hence the need to reallocate the existing grant to the funding process. The parish Council will engage with us and will need to consult with its residents to establish the exact number of households within Stock and Bradley that are eligible for protection devices.
4.4This is a similar scheme to those that have been successfully delivered at Beckford and Harvington. The Environment Agency will make the application for funding based on the results of the Parish Council consultation. Once approval is given Wychavon’s Engineers will need to engage an Independent Consultant to risk assess each property and following that stage will arrange for specialist manufacturers to provide competitive quotations for the home owners.
4.5The time scale is very much dependant on the funding route the Environment Agency adopt but it is hoped that if the application is successful then the works could be completed this time next year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Flood Restoration Funds: Reallocation of Parish Flood GrantReport | 2 pages | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.