Resolved
Resolved That £15,000 of the 106 money from D1/1123 Land of Three Springs Road Pershore J S Bloor [Tewkesbury] Ltd be released to allow the path work to be carried out.
Executive Board decided this item on Tuesday 10 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That £15,000 of the 106 money from D1/1123 Land of Three Springs Road Pershore J S Bloor [Tewkesbury] Ltd be released to allow the path work to be carried out.
1.1Several lengths of tarmac path in Abbey Park are deteriorating to the point where there is concern for public safety. The surfaces have worn away in places leaving trip hazards.
1.2Quotes have been obtained for the necessary remedial work and the best price is £17607.83.
1.3This report is requesting £15,000 of 106 monies to be released with the remaining £2607.83 being met from Parks revenue budget to enable this essential Health and Safety work to be carried out next month.
2.1That £15,000 of the 106 money from D1/1123 Land of Three Springs Road Pershore J S Bloor [Tewkesbury] Ltd be released to allow the path work to be carried out.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
This work will ensure that the paths are brought up to a good standard and will be fit for use for the future – an estimate 20 years of wear.
3.2Resource Implications
This section should include:
- financial implications - That £15,000 be released from D1/1123 106 money and the remaining £2607.83 paid from existing parks budget. SRS - staffing implications – none – work will be done as one off basis by Contractor.
- risks – there has already been one incident where a member of the public has tripped on the uneven surface of the path..
- Legal – we have a duty of care to all users of our facilities. Possible claims for compensation may be made where accidents occur due to path surfaces being worn and not properly maintained. All contributions received by the Council must be spent in accordance with the terms of the relevant Section 106 Agreement.
- property – repairing the path for the long term makes best economic sense.
3.3Diversity Impact Assessment – all ages and backgrounds of people both locals and visitors use Abbey Park.
4.1The need for repairs to the paths in Abbey Park in Pershore were identified by the Council’s Parks Officer and a specification for the necessary repairs was prepared by WDC Engineers in December 2011.
4.2Quotes have been obtained this year and work is scheduled to be carried out in early July 2012 before the school summer holidays commence.
4.3Damage to the paths has been caused by the alternation of excessively hot and dry weather and the -19 degree temperatures of recent winters. Also the existing paths do not have sufficient load bearing material in the base layer to take the wear and tear they encounter.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Abbey Park Pershore: remedial work required on the tarmac pathwaysReport | 2 pages | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.