Resolved 1. That the Pershore Northern Link feasibility report be endorsed and the implementation of the project be fully supported. 2. That further confirmation be sought from the County Council of its endorsement of the significance of the delivery of this important project. 3. That the Head of Community Services, in consultation with the Executive Board member for Economy, Regeneration and Flooding and the Executive Board member for Resources, submit an outline business case pro forma for the Pershore Northern Link to the Worcestershire Local Transport Body. 4. That a “round table” meeting be arranged with key partners, at the earliest opportunity, once the final feasibility study has been received.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Halcrow is about to publish a feasibility report for the proposed Pershore Northern Link bridge and road (also referred to as Keytec link) which would connect the Wyre Piddle by pass roundabout on A44 to the Keytec roundabout on Wyre Road. This report summarises the study and identifies a potential source of funding which could help towards its implementation.
Recommendations
2.1The Executive Board endorses the Pershore Northern Link feasibility report and fully supports the implementation of the project.
2.2Seek further confirmation from the County Council of its endorsement of the significance of the delivery of this important project.
2.3That the Head of Community services in consultation with the Executive Board members for Economy, Regeneration and Flooding and Resources submit an outline business case pro forma for the Pershore Northern Link to the Worcestershire Local Transport Body.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes – Supports all three of the council’s priorities (Strong Economy, Strong Environment and Strong Communities) by providing the necessary infrastructure improvements which will help to retain and grow businesses and jobs, facilitate new housing growth and reduce traffic congestion at key locations.
3.2Diversity Impact Assessment – To be produced
3.3Resource Implications
E:\moderngov\data\published\Intranet\C00000314\M00003764\AI00023011\$qtwoy2nh.doc Financial Implications – The feasibility report sets out in detail the estimated costs for implementing the Pershore Northern Link. In partnership with the Worcestershire LEP, County Council, developers, local councils (Pershore, Pinvin and Wyre Piddle) and the emerging Worcestershire Local Transport Body a funding package now needs to be developed. (SS)
Staffing Implications – The implementation phase is expected at this stage to be managed by existing staff.
Risks – Securing sufficient funds for the implementation of the Pershore Northern Link is not guaranteed but the study has at least provided a realistic assessment of what is required and a number of options e.g. developer contributions, Worcestershire Local transport Body has been identified
Legal – None at this stage.
Property – None.
Background
4.1Halcrow is about to publish a feasibility report for the proposed Pershore Northern Link bridge and road (also referred to as Keytec link) which would connect the Wyre Piddle by pass roundabout on A44 to the Keytec roundabout on Wyre Road. The study was commissioned by Worcestershire County Council and funded by Crown House Developments (through their S106 contribution arising from the planning approval for Keytec phase 2) and Wychavon District Council. When published the report will be a public document and will be made available on our website.
4.2The feasibility report identifies a preferred bridge and road to an outline design stage and estimates likely construction costs. In getting to this stage Halcrow has completed the following range of activities, including:
• Reviewed environmental constraints
• Prepared a Geotechnical desk study
• Design criteria including highway and network rail requirements (allows for duelling of tracks and potential electrification)
• Identified key constraints including public rights of way, statutory undertakers plant and equipment and maintenance strips
4.3The final feasibility report identifies a preferred route alignment and 3 styles of bridge construction (integral concrete bridge, integral steel bridge and precast concrete arch). The costs identified below includes estimated costs for further survey works (environmental, topographical and ground investigation), bridge and road construction, preparation and supervision costs plus an estimated cost for Network Rail’s costs (£300,000).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.