Item10
Resolved
It was agreed that these would be taken into account as far as possible whilst ensuring the viability of the project. It was then RECOMMENDED to COUNCIL 1. That the revised project cost estimates be supported and that Council approves an addition to the Capital Programme of up to £61,000 for the project, financed from New Homes Bonus monies. Resolved 2. That the project timeline for the development of the building at Appendix A to the report and the need to bring on board a provider to manage the property and occupants on behalf of the council be noted. 3. That authority be delegated to the Director of Housing and Communities in consultation with the Portfolio Holder responsible for Housing in respect of any adjustments to the final spend as appropriate. 4. That the unusual times currently being experienced and that the project may be placed on hold or delayed be noted.