Wychavon District Council
Executive Board, Wednesday 19 November 2025

UK Shared Prosperity Fund and Rural England Prosperity Fund update

Noted Executive 3 papers

AI summaryWychavon Executive Board notes midterm report on UK Shared Prosperity Fund and Rural England Prosperity Fund; 38% of UKSPF budget spent by September 2025 with no further funding confirmed after 2025/26.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted UKSPF and REPF delivery update for April to September 2025
Money£499,756 of £1,308,276 UKSPF spentREPF £245,746 budget with zero spent at midterm; reserve top-up of £121,708
What happens nextAwait government funding announcementCouncil to be updated when future funding position confirmed
Who it affectsAll Wychavon wardsBusiness support, place, skills and community projects

What was decided

The Executive Board noted the midterm report on UKSPF and REPF delivery for April to September 2025. Report P6, P5

Why

To update the Board on progress of the UKSPF and REPF programmes halfway through the 2025/26 financial year, with a midterm report already submitted to the Ministry of Housing, Communities and Local Government. Report P5, P7

What happens next

Officers will await government announcements on future funding and report back to Council once the position is confirmed, as no further UKSPF or REPF money has been allocated beyond 2025/26. Report 3.3

Projects will continue submitting quarterly reports, with all UKSPF and REPF funding forecast to be spent by the end of March 2026. Report P7, 3.2, 4.3

The money

  • £1,308,276 Total UKSPF budget for Wychavon, April 2025 to March 2026 Report P7
  • £499,756 UKSPF spend at midterm, 38% of total UKSPF budget Report P7
  • £245,746 Total REPF budget for Wychavon, April 2025 to March 2026 Report 3.2
  • £121,708 Additional funding from Wychavon reserves for the Wychavon Rural Fund Report 3.2

Implications

  • Financial: Risk of underspend, mitigated by an approved delivery plan, quarterly project reports and continuity from the previous programme. Report P7, 4.3
  • Financial: No further UKSPF or REPF funding has been confirmed beyond 2025/26, which may reduce or end business support, place, skills and community projects that have relied on the funds for four years. Report 3.3
  • Risk: Risk of partner misuse of monies is mitigated by the Council's procurement strategy and Contract Procurement Rules. Report 4.4
  • Equalities: Screening impact assessment found no adverse impacts on equality groups and identified likely positive impacts on rural areas, health and wellbeing, communities, town centres and the natural environment. Report 5.4, 5.5

Who and where

  • Residents and businesses across all Wychavon wards Report P2, P7
  • Recipients of UKSPF-funded business support, place, skills and community projects Report 3.3
  • Wychavon Rural Fund applicants and rural communities Report 3.2, 5.5

Timeline

  • April 2025 to September 2025: Reporting period covered by the midterm report Report P5, P6
  • End of October 2025: Midterm reports on UKSPF and REPF submitted to the Ministry of Housing, Communities and Local Government Report P7, 3.2
  • Early November 2025: Further Wychavon Rural Fund appraisal panel held Report 3.2
  • March 2026: End of the 2025/26 financial year; all UKSPF and REPF funding forecast to be spent by this point Report P7, 3.2
  • 2026/27: Any remaining Wychavon Rural Fund money to be allocated Report 3.2

Plain English for the jargon

  • UKSPF: UK Shared Prosperity Fund, a central government programme supporting local growth
  • REPF: Rural England Prosperity Fund, a government programme for rural areas
  • MHCLG: Ministry of Housing, Communities and Local Government
  • Wychavon Rural Fund: The local delivery scheme for REPF in Wychavon
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item38

Resolved

Resolved That the midterm report for the period April to September 2025 be noted.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 3 pages

EXECUTIVE BOARD 19th NOVEMBER 2025

UK SHARED PROSPERITY FUND AND RURAL ENGLAND PROSPERITY FUND UPDATE Relevant wards: All wards Portfolio holders: Cllr Richard Morris, Portfolio Holder for Economic Growth and Tourism

Head of Service: Shawn Riley

Contact officer: Elspeth McQueen If you have any questions about this report, please contact the portfolio holder or the contact officer.

1. Purpose and summary 1.1 To provide a midterm report on the delivery of the UK Shared Prosperity Fund (UKSPF) and the Rural England Prosperity Fund (REPF) Programmes for the period of April 2025 – September 2025.

2. Recommendations 2.1 The Board notes the midterm report for the period of April 2025 – September 2025.

3. Background 3.1 The total UKSPF budget for Wychavon for April 2025 – March 2026 is £1,308,276. A midterm report was submitted to the Ministry of Housing, Communities and Local Government (MHCLG) at the end of October reporting spend of £499,756 (38% of the total budget). All funding is forecast to be spent by year end. A list of the projects being supported is attached at Appendix A.

3.2The total REPF budget for Wychavon for April 2025 – March 2026 is £245,746. A midterm report was submitted to the Ministry of Housing, Communities and Local Government (MHCLG) reporting zero spend. The funding is being used to deliver the Wychavon Rural Fund therefore spend is weighted towards year end. All REPF funding has now been allocated and is forecast to be spent by year end. A list of the projects allocated funding under the Wychavon Rural Fund can be found at Appendix B. In addition to the REPF budget, a further £121,708 has been allocated from Wychavon reserves; 36% of which is also committed with another appraisal panel taking place early November. The Wychavon Rural Fund is now closed to new applications for this year and any remaining funding will be allocated in 2026/27.

3.3HM Government have confirmed that there will be no further UKSPF or REPF funding allocated beyond 2025/26 financial year. Without external funding support the business support, place, skills and community projects that have received investment via our UKSPF and REPF programmes over the past 4 years may not be available or significantly reduced. We await government announcements on future funding and will report back to Council when we have confirmation of the position.

4. Implications and impact What are the financial/resource implications? 4.1 A management and administration budget is built into the UKSPF Programme. The 25/26 programme will continue to be managed by the UKSPF team led by Elspeth McQueen.

What are the risks? 4.2 An underspend could occur. A delivery plan was submitted and approved at the March 2025 Board detailing how the funding would be used. All projects are required to provide quarterly reports to review progress made. Furthermore, all projects were running as part of the previous programme so there has been no lag time in the start of the delivery.

4.3The targeted outputs and outcomes will not be delivered. Outputs and outcomes submitted are based on deliverable and achievable targets set in agreement with the WDC staff and partners responsible for delivery. Outputs and outcomes will continue to be monitored closely through quarterly reports.

4.4There is a risk that monies will not be used effectively or misused by delivery partners. This will be mitigated by the Council’s procurement strategy, which is governed by the Council’s Contract Procurement Rules, requiring compliance with public sector procurement requirements. 5. Outcomes of the Impact Assessment Privacy 5.1 The risk of data compiled by partner organisations to evidence outputs and outcomes being submitted to Wychavon District Council is identified. This is mitigated by site visits to view the data instead of requests for it to be submitted to WDC.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UKSPF List of Projects 2025_26Appendix A 1 pages Download
PDF
Wychavon Rural Fund List of Projects 2025_26Appendix B 3 pages Download
PDF
UK Shared Prosperity Fund and Rural England Prosperity Fund updateReport 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 32 attended
RA
Councillor Rob AdamsMember, present
JA
Councillor Jodi ArnoldMember, in attendance
DB
Councillor Daniel BirchMember, apologies
JB
joe bloggsOfficer, expected
DB
Councillor Dan Boatright-GreeneMember, in attendance
EB
Councillor Eric BowdenMember, in attendance
JC
Councillor John ClatworthyMember, in attendance
AC
Councillor Angie CrumpMember, in attendance
ND
Councillor Nick DawkesMember, in attendance
CD
Councillor Christopher DayMember, in attendance
RD
Councillor Rick DellerMember, present
GD
Councillor George DuffyMember, in attendance

All 32 on the meeting page

On this subject at Wychavon

Search all
  1. UK Shared Prosperity Fund and Rural England Prosperity Fund updateThis decision
  2. UK Shared Prosperity Fund and Rural England Prosperity Fund delivery for 2022-2025Noted
  3. UK Shared Prosperity Fund and Rural England Prosperity Fund updatesApproved
  4. UK Shared Prosperity Fund and Rural England Prosperity Fund updateNoted
  5. UK Shared Prosperity FundAgreed
  6. UK Shared Prosperity Fund - Norton juxta Kempsey Green Lane Project (Part 1)Decided

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies