AI summaryWychavon Executive Board approves £35,450 in Community Building Energy Resilience grants to four venues and changes the award process to speed up future decisions.
Written from the decision and the officer reportPDF Pro
OutcomeApproved£35,450 awarded; one further grant conditional
Money£35,450Total of four approved grants, plus £20,000 conditional
What happens nextWallace House award pending infoFirm quotes and match funding confirmation needed
Who it affectsFour community buildings and one trustVillages across Wychavon district
What was decided
The Executive Board approved £35,450 of Community Building Energy Resilience grants to four organisations, with a further £20,000 awarded conditionally to a fifth. Report P3, P4, P5, P6
The Executive Board also approved the Section 106 Funding Request, though the papers give no further detail on it.
Members agreed to change the grants approval process so future applications do not need to come to the Executive Board, with Energy Audit grants approved directly by officers and Building Improvement grants reviewed by the Panel first. Report P7, P8, P9, P10, P11
Why
The Climate and Nature Panel assessed round one applications on 9 September 2026 and recommended awards to help community buildings cut energy use and costs. Report P1, P2, P3
Councillors wanted to add flexibility and speed to the way grants are approved and delivered, so small awards do not wait for full Board meetings. Report P8, P9
What happens next
The Samuel Wallace Smedley Trust must provide firm quotes and confirm match funding before its £20,000 solar panels award is released. Report P5, P6
Future Energy Audit grant applications will be approved by the Executive Board Member for the Environment and the Director of Economy and Environment, with Building Improvement applications routed through the Climate and Nature Panel to the same two officers. Report P10, P11
The money
£35,450 Total Community Building Energy Resilience grants awarded in round one Report P3
£20,000 Bretforton Grange and Theatrebarn, new LED stage lighting system Report P4
£8,000 Drakes Broughton Village Hall, 39 additional solar panels and battery storage Report P4
£6,600 Stock and Bradley Village Hall, doors, ceiling tiles and insulation Report P4
£850 Wyre Piddle Village Hall, energy audit Report P4
£20,000 Samuel Wallace Smedley Trust (Wallace House), rooftop solar panels, awarded conditionally Report P5, P6
Options considered
Chosen: Award the four grants as recommended by the Panel. Recommended by the Climate and Nature Panel following assessment of round one applications Report P2, P3, P4
Rejected: Award the Wallace House grant now. Further information on project readiness, firm quotes and match funding is still required Report P5, P6
Rejected: Keep the current process where all applications go to the Executive Board. Members wanted to add flexibility and speed to grant decisions and project delivery Report P8, P9
Chosen: Amend the process so Energy Audit grants go to officers and Building Improvement grants go to the Panel and then officers. Provides flexibility and speed while keeping Panel scrutiny for larger awards Report P9, P10, P11
Implications
Climate: Four community buildings will receive funding for LED lighting, solar panels, insulation or an energy audit, supporting lower energy use. Report P3, P4
Governance: Future grant approvals will be made by named officers rather than the full Executive Board, changing the decision-making route for these awards. Report P9, P10, P11
Risk: The Wallace House award carries a risk that further information may not satisfy the conditions, so funding is not yet committed. Report P5, P6
Samuel Wallace Smedley Trust, which runs Wallace House Report P5, P6
Future applicants for Community Building Energy Resilience grants Report P9, P10, P11
Timeline
9 September 2026: Climate and Nature Panel met and recommended grants to the Executive Board Report P1
16 September 2026: Executive Board approved the recommendations Report P3
Plain English for the jargon
Section 106 funding: Money paid by developers to a council as part of a planning agreement, often used for local community or infrastructure projects.
Community Building Energy Resilience Grant: A Wychavon grant helping community buildings become more energy efficient or generate their own energy.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33
Resolved
Resolved That both the Section 106 Funding Request and the Wychavon Community Resilience Grant recommendations be approved. Councillor B Hardman introduced the recommendations from the Climate and Nature Panel as follows: Community Building Energy Resilience Grant – Round 1 Applications The Panel assessed round one of the Community Building Energy Resilience grants applications. RECOMMENDED to Executive Board on 16 September 2026 that a total of £35,450 of Community Building Energy Resilience grants be awarded to the four organisations detailed below: • Bretforton Grange & Theatrebarn : £20,000 to install a new modern LED stage lighting system, replacing the existing inefficient and ineffective tungsten lighting system. • Drakes Broughton Village Hall: £8,000 to install and additional 39 solar panels of the village hall roof as well as a battery storage system. • Stock & Bradley Village Hall: £6,600 to improve the energy efficiency of ... view the full minutes text for item 33.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Recommendations to Executive Board on 16th September from the Climate & Nature Panel held on 9th September 2026
Community Building Energy Resilience Grant – Round 1 Applications The Panel assessed round one of the Community Building Energy Resilience grants applications.
RECOMMENDED to Executive Board on 16 September 2026 That a total of £35,450 of Community Building Energy Resilience grants be awarded to the four organisations detailed below:
• Bretforton Grange & Theatrebarn: £20,000 to install a new modern LED stage lighting system, replacing the existing inefficient and ineffective tungsten lighting system. • Drakes Broughton Village Hall: £8,000 to install and additional 39 solar panels of the village hall roof as well as a battery storage system. • Stock & Bradley Village Hall: £6,600 to improve the energy efficiency of the hall through new doors, ceiling tiles and insultation materials. • Wyre Piddle Village Hall: £850 to undertake an energy audit of the building.
It is also recommended the following grant is awarded on a conditional basis pending the receipt of further information:
• Samuel Wallace Smedley Trust (Wallace House): £20,000 for the installation of rooftop solar panels on Wallace House. Further information required on project readiness, including the provision of firm quotes and confirmation of match funding sources.
Community Building Energy Resilience Grants – Awards process
The panel considered the existing mechanism for the approval of grant awards, which currently requires all applications to be reviewed by the Climate & Nature Panel, who make recommendations to the Executive Board for approval.
To add flexibility and speed to the decision making on grants, and the delivery of the applicant’s projects, it is recommended that the awards process is amended as per below:
• Energy Audit grant applications: approval given directly by Executive Board Member for the Environment and the Director of the Economy & Environment • Building Improvement grant applications: reviewed by the Climate & Nature Panel, who make recommendations to the Executive Board Member for the Environment and the Director of the Economy & Environment for approval
For both types of applications, no approvals would be required by the Executive Board.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.