Resolved
The Director of Communities submitted a report seeking the approval to grant £350,000 of UKSPF to Fleetwood Trust, to fund capital works towards the repurpose and refit of ground floor space, to create a community hub, at the Former Fleetwood Hospital site, North Albert Street, Fleetwood. Decision The Resources Portfolio Holder agreed : · That £350,000 is granted to Fleetwood Trust for capital works towards the redevelopment of ground floor space, which will be used as a community hub facility. · · That the capital programme for the financial year 2024/25 be updated to reflect the spend profile of £350,000 on this project. · To note that Fleetwood Trust are intending to use their existing contractor, through a variation of their current contract of works, which will be compliant with the UKSPF procurement requirements and ensure the project is deliverable by 31 March 2025.
Word for word from the decision Wyre published for this meeting.
Source: wyre.moderngov.co.uk