UK Shared Prosperity Fund - Development of a Feel Good Factory at Thornton Leisure Centre

Approved Committee 1 paper

Portfolio Holder Decisions approved this item on Thursday 11 April 2024. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

The Director of Communities submitted a report seeking the approvals to facilitate the purchase and installation of a new Feel Good Factory gym facility at Thornton Leisure Centre together with associated running costs for the first year. Costs of £185,622 to be funded from the UK Shared Prosperity Fund (UKSPF), with the capital programme for 2024/25 to be updated to reflect that this includes spend of £117,543. Decision The Resources Portfolio Holder and the Leisure, Health and Community Engagement Portfolio Holder agreed : · That approval is given to purchase and install specialist, power assisted Feel Good Factory exercise equipment at Thornton Leisure Centre at a cost of £106,857 (plus 10% contingency of £10,686). The total cost is £117,543 and this is to be reflected in the capital programme for 2024/25, funded by an allocation from UKSPF. · That approval is given to fund staffing, marketing and service contract costs of £61,890 (plus contingency of £6,189). The total cost is £68,079 to support the first 12 months of the operation of the Feel Good Factory funded by an allocation from the revenue funding from UKSPF. · That approval is given by the Resources Portfolio Holder to allow the procurement under exemptions to contract procedures, contained within the Financial Regulations and Financial Procedure Rules on the grounds that: “the goods, works or services are of a specialised nature carried out by only one or a limited number of firms with no reasonably satisfactory alternatives available.”
Word for word from the decision Wyre published for this meeting. Source: wyre.moderngov.co.uk

Follow this further

Built from Wyre's papers

What the report saysPro

Report to Portfolio Holder Decisions
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
UK Shared Prosperity Fund: Development of a Feel Good Factory at Thornton Leisure CentreReport 128 KB Copy on its way

At this meeting

Whole meeting

On this subject at Wyre

Search all
  1. UK Shared Prosperity Fund - Development of a Feel Good Factory at Thornton Leisure CentreThis decision
  2. UK Shared Prosperity Fund (UKSPF) - Cottam Hall Pavilion RefurbishmentApproved
  3. UK Shared Prosperity Fund (UKSPF) / Rural England Prosperity Fund (REPF) updateNoted
  4. UK Shared Prosperity Fund (UKSPF) - Cottam Hall Pavilion RefurbishmentApproved
  5. UK Shared Prosperity Fund - Garstang Public Realm WorksApproved
  6. UK Shared Prosperity Fund - Development of the community hub at the former Fleetwood Hospital siteApproved

More from Wyre Portfolio Holder Decisions

All decisions
MeetingDecisionOutcome
13 Mar 2025 Biodiversity Net Gain Monitoring FeeThe Assistant Director of Planning and Building Control submitted a report to agree to a charge, payable by applicant... Agreed Open
13 Mar 2025 ICT Backup Power solution - UPS and GeneratorThe Director of Transformation and Change submitted a report to seek approval to purchase a backup power supply sourc... Approved Open
13 Mar 2025 Flood and Coast Resilience Innovative Programme – Our Future Coast DevelopmentThe Director of Environment submitted a report to seek approval to procure services from a number of consultants and ... Approved Open
17 Jan 2025 Fleetwood Pitch and Putt courses – New lettingThe Director of Communities submitted a report to set out the process undertaken to re-establish the old pitch and pu... Approved Open
16 Jan 2025 Endorsement of an update to the Fylde Coast Authorities Level 1 Strategic Flood Risk Assessment (SFRA) 2024The Director of Communities submitted a report to endorse updating four GeoPDF’s to refine the Flood Zone 3b in accor... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies