CS2263
Meeting of the Executive Members for 5th June 2006 Housing and Adult Social Services and Advisory Panel Report of the Director of Housing and Adult Social Services
Housing Capital Programme – Out turn Report Summary 1. This report presents the out turn position of the 2005/06 Housing Capital Programme and the resources available to support it.
Approved Slippage to (Under) / Actual % Variation Expenditure 2006/7 Overspend Expenditure £k £k £k £k 10143 50 (136) 9957 1.8%
Background 2. During the year the Executive Member receives first, second and third quarter monitoring reports for the Housing Capital Programme. These reports highlight any major changes in the agreed programme or the resources required to fund it.
3. At the Third Quarter Review presented to Housing EMAP on 6th February 2006 a number of minor variations were noted and a recommendation was made to approve any variations of £50k to £100k. Following approval of these recommendations, the Housing Capital Programme for 2005/06 stood at £10.143m of which £5.196m is funded by the Major Repairs Allowance (MRA).
4. Officers have reviewed the progress of investment projects during the final quarter of 2005/06 and the resources required to fund them. Minor variations have been agreed under officers delegated authority and slippage into 2006/07 identified. A detailed schedule is attached as Annex 1.
5. There is a total of £50k slippage on the capital funded element of the programme into 2006/07, this includes £32k on Installation and Replacement of Heating Systems and £18k for the Homeless Hostel at Howe Hill. There is an underspend of £97k on schemes funded by Capital. These are set out in Tables 1 to 3 in paragraphs 10 to 20 for the Executive Member’s Approval and information. 6. There is an underspend of £39k on MRA funded element of the programme. These are set out in Tables 4 to 5 in paragraphs 21 to 25 for the Executive Member’s Approval and information.
7. The MRA is ring fenced solely for improvements to council homes and does not affect the budgetary position of the council.
Consultation 8. There has been no consultation carried out to produce this report.
Options 9. As this report is for information, no options have been included.
Analysis 10. Table 1 – Modernisation of Local Authority Homes (Capital Scheme)
Scheme Approved Revised Costs (Under)/Overspend Budget 2005/06 2005/06 2005/06 £k £k £k Communal 162 136 (26) Security Doors Asbestos 18 26 8 Scooter Stores 32 43 11 Total 212 205 (7)
11. The under spend on Communal Security Doors is due to a reduction in the average unit cost as a result of a number of existing doors being identified at detailed survey stage of being suitable for upgrade rather than renewal. There is an overspend of £8k on Asbestos due to the survey identifying more works needing to be undertaken than originally planned. The overspend on Scooter Stores is a result of being charged fees for almost the whole of the scheme, when 70% of the scheme was slipped, at quarter 3, to 2006/7. This has been discussed with City Strategy and it will result in reduced fees being charged for the remaining work to be carried out during 2006/7.
12. There have been further minor variations within officers delegation on various modernisation schemes resulting in an underspend of £10k. This is made up of underspends of £3k on Burglar Alarms, £3k on Fire Door Replacement, £2k on Window Replacement and a further £2k on Capitalised Salaries.
13. Table 2 – Repairs to Local Authority Properties
Scheme Approved Revised (Under) / Slippage to Budget Costs Overspend 2006/07 2005/06 2005/06 2005/06 £k £k £k £k Installation and 842 810 0 (32) Replacement of Heating Systems Communal Access 138 119 (19) Flooring Repairs and 66 24 (42) Maintenance Communal areas Total 1,046 953 (61) (32)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing 200506 OutturnAppendix 1 | 36 KB | Download |
PDF |
Housing Capital Programme: Out turn ReportReport | 53 KB | DownloadRead as text |
Follow Housing and Adult Social Services Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2009 | Exclusion of Press and PublicThat the Press and public be excluded from the meeting during consideration of Annex 1 to agenda item 10 (External Pa... | Decided | Open |
| 16 Mar 2009 | MinutesThat the minutes of the meeting held on 27 January 2009 be approved and signed by the Chair and Executive Member as a... | Approved | Open |
| 16 Mar 2009 | 2008/9 Service Plans and Budget 3rd Monitor ReportAdvice of the Advisory Panel That the Executive Member be advised to note and comment on the content of this report D... | Noted | Open |
| 16 Mar 2009 | Housing and Adult Social Services Capital Programme – Monitor 3Advice of the Advisory Panel That the Executive Member be advised to note the progress on schemes and approve the var... | Noted | Open |
| 16 Mar 2009 | Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.