Social Services Capital Programme – Out turn Report

Decided Committee 2 papers

Housing and Adult Social Services Advisory Panel decided this item on Monday 5 June 2006. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

That the advice of the Advisory Panel as set out above be accepted and endorsed. REASON: To comply with Council Financial Regulations.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Housing and Adult Social Services Advisory Panel

CS2269

Meeting of the Executive Members for 5th June 2006 Housing and Adult Social Services and Advisory Panel Report of the Director of Housing and Adult Social Services

Social Services Capital Programme – Out turn Report Summary 1. This report presents the out turn position of the 2005/06 Social Services Capital Programme and the resources available to support it.

Approved Slippage to (Under) / Actual % Variation Expenditure 2006/7 Overspend Expenditure £k £k £k £k 1062 75 (23) 964 9%

Background 2. During the year the Executive Member receives first, second and third quarter monitoring reports for the Social Services Capital Programme. These reports highlight any major changes in the agreed programme or the resources required to fund it.

3. At the Third Quarter Review presented to Social Services EMAP in February 2006 the Executive Member approved one minor variation of £6k. Following this the revised gross Social Services Capital Programme for 2005/06 was £1,062k, of which £158k is funded from capital grants, £100k from the Housing Capital Programme to fund Disability Support Grants and £362k from other sources resulting in a net capital programme of £442k.

Consultation 4. There has been no consultation carried out to produce this report.

Options 5. As this report is for information, no options have been included. Analysis 6. Officers have reviewed the progress of investment projects during the final quarter of 2005/06 and the resources required to fund them. Minor variations have been agreed under officers delegated authority and slippage into 2006/07 identified. A detailed schedule is attached as Annex 1.

7. There is a total of £23k underspend on the Capital funded programme which is set out in paragraph 10. There is £75k slippage of expenditure into 2006/07 set out in paragraph 9..

8. The slippage is £27k from Modernisation of Oliver House due to delays in the scheme design and planning permission stages, £10k from Windsor House modernisation as the scheme is only now in the tender stages, £10k on Relocation of Hebden Rise Day Centre due to contract retention payments and £5k on Morrell House due to incomplete works. There is also £15k slippage relating to Information Management Improvements. The progress of the Integrated Children’s System has not been as expected with major development work now being scheduled for the second half of 2006/07 rather than 2005/06, with a need to slip £8k.

9. There is an underspend of £16k on the Community Equipment Loan Service purchasing of equipment due to a fall in demand for major items of equipment over the winter period. There is an overspend of £5k on Capitalised Salaries relating to Modernising EPH’s which is covered by an underspend of £13k on the Relocation of Hebden Rise day care centre due to savings on fixtures and fittings as well as capitalised salaries. There is also an overspend of £1k on the Disability Support Programme.

Corporate Objectives 10. The Capital Programme contributes to the Corporate Aims of improving the health, well being and independence of York residents.

Implications Financial

11. The final outturn of the 2005/06 Social Services Capital Programme is £964k gross compared to the approved programme of £1062k gross. The variation of £98k from the approved programme is due to slippage of £75k and an overall underspend of £23k.

12. There is currently a dispute with the contractor regarding the work at Morrell House which may incur additional costs. An update will be included in the first monitoring report of 2006/07.

Human Resources (HR)

13. None Equalities

14. None

Legal

15. None

Crime and Disorder

16. None

Information Technology (IT)

17. None

Property / Other

18. There are no property or other implications

Risk Management 19. This report follows the due process and presents the current out turn position and does not request decisions from a number of options hence does not contain risk.

Recommendations 20. The Executive Member is requested to

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Social services 200506 outturnAppendix 1 27 KB Download
PDF
Social Services Capital Programme: Out turn ReportReport 39 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
JG
Councillor Janet GreenwoodChair, apologies, sent representative
SG
Councillor Susan GallowayCabinet Member, present
SS
Councillor Susan SunderlandCabinet Member, present
BF
Councillor Bill FaircloughVice-Chair, in the Chair, present
GN
Councillor Gilbert NimmoCommittee Member, present
SF
Councillor Sandy FraserCommittee Member, present
DH
Councillor David HortonCommittee Member, present
MH
Councillor Mark HillCommittee Member, present
MG
Mrs Mildred GrundyCo-opted Non-Statutory Member, present
PH
Ms Pat HolmesCo-opted Non-Statutory Member, present

On this subject at York

Search all
  1. Social Services Capital Programme – Out turn ReportThis decision
  2. Healthwatch York Report - Listening to BAME people about Health and Social Care Services in YorkNoted
  3. Healthwatch York Report: LGBT experiences of health and social care services in YorkDecided
  4. Proposed 12 Month Pilot for the Payment of 'Golden Hellos' and 'Golden Handcuffs' to Social Workers in the Referral & Assessment Team in Children's ServicesAgreed
  5. 'Rewiring Public Services - Further Engagement on Adult Social Care and Place Based ServicesAgreed
  6. Attendance of the Cabinet Member for Health, Housing and Adult Social Services.Noted

More from York Housing and Adult Social Services Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 Exclusion of Press and PublicThat the Press and public be excluded from the meeting during consideration of Annex 1 to agenda item 10 (External Pa... Decided Open
16 Mar 2009 MinutesThat the minutes of the meeting held on 27 January 2009 be approved and signed by the Chair and Executive Member as a... Approved Open
16 Mar 2009 2008/9 Service Plans and Budget 3rd Monitor ReportAdvice of the Advisory Panel That the Executive Member be advised to note and comment on the content of this report D... Noted Open
16 Mar 2009 Housing and Adult Social Services Capital Programme – Monitor 3Advice of the Advisory Panel That the Executive Member be advised to note the progress on schemes and approve the var... Noted Open
16 Mar 2009 Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies