Advice of the Advisory Panel That the Executive Member for City Strategy be advised to : (i) Agree to the adjustments set out in the Annexes 1 & 2, subject to the approval of the Executive to the proposed funding changes; (ii) Note that the Skelton Speed Management scheme and Eastfield Avenue proposed 20 mph zone will be included in the Capital Programme. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City Strategy and 11 December 2006 Advisory Panel
Report of the Director of City Strategy
CITY STRATEGY CAPITAL PROGRAMME 2006/07 – SECOND MONITOR REPORT
Summary 1. The purpose of this report is to set out progress to date on schemes within the City Strategy Capital Programme for 2006/07. It reports on budget spend to the end of October 2006, which is seven months into the capital programme year. The budgetary position over the next four years is also identified. The report asks the Executive Member for City Strategy to approve the amendments to the 2006/07 budget as set out below.
Background 2. The City Strategy Capital Programme was agreed by the Executive Member in April 2006. The programme was finalised on 17 July 2006 when the Executive Member was presented with the consolidated Capital Programme for 2006/07, which included all work that had carried over from 2005/06.
3. Following minor programming changes at the first Monitoring Report in September, the current approved budget for the City Strategy Capital Programme for 2006/07 is £10,835k. This figure represents the budget available to spend and is therefore net of the overprogramming built into the Local Transport Plan (LTP) element of the programme. The overprogramming seeks to address the problem of schemes being delayed due to unforeseen circumstances arising.
4. The current approved City Strategy Capital Programme for 2006/07 has a value of £14,138k, which includes £3,304k of overprogramming.
City Strategy Capital Programme 5. The City Strategy Capital Programme is funded from the Local Transport Plan settlement, City of York Council capital resources, other government funding sources and the private sector (including section 106 agreements). The list of schemes set out below considers those with an element of LTP funding first, followed by those funded entirely from other sources. The funding figures shown are those for 2006/07 only and do not necessarily represent the full cost of the scheme. 6. The spend plus commitments for schemes within the City Strategy Capital Programme to the end of October was £4,403k. This represents 41% spend of the total budget allocation (ie: the programme minus overprogramming). This is higher than the spend at this time in previous years (the spend at end of October 2005 was 26% of the budget), which is due to a high level of spend against some of the larger schemes in the programme (mainly James St Link Road).
7. When the programme was prepared in March 2006 there was considerable uncertainty over a number of the larger schemes in the programme and therefore the level of overprogramming was set relatively high at approximately £3m. The projected outturn has been reviewed taking account of progress and issues which have arisen up to date. This review has indicated that owing to good progress on a number of key schemes approximately £1m of additional projects could be delivered if funding was available.
8. In previous years progress on schemes has been adjusted over the year end to ensure the budget allocation is fully spent. These schemes would become the first call on funds in the following year, however funding available for integrated transport is reducing over the next few years due to changes to the DfT allocation to the council. In addition Moor Lane Roundabout is planned to be delivered in 2007/08. The consequences of delivering this large scheme in one financial year and the reducing budget means that there is likely to be less funding available for other integrated transport schemes in 2007/08.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.