City Strategy Capital Programme - Monitor 3 Report

Approved Committee 4 papers

City Strategy and Advisory Panel approved this item on Monday 16 March 2009. Below is the council's own wording, with the papers it was decided on.

Item89

Resolved

Advice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to: (i) Approve the adjustments to the allocations to the LTP Programme identified in Annex 2; (ii) Approve the slippage of £149k of CYC funding to 2009/10; (iii) Approve the removal of £25k of CYC funding from the City Strategy Capital Programme; (iv) Approve the decrease to the 2008/09 City Strategy capital budget, subject to the approval of the Executive. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to City Strategy and Advisory Panel

Executive Members for City Strategy and 16 March 2009 Advisory Panel

Report of the Director of City Strategy

City Strategy Capital Programme – Monitor 3 Report Summary 1. The purpose of this report is to:

• Inform Members of the likely outturn position of the 2008/09 Capital Programme, based on the spend profile and information to the end of January 2009;

• To seek approval for any resulting changes to the programme;

• Inform the Executive Members of any slippage, and seek approval for the associated funding to be slipped between the relevant financial years to reflect this.

2. The 2008/09 – 2010/11 capital programme was approved by Council on 21 February 2008. Since then a number of amendments have taken place, as reported to Executive Members in the 2007/08 Capital Outturn report, Consolidated report (July), Monitor 1 report (September) and Monitor 2 report (December). These changes have resulted in a current approved capital programme for 2008/09 of £8.658m, financed by £6.903m of external funding, leaving a cost to the Council of £1.775m. Table 1 illustrates the movements from the original budget to the currently approved position.

Table 1 Current Approved Capital Programme Gross External Capital Budget Funding* Receipts £m £m £m Original Budget Approved by Council 7.943 6.441 1.502 at 21 Feb 2008 Re-profiling to 09/10 & 10/11 from 07/08 n/a n/a n/a outturn report Additions/ reductions from 07/08 outturn +0.496 +0.243 +0.253 report approved at Monitor 1 Additions/ reductions from 07/08 outturn +0.219 +0.219 report approved at Monitor 2 Current Approved 8.658 6.903 1.755 Capital Programme *External funding refers to government grants, non government grants, other contributions, developers contributions and supported capital expenditure.

3. The capital receipts column above implies receipts generated from the sale of Council assets will be used to fund the difference between the gross budget less all other specified funding sources. Due to the current economic climate not being favourable to achieving maximum receipt value from asset disposals, consideration will be given to the use of prudential borrowing to fund the capital programme as a temporary measure. When the economic climate returns to a more favourable state assets will be sold with the receipts being applied to finance the programme, thus replacing the temporary borrowing.

Consultation 4. The capital programme was developed under the Capital Resource Allocation model (CRAM) framework and agreed by council in 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local Councillors and residents in the locality of the individual schemes.

Summary of Key Issues 5. Against the current approved budget of £8.658m in 2008/09, there is a predicted outturn of £8.479m, a net decrease of £0.179m. The Monitor 2 report detailed the additional funding available from the Cycling City Grant and the Housing & Planning Delivery Grant, which increased the available capital budget up to 2010/11. The additional schemes in the Access York Phase 1 (Park & Ride) project (approx. £25m) have not been included in the 2009/10 and 2010/11 programme pending confirmation of the level of funding from the Department of Transport.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CS0809 M3 Report Annex 1 Rev1Appendix 46 KB Download
PDF
CS0809 M3 Report Annex 2 Rev1Appendix 20 KB Download
PDF
CS0809 M3 Report Annex 3 Rev1Appendix 56 KB Download
PDF
City Strategy Capital Programme: Monitor 3 ReportReport 53 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
IG
Councillor Ian GilliesChair, present
RC
Councillor Richard CreganCommittee Member, present
AD
Councillor Andy D'AgorneVice-Chair, present
SG
Councillor Steve GallowayCabinet Member, present
RP
Councillor Ruth PotterCommittee Member, present
DS
Councillor David ScottCommittee Member, present
SS
Councillor Susan SunderlandCommittee Member, present
AW
Councillor Andrew WallerCabinet Member, present

On this subject at York

Search all
  1. City Strategy Capital Programme - Monitor 3 ReportThis decision
  2. A City that Works for All: York's All-age Autism and ADHD Strategy 2025-2030Approved
  3. North Yorkshire and City of York Domestic Abuse Strategy 2024-2028 (10:07)Approved
  4. City of York Council Actions in Response to the York Anti-Racism and Inclusion Strategy (18:03)Approved
  5. City of York Council - Human Rights City Commitment Strategy (10:26 am)Agreed
  6. A refreshed all-age Autism Strategy for the City (5:32pm)Decided

More from York City Strategy and Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 MinutesThat the minutes of the last meeting of the Panel held on 27 January 2009 be approved and signed by the Chair and Exe... Approved Open
16 Mar 2009 Core Funding to Voluntary Organisations 2009/10Advice of the Advisory Panel That the Executive Leader be advised to: (i) Maintain the existing grant funding agreeme... Agreed Open
16 Mar 2009 Chief Executive's Monitor 3 Finance & Performance Report 2008/09Advice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 2008/09 Third Monitoring Report Economic Development and Partnerships - Finance & PerformanceAdvice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 Review of Night Time Taxi Rank ProvisionAdvice of the Advisory Panel That the Executive Member for City Strategy be advised to: (i) Approve Option 1, to take... Approved Open