Urgent Business - Administrative Accommodation Project

Approved Executive 1 paper

Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 13 February 2007. Below is the council's own wording, with the papers it was decided on.

Item160

Resolved

(i) That the appointment of Shepherd Construction as Constructor for the Administrative Accommodation project (Lot 1) be acknowledged. (ii) That the appointment of RMJM Ltd. as the Architect, Structural Engineer, Space Planner and Planning Supervisor for the Administrative Accommodation project (Lot 2) be approved. (iii) That the appointment of Gifford as the Mechanical and Electrical Engineer for the Administrative Accommodation project (Lot 3) be approved. (iv) That the appointment of WT Partnership as the Quantity Surveyor for the Administrative Accommodation project (Lot 4) be approved. (v) That the appointment of Turner and Townsend as Project Manager for the Administrative Accommodation project (Lot 5) be acknowledged. REASON: In order to achieve the best quality of service for the project within the available budget and to avoid unnecessary delay. (vi) That the above appointments be subject to the Chief Executive arranging for another department of the Council to carry out an independent check on the reasoning behind the decisions of the Corporate Landlord in those cases where he has not recommended acceptance of the lowest tender. REASON: So that Members can be absolutely certain that the additional expenditure occasioned by not accepting the lowest tenders is justified. (i) That the appointment of Shepherd Construction as Constructor for the Administrative Accommodation project (Lot 1) be acknowledged. (ii) That the appointment of RMJM Ltd. as the Architect, Structural Engineer, Space Planner and Planning Supervisor for the Administrative Accommodation project (Lot 2) be approved. (iii) That the appointment of Gifford as the Mechanical and Electrical Engineer for the Administrative Accommodation project (Lot 3) be approved. (iv) That the appointment of WT Partnership as the Quantity Surveyor for the Administrative Accommodation project (Lot 4) be approved. (v) That the appointment of Turner and Townsend as Project Manager for the Administrative Accommodation project (Lot 5) be acknowledged. REASON: In order to achieve the best quality of service for the project within the available budget and to avoid unnecessary delay. (vi)That the above appointments be subject to the Chief Executive arranging for another department of the Council to carry out an independent review of the ... view the full minutes text for item 160.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 13 February 2007

Report of the Corporate Landlord

Administrative Accommodation Project Summary 1. The Corporate Landlord has undertaken a comprehensive procurement process for the appointment of design and construction partners for the Administration Project. The process has been conducted on the basis of MEAT (Most Economically Advantageous Tender). When the results of the MEAT evaluation establish a preferred bidder that is not the lowest price the matter should be recommended to members for final approval. In this case, of the five appointments, three are not the lowest price.

Background 2. The council published an OJEU notification in May 2006 seeking expressions of interest from interested consultants and constructors to work as an integrated partnering team to design and construct the new office accommodation at Hungate. The notice stated that the council wished to engage with companies with a proven record of partnering on similar projects, working within integrated teams, showing a commitment to open book accountability, and an openness to sharing benefits and savings.

3. Interested parties were requested to apply for one or more of the following categories or Lots:

Lot 1 – Constructor

Lot 2 – Architect, Structural Engineering, Space Planner and Planning Supervisor

Lot 3 – Mechanical and Electrical Engineer

Lot 4 – Quantity Surveyor

Lot 5 – Project Manager 4. Tender documents were issued to short listed consultants and constructors following an appraisal of their pre-qualification submissions. The tender documents detailed the scope of the work, contract conditions, outline user brief and tender evaluation criteria.

5. The tender evaluation criteria stated that the award of contract would be MEAT and provided details of how price and quality factors would be assessed.

6. The qualitative criteria were assessed by an interview for the Constructor, Quantity Surveyor and Project Manager prior to the receipt of the price. This clearly demonstrated to the Tenderers that the qualitative assessment could not be influenced by price, but contributed to the final evaluation on a quality price basis.

7. The response for both design categories (Lots 2 and 3 above) was very strong and a different approach was adopted to allow more companies to compete. Tenderers were informed that they should submit their price before interview and that a maximum of five firms for each lot would be interviewed. All interviewed firms had to meet the project’s affordability criteria.

8. Having met the affordability criteria the award would be made on a qualitative basis to the company that demonstrated the greatest skill, experience and suitability during the interview. It was considered that this approach would ensure that the council would get the right companies for this project.

9. Evaluations of the tenders are now completed. The recommendations for both Constructor and Project Manger identified, through the price/quality evaluation, that the lowest financial bidders should be awarded the lots. The remaining categories identified companies whose tenders were not the lowest but which met the affordability criteria and they had demonstrated through interview and qualitative assessment that they were the most suitable appointment for this project.

10. The attached appendices give a summary of the results of both price and qualitative assessments.

Appendix 1 – Constructor

Appendix 2 – Architect, Structural Engineer, Space Planner, Planning Supervisor

Appendix 3 – Mechanical and Electrical Engineer

Appendix 4 – Quantity Surveyor

Appendix 5 – Project Manager Consultation 11. The council’s procurement team were consulted regarding the processes to be adopted.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Urgent Business: Administrative Accommodation ProjectReport 51 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
SG
Councillor Steve GallowayChair, present
SG
Councillor Susan GallowayCommittee Member, present
CJ
Councillor Ceredig Jamieson-BallCommittee Member, present
QM
Councillor Quentin MacdonaldCommittee Member, present
KO
Councillor Keith OrrellCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
SS
Councillor Susan SunderlandCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. Urgent Business - Administrative Accommodation ProjectThis decision
  2. Urgent Business (18:47)Approved
  3. Urgent Business - Urgent Review of Parking Charges (10:44am)Decided
  4. Urgent Business (6:37 pm)Decided
  5. Urgent Business - Advertising Contract (19:01)Noted
  6. Urgent Business (6:41 pm)Decided

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies