Advice of the Advisory Panel That the Executive Member for City Strategy be advised to: (i) Accept the increased cost of the Moor Lane roundabout scheme identified in paragraph 12 of the report : a total scheme cost of £3.5 m; (ii) Approve the proposed 2007/08 City Strategy Capital Programme as set out in the report. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City Strategy and 26 March 2007 Advisory Panel
Report of the Director of City Strategy
PROPOSED 2007/08 CITY STRATEGY CAPITAL PROGRAMME
Summary 1. The purpose of this report is to set out the details of the proposed City Strategy Capital Programme for 2007/08, and to ask the Executive Member for City Strategy to approve the proposed programme for 2007/08.
Background 2. The budget for the 2007/08 City Strategy Capital Programme was agreed at the Full Council Meeting on 21 February. The 2007/08 budget is £8,777k (compared to £10,464k in 2006/07) including funding from the Local Transport Plan (LTP) settlement, developer contributions and council resources.
3. As indicated in the ‘City of York’s LTP 2006-2011 Capital Settlement’ report to 27th February Executive, the council received additional resources compared to the 2005 indicative settlement, amounting to £460k in 2007/08 and £900k over the four years 2007/08-2010/11. The increased funding was due to the quality of the transport strategy set down in the second LTP document (LTP2), which was assessed as excellent. However despite this assessment the anticipated LTP integrated transport funding is projected to fall over the next four years from £4,141k to £2,986k due to the change over to a new formula- based allocation methodology. This is substantially lower than the £5,248k average settlement received during the LTP1 period.
4. The main opportunity to increase funding through the LTP process is to meet or exceed the targets set in the LTP document, therefore it is essential that all schemes are carefully assessed to ensure that they deliver measurable benefits against the objectives of the plan before they are included in the programme.
5. During the preparation of the programme, each scheme planned to be implemented in 2007/08, which had not already been committed for delivery, has been assessed against the main LTP objectives of tackling congestion, improving accessibility, safer roads and improving air quality, and evaluated against value for money criteria. During the LTP1 period the progress towards cycling and road safety targets was not as rapid as desired therefore resources have been directed to these areas in particular. The contribution of each scheme to the corporate strategy to increase the use of public and other environmentally friendly modes of transport has also been assessed.
6. Owing to the level of funding anticipated to be available, it was agreed at the City Strategy EMAP on 11 December that the allocations for each main block should be balanced across the entire budget over the next four years to minimise the impact of delivering Moor Lane Roundabout in 2007/08. This means that the proposed spend on structural maintenance has been reduced in 2007/08 but increased in future years. Over the four year period the spend on integrated transport and structural maintenance is projected to be equal to the budget. In this way the targets of the LTP can be progressed on a broad front in each year and the variation in workload between years is minimised.
City Strategy Capital Programme 7. The City Strategy Capital Programme is funded from the Local Transport Plan settlement, City of York Council capital resources, other government funding sources and the private sector, including section 106 agreements. The list of schemes set out below considers those with an element of LTP funding first followed by those funded entirely from other sources. The funding figures shown are those for 2007/08 only and do not necessarily represent the full cost of the scheme. Allowance has been made for the current assessment of the progress of schemes in the 2006/07 programme, but the allocations will need to be adjusted after the 2006/07 outturn figures are known to take account of any carryovers. A consolidated report taking into account these carryovers will be submitted to the City Strategy EMAP in July.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.