Housing and Adult Social Services Capital Programme 2006/07 outturn
ApprovedCommittee3 papers
Housing and Adult Social Services Advisory Panel approved this item on Monday 4 June 2007. Below is the council's own wording, with the papers it was decided on.
Members considered a report which presented the out turn position of the 2006/07 Housing and Adult Social Services Capital Programme and the resources available to support it. It was reported that the value of the approved Housing Capital Programme was £10,041k with £4,581k funded through the Major Repairs Allowance. A total of £160k slippage on the capital funded element of the programme into 2007/08 and an overspend of £176k. The value of the approved Social Services Capital Programme was £671k of which £250k was grant funded. There had been a total slippage of £16k and a net overspend of £11k. Advice of the Advisory Panel That the Executive Members for Housing and Adult Social Services be advised to (i) Approve the changes to the Housing and Adult Social Services Capital Programme as set out in the report; (ii) Refer the slippage of £16k on Social Services and £160k on Housing to the Executive for approval. Decision of the Executive Members for Housing and Adult Social Services
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Housing and Adult Social Services Advisory Panel
HASS28
Meeting of the Executive Members for 4th June 2007 Housing and Adult Social Services and Advisory Panel
Report of the Director of Housing and Adult Social Services
Housing and Adults Social Services Capital Programme – Out turn Report 2006/07
Summary 1. This report presents the out turn position of the 2006/07 Housing and Adult Social Services Capital Programme and the resources available to support it. Background 2. During the year the Executive Members have received reviews of the Capital Programme at first and second quarters, highlighting any major changes in the agreed programme or the resources available to fund it.
3. Staff have reviewed the progress of investment projects during the final 6 months of 2006/07 and the resources needed to fund them. Minor variations have been agreed under officers delegated authority and slippage into 2007/08 identified. Detailed schedules are attached as Annex 1 and 2.
4 The value of the approved Housing Capital Programme is £10,041k with £4,581k funded through the MRA. There is a total of £160k slippage on the capital funded element of the programme into 2007/08 and an overspend of £176k. These are set out in Tables 1 to 4 in paragraphs 9 to 18 for the Executive Member’s approval and information.
5 There is an underspend of £190k on the MRA funded element of the programme. These are set out in Table 5 in paragraphs 19 and 20 for the Executive Member’s approval and information.
6 The value of the approved Social Services Capital Programme is £671k of which £205k is grant funded. There is a total of £16k slippage and a net overspend of £11k. Consultation 7 There is no consultation required to complete this report.
Options 8. As this report is for information only there are no options included in this report.
Analysis - Housing 9. Table 1 – Modernisation of Local Authority Homes (Capital Scheme)
10. The £381k overspend on Tenants Choice Backfills is due to workload issues elsewhere on Tenants Choice schemes, predominantly a delay on the Foxwood programme resulted in a requirement to redirect contractors hence accelerating properties on the backfill list resulting in an increase in properties being modernised. The slippage on Scooter Stores has resulted due to long term staff sickness causing delays in the programme that were unable to catch up and the demolition project was one which only started late in the financial year and has unfortunately over-run.
11. There have been minor variations within officers delegation on various schemes resulting in an underspend of £8k. This is made up of an overspend of £13k on Kitchens, and underspends of £11k on Communal Security Doors, £6k on Burglar Alarms and £4k on Window Replacement.
12. Table 2 – Repairs to Local Authority Properties
Scheme Approved Revised Costs (Under) Budget 2006/07 / Overspend 2006/07 £k 2006/07 £k £k Installation and 1673 1453 (220) Replacement of Heating Systems 13. The Heating Programme is showing an underspend due to programming issues on behalf of the contractor, the overall partnering contract is a 3 year programme which is on course to deliver however at year end has slipped into an underspend. There have been minor variations within officers delegation on various schemes resulting in an overspend of £16k. This is made up of a £1k underspend on the refurbishment of 92 Holgate Road, a £5k overspend on Reroofing Works, a £5k overspend on Communal Access Flooring, a £2k overspend on Security Lighting, a £1k overspend on External Communal Areas and a £4k overspend on Cladding Denis Wilde Homes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing and Adult Social Services Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.