Housing and Adult Social Services Advisory Panel agreed this item on Monday 4 June 2007. Below is the council's own wording, with the papers it was decided on.
Members considered an overview of progress in the General Fund Service Plan agreed in April 2006. The report covered The Executive Member for Housing congratulated officers for all their hard work in delivering the General Fund Service Plan. Advice of the Advisory Panel That the Executive Member for Housing be advised to (i) Note progress and achievements made in delivering the General Fund Service Plan at the end of 2006/07; (ii) Agree the carry forward of £15,000 outlined in paragraph 19 of the report and reference to the Executive for approval. Decision of the Executive Member for Housing
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Housing and Adult Social Services Advisory Panel
HASS27
Meeting of the Executive Members for Housing and Adult Social Services and 4th June 2007 Advisory Panel Report of the Director of Housing and Adult Social Services
Housing General Fund Service Plan Outturn Report 2006/7 Summary 1. To provide the Executive Member with an overview of progress on the General Fund Service Plan agreed in April 2006.
Background 2. The Executive Member agreed the General Fund Service Plan in February 2006 for the following areas: • Housing Revenue Account • Housing General Fund
The process and structure followed guidelines set out by the Corporate Centre. It was agreed that the Executive Member would receive monitoring reports in September & December 2006. It was also acknowledged that both the creation of service plans and the method of monitoring were an evolving process. 3. This report covers the following areas: • Achievements over the year 2006/2007 • Updates on Critical Success Factors (CSF’s) • 2006/2007 performance on Key Performance Indicators (KPI’s) • New external priorities or demands identified • Significant organisational issues
4. There are a number of aspects of the service plan for functions in the Corporate Services element of the Adult Social Services plan that relate to housing. Rather than repeat what is included in another report on the agenda the Executive Member is referred to the companion report for Adult Social Services. Consultation 5. The report is for information and no formal consultation has been undertaken.
Options 6. This report is an overview of progress against agreed objectives and a report on the actual expenditure for 2006/7. Specific options are not being recommended to the Executive Member as part of this report.
Analysis 7. Achievements between April 2006-March 2007 • The Council adaptations work is now included in the Repairs Partnership with a new Schedule of Rates agreed. • Peasholme relocation- Plans to relocate the Peasholme re-settlement Centre to 4 Fishergate were approved during April 2007. • The Housing Strategy and Older Peoples Housing Strategy were published in September 2006. Quarterly monitoring systems have been set up to ensure delivery against the objectives and this is managed through the Housing Services Management Team.
• Year 1 of the refurbishment works programme has been completed on the Travellers Sites with joint funding obtained from Government Office for Yorkshire and The Humber (GOYH).
• Phase 2 of an extensive refurbishment has been carried out to Howe Hill Hostel during 2006/07, 10 units of accommodation have been upgraded or improved bringing additional units into use. When completed the total number of units will have increased from 13 to 27 and will include a wheelchair accessible unit. The homeless hostel at Ordnance Lane has benefited from increased security following the installation of CCTV cameras
• Extensive self assessments against the Audit Commission’s Key Lines of Enquiry (KLOE) have been carried out for Strategic Housing, Private Sector Housing and homelessness. Detailed action plans for improvements have been drawn up
• The average time spent in hostel accommodation has almost halved to 5.67 weeks in 2006/7 from 10.71 weeks in 2005/6. No families have remained in Bed and Breakfast accommodation over six weeks, other than those housed under discretionary powers, and these numbers have reduced from last year. The average time spend In bed and breakfast has also reduced from 4.66 to 3.33 weeks, which has also led to a significant reduction in costs. • A review of the Homelessness Strategy is underway and is due for publication in July 2008
• Resources in the Homelessness Service have been redirected away from casework into prevention services and this has contributed to an increase in the number of cases of homelessness prevented via intervention from the homelessness service. Prevention cases have more than doubled from 126 in 2005/6 to 288 last year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing and Adult Social Services Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.