Leisure, Culture and Social Inclusion and Advisory Panel noted this item on Tuesday 5 June 2007. Below is the council's own wording, with the papers it was decided on.
(i) That the updates to the scheme detailed in the report be noted; (ii) That the scheme slippage set out in the report and summarised in Annex 1 be agreed; (iii) That the revised capital programme as set out in Annex 1 of the report be approved. REASON: In order to allow the effective monitoring of the Capital Programme. That the advice of the Advisory Panel be accepted and endorsed. REASON: In order to allow the effective monitoring of the Capital Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Executive Member for Leisure & Culture and Advisory Panel 5 June 2007
Report of the Director of Learning, Culture and Children’s Services and the Director of Resources
CAPITAL PROGRAMME OUT-TURN 2006/07 Summary 1 This report is to: • inform Members of the final outturn position of the 2006/07 Capital Programme. • advise Members of changes to existing schemes to allow the more effective management and monitoring of the Capital Programme. • inform Members of any slippage in budgets between financial years. • inform Members of any new schemes and seek approval for their addition to the 2007/08 to 2009/10 Capital Programme.
Background 2 The original capital programme for the financial year 2006/07 was approved at Council on 1 March 2006. Since then a number of amendments to the programme have been approved both by the Executive Member and the Executive. This has resulted in a current approved Leisure and Heritage capital programme for 2006/07 which shows gross capital expenditure of £1.001 m, of which £0.642m is from external sources giving a net capital programme cost of £0.359m. The table below details the approved changes to the 2006/07 capital programme since the original programme was approved in March 2006..
Table 1 – Approved Amendments to the 2006/07 Capital Programme Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2006/07 4.305 (1.393) 2.912 Slippage and Adjustments from the 2005/06 0.509 (0.343) 0.166 Outturn report Adjustments from the First and Second Quarter (3.813) 1.094 (2.719) Monitoring reports
Current Approved Capital Programme 2006/07 1.001 (0.642) 0.359 Consultation
3 Not applicable
Options and Analysis
2006/07 Scheme Outturn
4 Each scheme in the capital programme has been reviewed to provide an assessment of its current status. Annex 1 shows the current approved capital programme and the outturn position for 2006/07, together with any slippage that is required to and from future financial years. Updates have been provided for all schemes with progress and significant variations explained in the following paragraphs.
York Pools and Indoor Sports Provision (£8.133m) 5 As previously reported the delay in the capital receipt for the Barbican site has pushed back work on the major elements of this scheme. Only £57k of fee expenditure has been incurred in 2006/07.
Danebury Drive Allotments (£0.042m) 6 Only a small amount of the outstanding work on this scheme was carried out by the end of the financial year, so the remainder of the budget needs to be slipped to 2007/08.
Museum Service Heritage Lottery Bid (£1.900m) 7 As reported at Monitor 2 £50k was released to the Trust in 2006/07 for the immediate refurbishment of Kirkgate.
Oakland’s Sports Centre Development (£1.892m) 8 The centre is now fully operational and there are only retentions and minor items of expenditure remaining. A small amount of funding has been slipped into 2007/08 to fund these costs.
Parks and Open Spaces Section 106 Development (£0.480m) 9 The majority of this budget was slipped into 2007/08 at monitor 2. Only a small amount of additional expenditure has been incurred in 2006/07, mainly on minor work in Hull Road park.
Knavesmire Emergency Drainage Works (£0.275m) 10 The improvement works to the Knavesmire drainage have been completed successfully, with only a small overspend of £2k on the current approved budget.
War Memorial Gardens (£0.030m) 11 This scheme has been slipped into 2007/08, as work has not yet begun.
Acomb Library (£0.750m) 12 Tenders for the scheme are due by 24th May 2007, with an estimated start on site in June 2007. The building work is expected to take six months and the new library learning centre will reopen in February 2008. The expenditure in 2006/07 relates to fees. York Pools and Indoor Sports Strategy Update
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.