City of York Council
Executive, Tuesday 7 July 2026 at 4.30pm

Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 Programme

Approved Executive 3 papers

AI summaryCity of York Council Executive moved £58.432m of capital spending into future years, approved £500,000 for museum roof match funding and accepted an £888k housing grant. [D] It recommended a £441.313m programme and up to £938k borrowing to Full Council. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull Council approval is sought for programme and borrowing. [D]
Money£441.313m; £500,000 museum matchAlso £58.432m reprofiled, £888k grant, and up to £938k borrowing. [D]
What happens nextNegotiate security and execute grantsOfficers act; Full Council considers programme and borrowing. [D]
Who it affectsMuseum, housing and capital schemesRoof works, homes and future programme delivery are affected. [P16] [P73]

What was decided

The Executive noted the 2025/26 capital outturn of £81.948m, approved £58.432m of reprofiling into future years and noted net expenditure adjustments of £1.346m. Report P5, P8

It recommended the restated 2026/27 to 2029/30 programme of £441.313m to Full Council and approved a £5.4m virement from Integrated Transport for the updated York Station Gateway forecast.

The Executive authorised lawful security for Arts Council England's museum contribution, approved £200,000 match funding with £300,000 for a future successful bid, allocated £500,000 from Capital Contingency, accepted £888k from MHCLG and recommended up to £938k borrowing to Full Council.

Why

Reprofiling reflects changing delivery timetables in a complex programme and supports effective management and monitoring of the capital programme. Report P7, P9

The museum security must be lawful and deliverable, compatible with existing Council and YMT arrangements and sufficient for ACE to sign the grant agreement, while the match allocation supports grant acceptance and legal compliance. Report P18

The housing grant will support open market purchases for affordable rent for refugee resettlement and temporary accommodation, and rental income is expected to cover repairs and the revenue cost of borrowing. Report P73, P74

What happens next

Officers will work with YMT and ACE to agree lawful security, enter necessary agreements and finalise the grant funding agreement.

The S151 Officer will sign the Memorandum of Understanding for the MHCLG grant.

Full Council will consider the restated capital programme and the proposed additional borrowing.

The money

  • £441.313m Restated 2026/27 to 2029/30 capital programme recommended to Full Council.
  • £58.432m Scheme budgets approved for reprofiling from 2025/26 into future years. Report P7
  • £81.948m Noted 2025/26 capital outturn. Report P5
  • £5.4m Virement from Integrated Transport for the updated York Station Gateway forecast.
  • £500,000 Capital Contingency allocation providing £200,000 for current roof works and £300,000 for future match funding if a later bid succeeds.
  • £888k MHCLG grant accepted for the Local Authority Housing Fund. Report P73
  • £938k Additional borrowing recommended to match the housing grant. Report P74
  • £1.346m Net increase to scheme expenditure in 2025/26. Report P8

Options considered

  • Chosen: Recommend additional borrowing of up to £938k if required. The housing scheme's rental income is assured to cover repairs and the revenue cost of borrowing. Report P74

Implications

  • Financial: Reprofiling shifts £58.432m from 2025/26 into future years while net scheme adjustments add £1.346m. Report P7, P8
  • Financial: The museum allocation is £500,000 from Capital Contingency, comprising £200,000 current match funding and £300,000 for a future successful bid.
  • Legal: Any security could require amendments to the 2009 Yorkshire Museum and Gardens Charitable Scheme, subject to Charity Commission approval, property arrangements and landlord consents. Report P18
  • Legal: The museum grant funding arrangements must comply with the Subsidy Control Act 2022, the Council's Constitution and the Council's Financial Regulations.
  • Risk: ACE's grant agreement cannot be signed until lawful and deliverable security has been agreed. Report P18
  • Climate: The roof work is intended to keep the Yorkshire Museum watertight and address increased rainfall associated with a changing climate. Report P16
  • Financial: The housing scheme requires match funding up to £938k, with rental income expected to cover repairs and the revenue cost of borrowing. Report P74
  • Other: The restated programme and additional borrowing require Full Council approval before implementation.

Who and where

  • City of York Council capital programme teams Report P1
  • Residents benefiting from infrastructure and asset improvements Report P1
  • York Museums and Gallery Trust Report P17
  • Arts Council England
  • People needing affordable rented homes for refugee resettlement and temporary accommodation Report P73
  • Integrated Transport budget and York Station Gateway programme
  • Full Council
  • Council housing services, tenants and adaptations programmes Report P48, P50, P57

Timeline

  • 27 February 2025: Council approved the 2025/26 capital budget of £180.743m. Report P1
  • September 2nd, 2025: Monitor 1 reduced the programme to £180.331m. Report P2
  • November 4th, 2025: Monitor 2 reduced the programme to £162.466m. Report P3
  • January 27th, 2026: Monitor 3 reduced the programme to £139.034m. Report P4
  • 2025/26: The outturn was £81.948m, £57.086m below the revised budget. Report P5
  • 2026/27 to 2029/30: The restated programme of £441.313m was recommended to Full Council.
  • Summer 2026: York Station Gateway highway works were due to finish, with multi storey car park main works due to start. Report P167, P173
  • Spring 2027: Station and loop road works at York Station Gateway were planned to begin. Report P166, P167

Plain English for the jargon

  • Reprofiling: Moving approved scheme budgets between financial years when delivery timetables change. [P7]
  • Outturn: Actual 2025/26 capital expenditure of £81.948m. [P5]
  • ACE: Arts Council England, the grant funder for the Yorkshire Museum roof works. [P16] [P17]
  • YMT: York Museums and Gallery Trust, the independent organisation managing museum collections and facilities for the council. [P17]
  • MEND fund: An ACE fund supporting cultural infrastructure projects and forming part of the Arts Everywhere Fund. [P17]
  • Virement: Moving £5.4m from Integrated Transport to the York Station Gateway forecast. [D]
  • S151 Officer: The officer authorised to sign the MHCLG Memorandum of Understanding. [D]
  • Subsidy Control Act 2022: Legislation cited as a requirement for the museum grant funding arrangements. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

Resolved (unanimously): That Executive a) In relation to the capital programme outturn i) Notes the 2025/26 capital outturn position of £81.948m and approves the requests for re-profiling totalling £58.432m from the 2025/26 programme to future years. ii) Notes the adjustments to schemes increasing expenditure in 2025/26 by a net £1.346m. iii) Recommends to Full Council the restated 2026/27 to 2029/30 programme of £441.313m as summarised in Table 3 and detailed in Annex 1 to the report. iv) Approves the virement of £5.4m from Integrated Transport to fund the updated spend forecast on York Station Gateway. Reason: To enable the effective management and monitoring of the council’s capital programme. b) In relation to the Yorkshire Museum Capital Scheme i) To authorise officers to commence work with York Museums and Gallery Trust (YMT) and Arts Council England (ACE) to identify and agree a lawful and deliverable form of security for ACE’s contribution to the Yorkshire Museum roof works, and to delegate authority to the Director of City Development, in consultation with the Executive Member for Economy and Culture, the Director of Governance and the Director of Finance, to negotiate and enter into any necessary agreements to give effect to the preferred form of security, including (where required): · amendments to the 2009 Yorkshire Museum and Gardens Charitable Scheme, subject to Charity Commission approval; · any documents required to create or support the agreed security for ACE; · any lease or property arrangements required to facilitate the agreed form of security; · any necessary landlord consents from the Council to YMT to facilitate the agreed form of security; · any required applications to HM Land Registry, the Charity Commissioner, Companies House, or any other regulator; and · any consents required to enable the roof works to proceed. ii) Subject to the above, to approve the award of £200,000 match funding to the York Museums and Gallery Trust towards the improvement works for the roof and rainwater goods at the Yorkshire Museum, alongside the allocation of a further £300,000 for future match funding if successful and to delegate authority to the Director of City Development in consultation with the Director of Finance and the Director of Governance, to finalise and execute a grant funding agreement with the York Museums and Gallery Trust. iii) Allocates the £500,000 match funding from Capital Contingency. Reason: To ensure that any charge created at the Yorkshire Museum is in line with the existing arrangements the Yorkshire Museum between CYC and YMT. To enable YMT’s acceptance of the grant funding, and all grant funding arrangements, are in compliance with the Subsidy Control Act 2022, the Council’s Constitution, and the Council’s Financial Regulations. c) In relation to the funding from the Local Authority Housing Fund (round 4) from MHCLG, are recommended to: i) Accepts grant funding from the MHCLG of £888k, by delegating authority to the S151 Officer to sign the Memorandum of Understanding. ii) Recommends to Full Council , the approval of additional borrowing up to £938k to match fund the scheme. iii) Delegates authority to ...
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 45 pages

Meeting: Executive Meeting date: 7 July 2026 Report of: Debbie Mitchell, Director of Finance Portfolio of: Councillor Katie Lomas, Executive Member for Finance, Performance, Major Projects, Human Rights, Equalities and Inclusion

Capital Programme Outturn 2025/26 and Revisions to the 2026/27 – 2029/30 Programme

Subject of Report

1. The purpose of this report is to set out the capital programme outturn position for 2025/26 including any under/overspends and adjustments, along with an update to the future years programme.

2. The report contains details of the capital investment made during 2025/26 and how this has supported delivery of the Council Plan. Key areas of investment are listed below with further details contained in the body of the report: 1.  £4.4m on the expansion and improvement of school facilities across the city  £8.8m on construction and development of new council housing at Duncombe Barracks and Burnholme  £10.5m on the modernisation of and ongoing repairs to council homes  £4.9m on improvement works to homes in Bell Farm  £10.4m on capital investment on the council’s highway network including roads, bridges, drainage and lighting  £11.6m on improvements at Station Gateway  £1.5m on developing the Council’s ICT infrastructure  £1.4m on repairs to the Mansion House. 3. Some of the direct outcomes of the investment include:  Classroom expansion to St Oswald’s and Applefield’s primary schools and St Paul’s Nursery school  Completion of the final expansion phase at Huntington School  Heat pump and solar photovoltaic upgrades to all 61 properties  45 properties received funding under the scheme Home Upgrade Grant scheme  Construction completed on new Passivhaus affordable housing at Duncombe Barracks and Burnholme  Work completed on major refurbishment schemes in Bell Farm and also Glen Lodge  56 new vehicles were delivered and put into operation  Mansion House repairs work is completed  279 private properties and 156 council properties supported with adaptation works to their homes  9 new footpath schemes completed  8 Large Patching Schemes completed with a total area of 12,000 square metres  7 Surface Dressing schemes covering an area of 70,000 square metres  10 carriageway schemes completed including 60,000 square metres of refurbished roads  500 old street lighting columns upgraded to LED  12 drainage improvement schemes completed  12 new bus shelters have been installed

4. The report also seeks to consider a request to provide a capital contribution towards a scheme to upgrade the roof at the Yorkshire Museum which has been awarded a £2m grant by Arts Council England.

Benefits and Challenges 5. The capital programme is key in delivering the Council Plan. Members are able to prioritise capital expenditure to deliver improvements across all service areas notably Schools, Housing, Transport and Regeneration as well as supporting Climate Change ambitions. The capital programme can also play a role in supporting more effective management and reduction of the council’s revenue expenditure in the future, with for example investment in schools allowing for more efficient operations, green technology reducing energy costs etc.

6. The programme does involve significant levels of council borrowing which impacts the level of revenue expenditure. The cost of delivering the capital programme is therefore dependent on levels of external funding, inflation levels and interest rates. The capital programme is subject to value for money assessment as part of its ongoing delivery, and this is increasingly important in the broader context of budgetary pressures across the council. Additional controls and processes are now also being implemented through the newly established corporate Programme Management Office function.

Policy Basis for Decision

7. This report is to note the outturn position for 2025/26 and agree to slippage where necessary to deliver the projects which support the delivery of the council plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn 2025/26 and Revisions to the 2026/27: 2029/30 ProgrammeReport 45 pages DownloadRead as text
PDF
Item 9: Capital Programme Outturn 2025-26 and Revisions to the 2026-27: 2029-30 Programme: Annex 1Appendix 3 pages Download
PDF
View item 18. as HTML 354 KBReport 354 KB Copy on its way

At this meeting

Whole meeting

Who was there

7 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneCommittee Member, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, apologies
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbVice-Chair, present

On this subject at York

Search all
  1. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeThis decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  5. Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor Two 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open