Advice of the Advisory Panel That the Executive Member for City Strategy be advised to: (i) note the significant progress made in 2006/07 in implementing the City Strategy capital programme; (ii) note the financial implications indicated in paragraphs 114 – 114 of the report; (iii) approve the proposed carryovers as outlined in paragraphs 115 – 117, subject to the approval of the Executive. Decision of the Executive Leader
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City 6 June 2007 Strategy and Advisory Panel Report of the Director of City Strategy
CITY STRATEGY CAPITAL PROGRAMME 2006/07 – OUTTURN REPORT
Summary 1. The purpose of this report is to set out progress on schemes in the City Strategy Capital Programme during the financial year 2006/07. It is the outturn report for 2006/07 and reports on budget spend to the end of March 2007.
Background 2. The City Strategy Capital Programme was agreed by the Executive Member in April 2006, and finalised on 17 July 2006 when the Executive Member was presented with the consolidated Capital Programme for 2006/07, which included all work that had carried over from 2005/06. Following amendments to the programme at the second Monitoring Report in December, the current approved budget for the City Strategy Capital Programme for 2006/07 is £19,564k (£10,509k excluding the ecoDepot).
3. The outturn for the 2006/07 Capital Programme was £19,252k (£9,915k excluding the ecoDepot), an underspend of £312k against the budget. This represents an underspend of approximately 2% against the budget (5.7% on the programme excluding the depot). The underspend is principally due to the late commencement of schemes in the structural maintenance area to reduce traffic disruption and the planned delay on the City Walls Robin Hoods Tower scheme to enable it to be funded over two years.
4. During 2006/07, 109 schemes were completed, feasibility and design work was carried out on 113 schemes, and seven schemes were ongoing at the end of March. Over 1200m of off road cycle route was constructed, 4 sets of traffic signals introduced, 5 city space information points installed, 9.5km of carriageway resurfaced and 13km of footway rebuilt.
5. There has been a substantial amount of work delivered in the year including the construction of James Street link road to relieve congestion on the inner ring road and provide access to the Foss Islands developments, provision of infrastructure improvements for the introduction of the ftr, construction of traffic signals at Crockey Hill and York Road, Dunnington to improve safety and provide better access to the principal road network, relocation of the Park & Ride pick up point at the Designer Outlet to reduce journey times and provide better access to facilities. In addition further technology has been introduced to manage traffic and provide real time public transport information.
City Strategy Capital Programme 6. Progress on the major elements of the programme is set out in more detail in the following sections. Schemes that are funded from the Local Transport Plan are considered first, followed by schemes funded from other sources.
7. A scheme by scheme review of progress is set out in Annex 1, which shows the scheme status at the end of March 2007. Progress on schemes since the end of the financial year is also shown where appropriate.
Schemes within the Local Transport Plan OUTER RING ROAD AND JAMES ST LINK ROAD Programme: £2,906k (£1,563k LTP, £1,343k s106) Outturn at 31st March 2007: £2,405k
8. A64 Hopgrove Roundabout (OR01/05). The Highways Agency developed a scheme in partnership with the council to enhance the capacity of the junction. Although the scheme was endorsed by City Strategy EMAP on 30 October 2006, it has been delayed because the estimated costs now exceed the £5m threshold for Highway Agency regional schemes. The proposals are being reviewed but, unless the scheme can be redesigned to be within the £5m threshold, it will have to be considered as one of the Targeted Programme of Improvements national schemes which may substantially delay delivery. Confirmation of the latest position is awaited from the Highways Agency.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.