Advice of the Advisory Panel That the Executive Member for City Strategy be advised to: 1. Approve the carryover schemes and adjustments set out in Annexes 1 and 2 of the report. 2. Approve the increase to the 2007/08 City Strategy Capital budget subject to the approval of the Executive. Decision of the Executive Leader for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City 16 July 2007 Strategy and Advisory Panel Report of the Director of City Strategy
CITY STRATEGY CAPITAL PROGRAMME 2007/08 – CONSOLIDATED REPORT Summary 1. The purpose of this report is to consolidate the 2007/08 City Strategy Capital Programme to include the carryover schemes that were not completed in 2006/07, and to make adjustments to schemes and blocks to reflect individual underspends and overspends within the programme. The report asks the Executive Member for City Strategy to approve the amendments to the 2007/08 budget as set out below.
Background 2. The City Strategy Capital Programme budget for 2007/08 of £8,777k was agreed by the Executive Member in March 2007, and includes the Local Transport Plan Capital Programme allocation of £5,560k, and other elements allocated funds through the Council’s budget process. These figures do not include overprogramming, which was set at £269k in the 2007/08 budget report.
3. The 2006/07 capital programme contained a level of overprogramming of £2,883k at the consolidated report stage of 2006/07 to give some flexibility in the programme should slippage in some schemes occur. Following minor revisions at the Monitor 1 stage, the full programme agreed by Members at the Monitor 2 report in December 2006 was £10,710k (£19,765k including the ecoDepot) with a budget of £10,508k (£19,563k including the ecoDepot). There was therefore £202k worth of work outstanding that could not have been funded by the LTP in 2006/07.
4. For this reason it was necessary when planning the 2007/08 programme in early 2007 to take account of schemes that would slip from 2006/07 due to budget constraints.
5. As reported to Members in June, the outturn for the 2006/07 capital programme was £9,914k (£19,252k including the ecoDepot). This represents an underspend of £594k against the budget of £10,508k. Following the use of £125k to pay back part of the venture loan used to set up the Street Environment Service, there was £469k of funding available to carry forward into 2007/08.
6. The carryover and new schemes that have been added to the 2007/08 programme are detailed below, along with budget alterations for existing schemes where changes to the scheme cost have been identified. It is proposed to fund schemes by using the carried over funds from 2006-07, the introduction of new funds or increasing the level of overprogramming.
7. The key changes included in this report are summarised in Annex 1, and the current and proposed budgets for each scheme are shown in Annex 2.
City Strategy Capital Programme 8. Moor Lane Roundabout (OR01/06) - £3,000k. As this scheme is progressing faster than originally anticipated, it is proposed to increase the allocation for this scheme in 2007/08 to £3,150k by bringing forward £150k of the £193k 2008/09 budget allocation for this scheme. The total scheme budget over three years remains unchanged at £3,500k.
9. Works commenced on 30th April, and the site has been substantially cleared and the site compound set up. Good progress has been made on the initial works to the east of the A1237 including the formation for the new Moor Lane link.
10. Hopgrove Roundabout (OR01/05). It is proposed to allocate £482.7k of Section 106 funding for this scheme, made up of £76.7k of carryover Section 106 funding from 2006/07, and £406k of Section 106 funds which have been received from developments in the Foss Basin Masterplan area. These contributions are being used to ‘payback’ the LTP which was used to part fund the James St. Link Road. As reported to Members in March, the Highways Agency improvements at the A64 Hopgrove Roundabout have been delayed due to increased scheme costs, which may require the scheme to be assessed at a national rather than regional level if the scheme cannot be redesigned to reduce costs. This allocation will ensure that funding for the CYC contribution to this scheme is available if the scheme is progressed in 2007/08.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.