Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 24 July 2007. Below is the council's own wording, with the papers it was decided on.
(i) That the contents of the report and the progress of the accommodation project to date be noted; (ii) That the revised business case for the project that supports the outcomes of the feasibility study, detailed in paragraph 42 of the report, be approved. REASON:To update the Executive on progress achieved and to monitor the project effectively. (i) That the contents of the report and the progress of the accommodation project to date be noted; (ii) That the revised business case for the project that supports the outcomes of the feasibility study, detailed in paragraph 42 of the report, be approved. REASON:To update the Executive on progress achieved and to monitor the project effectively.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Meeting of the Executive 24th July 2007
Report of the Director of Resources
Accommodation Project - Update Summary 1. This report provides a progress update of the council’s corporate accommodation project, which includes the targets and achievements for the period October 2006 to June 2007.
2. The main focus of the report is the outcomes from the Hungate feasibility study, a key area of activity during this reporting period. The study demonstrates how a level of further investment will improve the overall business case for the project and provide further benefits particularly in relation to sustainability and the future use of the building. It sets out the top ten project risks and how these continue to be managed and seeks Member approval to a revised business case for the project.
Background 3. At the Executive meeting on 22nd November 2005, Members approved the overall business case to rationalise the council’s administrative accommodation portfolio and to provide a new city centre administrative headquarters, incorporating a one-stop customer centre on the Hungate development site.
4. The key components of the project are:
• The land assembly at the Hungate site, including the relocation of the Peasholme Centre and the ambulance station, the closure of the Haymarket car park, and archaeological investigations,
• the property exit strategy including the sale of existing freehold premises and land, and the extension and/or termination of existing lease arrangements,
• the design and construction of both the new administrative headquarters at Hungate and the Peasholme Relocation Centre,
• ICT connectivity to the new premises, the reorganisation of the ICT network to two principal data sites, and the decommissioning of all of the vacated sites. • a review of the current facilities management (FM) arrangements, and the formulation and implementation of a central FM service for the new accommodation,
• a future business needs study to inform the user brief for the new accommodation and the associated development and implementation of future accommodation occupancy arrangements.
Progress To Date 5. The project has been divided into stages with progress being reported at key stages/milestones. The following covers the period since the last Executive report in October 2006 to June 2007.
6. The targets and achievements for this period were as follows.
Relocation Of The Ambulance Station 7. The Ambulance Service has indicated that a contingency plan has been formulated enabling them to commit to vacate Hungate in time to meet the councils overall project timetable. Their preferred relocation site is at Clifton with Yearsley Bridge as a fall back option. Following unfavourable feedback from Planning to their Clifton proposal, a further meeting has been arranged in July to clarify their current position.
New Hostel – Planning Consent 8. Planning consent has been granted for the new hostel at Fishergate and Allerton Construction Ltd, the lowest tender has been appointed as the constructor. The construction phase will start in July 2007 for a period of 40 weeks.
9. The Fishergate business unit has been successfully relocated to a temporary home at Hospital Fields Road, prior to its permanent relocation to Amy Johnson Way.
Archaeological Investigations 10. Archaeological investigations have now commenced on the council’s Hungate site and the outcomes to inform the strategy for the construction of the new building are due to be reported in July. Early indications suggest that there is nothing of significance on the site that will warrant anything other than a watching brief during the construction phase of the project.
Extension Of Existing Leases 11. All leases, with the exception of Mill House, have now been extended following negotiations with the landlords. Leases have been granted which meet both the timescales and cost profiles in the project plan. Legal Services are currently working to secure an extended lease for Mill House.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.