Accommodation Project - Update Report

Noted Executive 2 papers

Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 20 July 2010. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

(i) That the report be noted. (ii) That the ongoing communication with the public, through the Council’s website, Your City and e-mail, be noted. (iii) That it be requested that the business case for the financial benefit of the project be included in future communication. REASON: To ensure that the benefits of the project, particularly in terms of long-term financial savings, can be clearly communicated to the public. (iv) That the property exit strategy, and the release of De Grey House and 1A & B Swinegate Court East on the first break clause dates of March and May 2011, with affected staff to be relocated to within the existing accommodation portfolio, be endorsed, and that an updated report be brought to Executive within three months detailing the break clause in leases, tendering process for dilapidation works and the minimisation of the period of time between departure from office and the end of the Council’s lease on the building. REASON: In order to vacate the premises and re-locate staff within the project’s financial model and with minimal disruption and risk to Council services. (v) That the Director of City Strategy detail to the Leader any costs arising from the objection by the Victorian Society. REASON: To assess the financial effect on the project of this late intervention in the planning process by a statutory consultee. (i) That the report be noted. (ii) That the ongoing communication with the public, through the Council’s website, Your City and e-mail, be noted. (iii) That it be requested that the business case for the financial benefit of the project be included in future communication. 1 REASON: To ensure that the benefits of the project, particularly in terms of long-term financial savings, can be clearly communicated to the public. (iv) That the property exit strategy, and the release of De Grey House and 1A & B Swinegate Court East on the first break clause dates of March and May 2011, with affected staff to be relocated to within the existing accommodation portfolio, be endorsed, and that an updated report be brought to Executive within three months detailing the break clause in leases, tendering process for dilapidation works and the minimisation of the period of time between departure from office and the end of the Council’s lease on the building. 2 REASON: In order to vacate the premises and re-locate staff within the project’s financial model and with minimal disruption and risk to ... view the full minutes text for item 35.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 20th July 2010

Report of the Director of City Strategy

Accommodation Project - Update Report Summary 1. This report:

• Provides an accommodation project update which includes the planning decision for the new offices at West Offices, Station Rise; the outcomes from the Office of the Future pilot study; the project’s current financial status; the timeframe moving forward and the current level of risk.

• Sets out the property exit strategy and seeks Members’ endorsement of the property exit strategy to vacate De Grey House and 1A and B Swinegate Court East in March and May 2011 respectively.

• Seeks Members agreement to an increase in the use of the Venture Fund to £2.13m to fund the projects Early Years Deficit.

Background 2. The accommodation project and the move to a new headquarters building is a key component of the council’s ‘More for York’ improvement and efficiency programme. The project remains on track to be delivered within the approved capital budget of £43.8m, over time the new accommodation will make savings measured against the current accommodation and will also achieve the full range of benefits:

3. For the customer, in providing a purpose built York Customer Centre that will be fully flexible, accessible and compliant with the Disability Discrimination Act (DDA) and provide the single most important focal point for the new headquarters building. The new customer facility will enable quick, simple and easy access to the full range of council services in one place, in a modern customer environment that supports the delivery of the council’s customer strategy. (Customer access principles to be used in the new Customer Centre will be trialled in the current Library Square reception prior to the final move to the new HQ).

4. For the environment, the new headquarters will be sustainable in terms of its economic, social and environmental impact. Its central location will support the vitality of the city centre, as well as supporting the existing infrastructure and transport links for customers, visitors and the large volume of staff walking or cycling to work. The new headquarters building is designed to deliver a 70% reduction in carbon emissions compared to the council’s current accommodation. In terms of energy efficiency it aims to be 41% better than our current accommodation and is set to deliver 84% renewable energy, to reduce the future running costs of the building. The proposal is performing well beyond similar existing buildings and due to the highly efficient building services, out-performing typical newly built premises.

5. For the business, in providing a modern working environment to support an effective and efficient business operation. Rationalising 16 administrative offices down to four will achieve long-term savings and fund the cost of the new headquarters building, at no additional cost to the residents of York. The new headquarters will provide the potential to share space with partner organisations to support and improve partnership working and support more collaborative working between services, resulting in a more joined-up and efficient delivery to customers.

6. For the City, by providing the opportunity for inward investment to the city by releasing a number of important historic buildings which can be sensitively restored and put to more appropriate use such as Blake Street which has undergone a complete refurbishment and is now the new ‘Visit York’ information centre.

7. At the Executive meeting on 15th December 2009 Members approved West Offices, Station Rise as the preferred site for the council’s new headquarters building and granted the Director of City Strategy the delegated authority to enter into a contract with Tarras Park Properties York Investors LLP (Tarras) following agreement of the final terms of the Conditional Sale and Development Agreement and the satisfactory resolution of any outstanding items of clarification.

Progress

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Accommodation Project: Update ReportReport 144 KB DownloadRead as text
PDF
Accommodation Project UpdateAppendix 1 54 KB Download

At this meeting

Whole meeting

Who was there

7 of 10 attended
AW
Councillor Andrew WallerChair, present
NA
Councillor Nigel AyreCommittee Member, present
SG
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
DM
Councillor Dave MerrettAttendee, in attendance
PH
Councillor Paul HealeyAttendee, in attendance
SW
Councillor Sian WisemanAttendee, in attendance

On this subject at York

Search all
  1. Accommodation Project - Update ReportThis decision
  2. Accommodation Project - Update ReportNoted
  3. Accommodation Project - Update ReportApproved
  4. Accommodation Project - Update ReportApproved
  5. Administrative Accommodation Project Financial UpdateNoted
  6. Administrative Accommodation Project Financial UpdateApproved

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open