Housing and Adult Social Services Capital Programme 2007/08 Monitor 1
ApprovedCommittee3 papers
Housing and Adult Social Services Advisory Panel approved this item on Monday 10 September 2007. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Members for Housing and Adult Social Services be advised to i) Note progress made on schemes ii) Approve the variations listed in Table 1 (Repairs to Local Authority Properties) and Table 2 (Modernisation of Local Authority Homes) iii) Refer the schemes in Table 3 (Social Services) and referred to in paragraph 19 to the Executive for approval iv) Note minor variations made under officers delegated authority and the officer specification recommendation in relation to combination central heating boilers referred to in paragraph 13 Decision of the Executive Members for Housing and Adult Social Services
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Housing and Adult Social Services Advisory Panel
HASS32
Meeting of the Executive Members for Housing and Adult Social Services and 10 September 2007 Advisory Panel Report of the Director of Housing and Adult Services
Housing and Adult Social Services Capital Programme 2007/08 Monitor 1 Summary 1. This report presents the first quarter review of the 2007/08 Housing and Social Services Capital Programmes and the resources available to support them. The report also recommends that the Executive Members approve the variations.
Background 2. The approved Housing Capital Programme for 2007/08 is £9,131k with £4,685k funded through the MRA. The approved Social Services Capital Programme for 2007/08 is £221k. Annexes 1 and 2 set out the programmes in detail.
3. Officers have reviewed the programme of investment projects during the first quarter of 2007/08 and the resources needed to fund them. Any minor variations have been agreed within delegated powers.
Consultation 4. There has been no consultation carried out to produce this report.
Housing Capital Programme Modernisation of Local Authority Homes (Capital Scheme)
5. There have been minor variations resulting in a projected increase in expenditure of £24k, this is made up of increases of £22k in window replacement and £2k in Sheds & Garages. Table 1. Repairs to Local Authority Properties, Scheme Approved Revised (Under)/Over Budget Costs 2007/08 spend 2007/08 £000k 2007/08 £000k £000k Installation and 1,481 1,712 231 Replacement of Heating Systems 6. There is a major variation resulting in a projected increase in expenditure of £231k within the Installation and Replacement of Heating Systems project. This is as a result of large numbers of predominantly old back boiler units failing their annual gas service. These boilers are due for replacement within the current 4 year capital programme and hence this work is not additional to the programme but is simply being brought forward into a larger 2007/08 project. A number of additional operational processes have been brought into place to monitor and manage this process. Assistance to Older & Disabled People 7. There has been a minor variation resulting in a projected increase in expenditure of £10k on the Council Adaptations project. Housing Grants & Associated Investment 8. There has been minor variations resulting in a projected increase in expenditure of £48k, this is made up of increases of £8k on Mandatory Disabled Facilities Grants and £2k on the York Repair Grant and a projected decrease in expenditure of £2k on Decent Homes Grants. A new £40k security grant has been established and funded from within existing grant income. Table 2. Modernisation of Local Authority Homes (MRA Scheme),
9. There were 23 properties on Dodsworth Avenue that had been included in the Tang Hall programme to receive partial TC works due to the age of their electrical wiring and boilers. Upon survey it became clear that the good condition of the wiring and boilers meant that the properties did not fail decent homes (elements must be old and in poor condition). Under the York Standard of whole house modernisation at this point should the wiring and heating have been modernised the kitchen and bathroom’s were not of an age to warrant works and these customers would have had to be revisited and disturbed again for another future modernisation.
10. It is therefore recommended that the properties in Dodsworth Avenue are monitored over time to a point where whole house modernisation is considered appropriate in order to reduce unnecessary works and disruption. This would result in a reduction in expenditure of £174k on the Tang Hall project. The 6 customers who were visited regarding potential works have been informed of this, the remaining 17 customers had not been informed of any potential works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing and Adult Social Services Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.