Final Report for Part B of the Highways Maintenance Procurement and PFI Ad-hoc Scrutiny Review

Agreed Scrutiny 6 papers

Customer and Corporate Services Scrutiny Management Committee agreed this item on Monday 25 February 2008. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

(i) That Members agreed the following findings of the Highways Maintenance Ad-Hoc Scrutiny Committee: · There had been an impact on the repayments to the Venture Fund caused by the delays in implementing the actions agreed as part of the Best Value Review. · The delays were not unnecessary · The total savings made in Highways Maintenance since the Best Value Review are significantly higher than those identified therefore there has been no financial loss to the Council caused by the delays in the procurement process. (ii) That a report be prepared for the Executive showing the findings of this Scrutiny Review. 1
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Customer and Corporate Services Scrutiny Management Committee

Scrutiny Management Committee 25 February 2008

Final Report for Part B of the Highways Maintenance Procurement & PFI Ad-hoc Scrutiny Review

Background 1. At its meeting in September 2006, Scrutiny Management Committee (SMC) agreed to proceed with a review of topic No.135 into Highways Maintenance Procurement and the PFI bid. The issues raised within the registered topic were split into parts A & B. At a meeting of SMC in March 2007 the final report for Part A was presented and the following remit for Part B of this review was agreed:

Aim

2. To examine how the Council can fund the PFI and gain an understanding of the alleged financial loss to the council caused by delays in the procurement process since 2003.

Objectives

3. The above aims to be achieved through the following objectives:

A. To examine the financial information that was provided to Urgency Committee in September 2006 including the key financial risks highlighted within the report

B. To investigate the figures included in the report which advised Members to go ahead with the PFI approach to Highways Maintenance Procurement

C. To compare the actual cost to the Council since 2003 in respect of Highways procurement to the costs originally included in the Best Value Review of 2001

4. In 2001 when the Best Value Review was originally considered, 7 proposals were made and a decision was taken to implement the following 2 options:

Option 1 - To improve the efficiency of the current system

Option 2 - Change the basis of contractual arrangements and extend the scope of the mixed economy of service provision that currently exists 5. In order to achieve these options, 11 improvement objectives were identified:

• Produce a Highways Maintenance Management Plan. • Review the current approach to managing and planning the service. • Develop an operating culture of ‘Right First Time’. • Increase the customer orientation of the service. • Improve the quality of financial information. • Further improve the efficiency and effectiveness of staff who deliver the service. • Develop procurement practices and partnership working. • Review the remit of the Highways Maintenance Service. • Raise the profile and understanding of the service and develop understanding of customer needs. • Increase the quality of the finished product delivered. • Further increase and improve knowledge of the highway asset.

Consultation 6. This review was progressed in consultation with the Assistant Director of City Development & Transport and other key officers in City Strategy.

Objectives A & B To examine the financial information that was provided to Urgency Committee in September 2006 including the key financial risks highlighted within the report

To investigate the figures included in the report which advised Members to go ahead with the PFI approach to Highways Maintenance Procurement

Information Gathered

7. At a meeting in June 2007, officers provided detailed information (see Annex A) on the following:

• Clarification on the outcome of the Best Value Review (BVR) • Table showing the cashable efficiencies gained as a result of the BVR • Budgets for highways maintenance from 2002 to 2007 • Comparison of the staffing resources of 2004 and 2007, associated with the provision of highway maintenance

8. This together with the financial information previously presented to Urgency Committee in September 2006 (see Annex B), was used to support Members during their investigation of the first two objectives of this review.

9. In October 2007, Members received information on work which was ongoing to benchmark the whole of the Highways Maintenance Service (see Annex C) together with a verbal update in relation to the Council’s Expression of Interest (EOI). Issues Arising

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 35 KB Download
PDF
Appendix BAppendix B 77 KB Download
PDF
Appendix CAppendix C 45 KB Download
PDF
Appendix DAppendix D 35 KB Download
PDF
Appendix EAppendix E 38 KB Download
PDF
Final Report for Part B of the Highways Maintenance Procurement and PFI Ad-hoc Scrutiny ReviewReport 53 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
JG
Councillor John GalvinChair, present
PB
Councillor Paul BlanchardVice-Chair, present
MK
Councillor Madeleine KirkCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
DS
Councillor David ScottCommittee Member, present
TS
Councillor Tracey Simpson-LaingCommittee Member, present
DT
Councillor Dave TaylorCommittee Member, apologies
RW
Councillor Richard WatsonCommittee Member, present
AD
Councillor Andy D'AgorneSubstitute, present as substitute

On this subject at York

Search all
  1. Final Report for Part B of the Highways Maintenance Procurement and PFI Ad-hoc Scrutiny ReviewThis decision
  2. Called-In Item: Traffic Congestion Final Report Part 1Noted
  3. Called-in Item: Traffic Congestion Final report Part 1Approved
  4. Traffic Congestion Final Report Part 1Noted
  5. Review of Highways Maintenance (Part B) – Draft Final ReportDecided

More from York Customer and Corporate Services Scrutiny Management Committee

All decisions
MeetingDecisionOutcome
6 Mar 2023 Minutes (5.32 pm)That the minutes of the meeting of the committee held on 9 January 2023 be approved and signed as a correct record. T... Approved Open
6 Mar 2023 City Centre Access (5.41 pm)i. that the ongoing work to improve access to the city centre be noted. ii. That the change to the rules relating to ... Noted Open
6 Mar 2023 Customer Centre Telephone Performance Update (6.48 pm)i. That the report be noted. ii. Call data relating to Housing, Adult Social Care and direct dial calls to officers b... Noted Open
6 Mar 2023 York and North Yorkshire Devolution Update (7.10 pm)that the update be noted. Reason: to ensure the Committee had oversight of the Devolution process. Noted Open
6 Mar 2023 Work Plan (7.29 pm)i. That the Work Plan be noted. ii. That s106 agreements be added to the future Work Plan. Reason: To ensure the Comm... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies