That the progress made in implementing the audit recommendations, as reported in paragraphs 7 to 12 and verbally at the meeting, be noted, with thanks to the relevant Officers. REASON: To fulfil the role of this Committee in providing independent assurance on the Council’s control environment.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Assistant Director (Audit and Risk Management)
Follow Up of Internal Audit Recommendations
Summary 1. This report sets out the progress made by departments in implementing those agreed audit recommendations which were due to have been implemented by 29 February 2008.
2. The report also includes a summary of progress made in addressing the implementation of the recommendation made in the Youth Services audit regarding Criminal Records Bureau (CRB) checks and recommendations made as part of the Car Parking audit 2007/08, for which Members requested that a priority follow up was conducted.
Background 3. In June 2006, the Audit and Governance Committee approved the process to be followed in reviewing and reporting on progress made by service departments in implementing agreed internal audit recommendations. In accordance with this process reports are brought to Committee for Members consideration every six months setting out progress, together with details of any outstanding recommendations that require referral to the Committee for further action. This report is based on follow up work by the Internal Audit Service. All recommendations are reviewed once their agreed implementation date has passed. The review is carried out using a combination of questionnaires completed by departments, risk assessment, and by further detailed examination by Internal Audit where appropriate.
Consultation 4. Details of the findings of follow up work have been discussed with the relevant service managers and chief officers.
Follow Up of Recommendations 5. A total of 158 recommendations were followed up as part of this review. A summary of the priority of these recommendations is included in figure 1, below. Figure 1: Recommendations followed up as part of the current review Priority of No. of Recommendations Recommendations Followed Up 1 (High) 5 2 (Medium) 97 3 (Low) 56 Total 158
6. Figure 2 below provides an analysis of the recommendations which have been followed up, by Directorate. Figure 2: Recommendations followed up by Directorate No. of Recommendations Followed Up by Directorate Priority of Chief City HASS LCCS Resources Neighbourhood Recommendations Executives Strategy Services 1 (High) 0 0 0 3 1 1 2 (Medium) 1 6 0 73 14 3 3 (Low) 4 2 0 39 10 1 Total 5 8 0 115 25 5
7. Of the 158 recommendations, 5 (3%) had been superseded (for example by business developments or because of cessation of service). Of the remaining recommendations, 133 (84%) had been satisfactorily implemented.
8. In 20 cases (13%), the recommendations had not been implemented (although progress had been made in some cases). These were referred back to the relevant service manager or assistant director. Following this, a revised implementation deadline has been agreed. These will be followed up again after the revised deadline, and if necessary will proceed to the next stage of the approved escalation procedure.
Youth Services CRB Checks 9. During the 2007/08 Youth Services audit, it was identified that CRB checks were not being carried out for all staff working with young people. Therefore a recommendation was made that all current staff needed to have a check made, and that in future new staff should not be allowed to start work without having had a check carried out.
10. In January 2008, when this recommendation was reported to Members of the Audit & Governance Committee, a request was made that Internal Audit carry out a priority follow up to establish whether progress had been made in this area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.